Atlanta streetcar construction traffic update



Download 18.74 Kb.
Date conversion16.08.2017
Size18.74 Kb.
atlanta streetcar - atlanta, ga

December 20, 2013



ATLANTA STREETCAR CONSTRUCTION TRAFFIC UPDATE

Effective Week of December 23, 2013

Construction is progressing on the Atlanta Streetcar Project with Guideway construction underway. We are pleased to announce the partial re-opening of several key streets:

  • The westbound lane of Luckie Street between Fairlie and Spring has re-opened



  • The east and west bound lanes of Luckie between Spring Street and Centennial Olympic Park



During the week of December 23rd there will be limited Streetcar work underway, please remain alert when in the construction zone area. Thank you for your continued patience, please see the update below. Happy Holidays!

East Loop Construction Notifications issued week of December 16, 2013

  • NONE



Central Loop Construction Notifications issued week of December 16, 2013

  • NONE

West Loop Construction Notifications issued week of December 16, 2013

  • NONE

Page 2

Atlanta Streetcar Traffic Construction Update

Effective: December 23, 2013

The following Construction Notifications remain in effect in the East Loop:

  • Effective June 3, 2013 - Installation of the foundations for the Overhead Catenary System (OCS) on Edgewood and Auburn between Jackson and Fort Streets



  • Effective July 18, 2013 – Guideway Construction – Lane and Sidewalk Closure – Fort to Auburn and Auburn between Fort and Bell Streets



  • Effective July 19, 2013 - Guideway Construction - Lane and Sidewalk Closure - Fort Street between Edgewood and Auburn and Auburn between Fort and Bell



  • Effective through October 10, 2013 - Full Street and Sidewalk Closure on Auburn between Bell Street and Fort Street including Bell Street intersection – EXTENDED



  • Effective through October 29, 2013 - Lane and Sidewalk Closure on Auburn between Peachtree and Fort - EXTENDED

The following Construction Notifications remain in effect in the Central Loop:



  • Notification of Pending Water Service Interruption – Park Place between Auburn Avenue and John Wesley Dobbs



  • Notification of Pending Water Service Interruption – Auburn Avenue between Peachtree Center and Park Place





  • Effective May 20 – October 20, 2013 – Lane and Sidewalk Closure on Edgewood between Piedmont and Bell for Guideway construction – EXTENDED



  • Effective May 22 – October 10, 2013 – REMINDER – Lane, Sidewalk and Parking Meter Closure Edgewood between Fort and Courtland – EXTENDED



  • Effective June 17 – October 10, 2013 – Lane and Sidewalk Closure – Edgewood between Piedmont and Park Place - EXTENDED





Page 3

Atlanta Streetcar Traffic Construction Update

Effective: December 23, 2013

  • Effective July 31, 2013 – Guideway Construction – Lane and Sidewalk Closure – Auburn between Piedmont Avenue and Peachtree Center Avenue



  • Effective August 1, 2013 – Guideway and Overhead Catenary System Lane and Sidewalk Closure – Auburn Avenue between Peachtree Center Avenue and Park Place

  • Effective August 1, 2013 – Guideway and Overhead Catenary System Lane and Sidewalk Closure – Auburn Avenue between Peachtree Center and Peachtree Street




  • Effective August 5, 2013 – Overhead Catenary System – Lane and Sidewalk – Park Place to Edgewood to Hurt Plaza





  • Effective through October 29, 2013 - Lane and Sidewalk Closure on Auburn between Peachtree and Fort - EXTENDED

The following Construction Notifications remain in effect in the West Loop:

  • Effective August 1, 2013REMINDER NOTIFICATION – Guideway and Overhead Catenary System Lane and Sidewalk Closure – Centennial Olympic Park to Luckie Street and Luckie Street to Peachtree Street

  • Effective August 15, 2013 – REMINDER NOTIFICATION – Guideway Construction Street Closure and Intermittent Sidewalk Closure – Luckie Street between Centennial Olympic Park and Peachtree Street

  • Effective through October 10, 2013 – Road Closure on Andrew Young between Centennial Olympic Park and Williams Street – EXTENDED

  • Effective through September 15, 2013 – Lane Closure on Luckie Street – EXTENDED




  • Effective thru September 29, 2013 – Street and Intermittent Sidewalk Closure on Luckie Street between Centennial Olympic Park Blvd. and Spring Street - EXTENDED



Other Streetcar work on the East Loop during the week of December 16 includes:

Other Streetcar work on the Central Loop during the week of December 16

  • Water Main Work on Auburn between Park Place and Peachtree Street inclusive of Lane and Sidewalk Closure

Page 4

Atlanta Streetcar Traffic Construction Update

Effective: December 23, 2013



Courtland Street

Other Streetcar work on the West Loop during the week of December 16 includes:

  • None