8.5 Safety Critical Elements, Performance Standards, Assurance and Verification The requirements for this section areas per section 4.5 for those Safety Critical Elements that remain in operation during
the decommissioning process, recognising that the extent and nature of the hazards to be managed during decommissioning are different from production. The Facilities Verification Scheme and Well Verification Scheme must be referenced in the safety case and meet the requirements in sections 2.2.1, 2.4 and 2.5 of the
Compliance Assurance System document.