Compliance is mandatory



Download 3.19 Mb.
Page36/61
Date16.08.2017
Size3.19 Mb.
#33131
1   ...   32   33   34   35   36   37   38   39   ...   61

10.5Continuous Inspection

      1. Inspections are the cornerstone of facilities maintenance management. They identify needed maintenance work, provide feedback on the effectiveness of the facilities maintenance program, and form the basis for changes to the program. NASA Centers should continuously assess facility conditions in a manner that results in the identification and quantification (in terms of dollars) of the repair needs that will address the deferred maintenance.

      2. General Inspection Requirements

        1. During an inspection, if the inspector uncovers unsafe conditions, the inspector shall notify the individual in charge of the operation and determine whether people and/or property are in imminent danger. If so, there should be a strong consideration by the operator to cease operations until corrective action is taken. The Center’s safety office shall be notified of the situation as soon as possible.

        2. Safety is recognized as a leading value in the maintenance process and, therefore, an important part of the inspection program. Facility and equipment deficiencies identified in the continuous inspection program will be evaluated for failure and failure consequences (risk assessment) to identify safety impacts.

        3. Centers should develop a procedure for performing and documenting risk assessments of deficiencies identified in the continuous inspection program, for notifying the Center’s safety office of any safety deficiencies, and for ensuring that the deficiencies are made safe.

      3. Inspection Types. A Center’s continuous inspection program should include the following:

        1. Predictive Testing & Inspection. PT&I uses advanced technology to sense building, electrical equipment, and machinery operating characteristics, such as vibration spectra, temperature, noise, and pressure and to compare the measured values of these characteristics with historical data or other preestablished criteria to assess the items’ conditions. PT&I permits condition-based rather than time-based initiation of the maintenance effort to correct any problems identified. Evaluation of the PT&I data can be used to project future maintenance requirements for inclusion in the AWP or Five-Year Plan. See Chapter 7, Reliability Centered Maintenance, for additional information about PT&I.

        2. Preventive Maintenance. Inspections are a major part of preventive maintenance and are performed on a time- or other interval-based schedule, normally using prespecified checklist items. These inspections may include minor adjustments and minor repairs (no larger in scope than TCs) of equipment included in a PM program. The inspection results should include a condition assessment documented in the Center’s CMMS for use in projecting future maintenance requirements. PMs typically cover untended equipment.

        3. Operator Inspections. Operator inspections are the examinations, lubrication, minor repairs (no larger in scope than TCs), and adjustments of equipment and systems that have an operator assigned. Typically, they apply to equipment or systems such as those in a central utility plant. Operators should provide condition assessments for documentation in the CMMS.

        4. Facility Manager/Management Inspection. Periodic inspections should be performed by the Facility Manager. These inspections should include common spaces, hallways, equipment rooms, roofs, grounds, and other areas not covered by individual facility users. Users of private spaces, such as offices, should be evaluated as described in paragraph 10.5.3.5, Facility User/Occupant Inspection. The facility manager should document the facility condition on, at least, a semiannual basis.

        5. Facility User/Occupant Inspection. The facility user should be surveyed on a semiannual basis. The user’s inspection input could be reported on a form such as the one shown in Figure 10-1. This is in addition to the facility manager’s inspection. Figure 10-2 should be printed back-to-back with the Figure 10-1 form to ensure that the facility user’s input can be coded into the CMMS for data integration and analysis.




Figure 10-1 Facility User Inspection
Circle a number from the two furthest-left columns to identify which item failed.

Circle a letter from the right column to identify how item failed.



Which Equipment?

P
DISCREPANCY?

A. Broken

B. Burned out

C. Damaged

D. Disconnected

E. Faulty Ground

F. Flood

G. Gas smell/leak

H. Leak

I. Loose


J. Low level

K. Low/No charge

L. Missing

M. No hot water

N. No insulation

O. No power

P. Noisy

Q. Out of adjustment

R. Out of setting

S. Overflow

T. Plugged

U. Smoke/odor

V. Stuck open/closed

W. Tripped

X. Spill

Y. Fell off

Z. Programming

AA. Contamination

AB. Other

Specify
LUMBING
HVAC

(1–15) (20–25)

1. Urinal 20. Control

2. Toilet 21. Thermostat

3. Water line 22. Filters

4. Valve 23. Duct

5. Faucet 24. Refrigerant

6. Fuel line 25. Steam Trap

7. Sewer


8. Steam BUILDING TRADES

9. Storm (40–61)

10. Natural Gas line 40. Door

11. Fire Sprinkler 41. Window

12. Irrigation 42. Hinge

13. Heater 43. Lock

14. Pump 44. Handle/Knob

15. Container 45. Push/pull gate

46. Stops

ELECTRICAL 47. Glass

(70–83) 48. Closures

70. Switch 49. Ceiling/floor tiles

71. Outlet 50. Carpet

72. Panel 51. Partitions

73. Fixture 52. Ext. Bldg.Struct.

74. Light (lamp) 53. Signs

75. Ballast 54. Asphalt

76. Battery 55. Concrete

77. Wiring 56. Fencing

78. Breaker 57. Curbs

79. Conduit 58. Shop equipment

80. Timer 59. Steps

81. Cords 60. Wall

82. Transformer (isol.) 61. Vehicle equip.

83. Other



Specify
Figure 10-2 Equipment/Discrepancy Classification Form
      1. Inventory. The facilities and equipment inventory is the baseline for what is inspected and maintained. The inventory should permit identifying inspected items, items subject to PM inspection, and items subject to operator inspection. Chapter 3, Facilities Maintenance Management, discusses facilities and equipment inventories.

      2. Frequency of Inspection

        1. As the name implies, continuous inspections should be ongoing, with all facilities and equipment inspected periodically. The frequency of inspection depends on a number of factors, including the following:


  1. Importance of the facility.

  2. Legal or regulatory requirements.

  3. Likelihood of condition changes since the last inspection.

  4. Safety considerations.

  5. Availability of inspection resources.
        1. Table 10-1 provides suggested inspection intervals for a number of facilities and systems. These apply to facilities and equipment under average conditions supporting routine operations. Centers should adjust the frequencies to suit local conditions, regulatory requirements, known equipment conditions as a result of PM and PT&I, operational requirements, and user inputs.

      1. Inspection Procedures. Preparing for and conducting an inspection involves many of the following steps, some of which may not apply in the case of PM inspections and operator inspections:


  1. Identify the items to be inspected, based on the inventory.

  2. Obtain the facility or equipment history. This includes information on completed and pending work orders, as well as the results of past inspections and the current use of the facility or equipment.

  3. Review the applicable physical condition standards with a view toward the planned use of the facility or equipment. (Facilities or equipment scheduled for disposal or deactivation normally will have lower maintenance standards.)

  4. Identify planned changes to the configuration and use of the facility or equipment.

  5. Identify the inspector skills, specialized tools, and equipment required for the inspection.

  6. Schedule the inspection and set the inspection route, considering the operational requirement for the facility, the availability of inspectors, and related factors. Factors such as safety certification requirements, mission criticality, observed rate of deterioration or condition change, and system availability determine inspection schedules and frequency.

  7. Conduct the field inspection and document the conditions found, includes noting of appropriate asset identification (ID) tags. The documentation should be a clear and concise presentation of the conditions found and permit determining and estimating corrective action. (Serious and safety-related deficiencies shall be entered into the work control system for immediate action.)


Item Inspected

Interval (years)

1. Antenna-supporting Towers & Masts

2

2. Boilers and Water Heaters

1

3. Bridges

2

4. Building Structure

3

5. Building Electrical Systems

2

6. Bulk Fuel Storage

2

7. Cathodic Protection Systems

0.5

8. Chimneys and Stacks

2

9. Drainage and Erosion Control

1

10. Dredging and Moorings

3

11. Electrical Distribution Systems

1

12. Electrical Vaults, Manholes

1 or 2, determined by site location

13. Elevators, Lifts, and Dumbwaiters

1

14. Exhaust Systems

1

15. Explosive Storage Buildings

2

16. Explosive Building Grounding Systems

0.5

17. Fences and Walls

2

18. Fresh Water Storage

2

19. Fuel Facilities (Receiving and Issue)

1

20. Grounds

3

21. HVAC Systems

1

22. Inactive Buildings and Facilities

5

23. Pavements

1

24. Piers, Wharves, and Other Waterfront Structures

1

25. Plumbing

2

26. Power Switches, Instruments, and Potheads

2

27. Railroads

1

28. Roofs

1

29. Sewage Collection and Treatment Systems

1

30. Steel Power Poles and Structures

3

31. Trusses

1

32. Water Treatment and Distribution Systems

1

33. Wood Poles

2
Table 10-1 Suggested Inspection Intervals under Routine Operations and Average Conditions



      1. Inspection Followup. The following actions are normally taken with regard to deficiencies found during an inspection:

        1. Reporting Conditions and Recommendations. Inspections are intended to be used for determining and initiating corrective action. Therefore, it is important that problems be reported and a recommended corrective action be submitted to cognizant facilities maintenance managers for decisions on corrective action. The following are a range of corrective actions:


  1. Issuing work orders.

  2. Expanding the types and increasing the frequencies of PT&I tests to allow for closer monitoring of the problem. Tag or retag assets with appropriate ID tags.

  3. Including corrective action in the AWP or Five-Year Plan.

  4. Preparing a facility project.

  5. Modifying maintenance standards or actions.

  6. Including the deficiency as part of the DM.

  7. A combination of the above.
        1. Estimating Corrective Actions. The cost estimate associated with an inspection report typically is a scoping estimate. However, repair work orders normally require a detailed estimate. All of the information obtained during the identifying and estimating process should be documented, including any impact on the customer. All information is then entered into the work control process for further determination of prioritization, approval or deferral, and scheduling for accomplishment, as discussed in Chapter 5, Facilities Maintenance Program Execution.



Download 3.19 Mb.

Share with your friends:
1   ...   32   33   34   35   36   37   38   39   ...   61




The database is protected by copyright ©ininet.org 2024
send message

    Main page