Implementation Timeline: e-tag version 3 Vendor Interoperability Testing Dates: June



Download 7.1 Kb.
Date01.02.2018
Size7.1 Kb.
#38698
NAESB Electronic Tagging (e-Tag) Specification Version 1.8.3 Implementation Plan

Description of change(s):

Please see the functionality document created by the NAESB Wholesale Electric Quadrant (WEQ) Coordinate Interchange Scheduling Subcommittee (CISS).



Implementation Timeline:

E-Tag version 1.8.3 Vendor Interoperability Testing Dates:

June: 13 and 15 (NAESB Conference Bridge from 1:00pm CPT to 4:00pm CPT)

July: 11 and 13 (NAESB Conference Bridge from 1:00pm CPT to 4:00pm CPT)

E-Tag version 1.8.3 Implementation Date: Midnight CST (1:00 AM CPT)

October 10, 2017 00:00 CST (Midnight CST between October 9 and October 10 2017)

Prevailing times for Implementation Date –

Atlantic Daylight Time October 10, 2017 03:00

Eastern Daylight Time October 10, 2017 02:00

Central Daylight Time October 10, 2017 01:00

Mountain Daylight Time October 10, 2017 00:00

Pacific Daylight Time October 9, 2017 23:00



Proposed E-Tag vversion 1.8.2 Retirement Date: 11/07/2017 Midnight CST

November 7, 2017 00:00 CST (Midnight CST between November 6 and November 7 2017)

Prevailing times for Retirement Date –

Atlantic Standard Time November 7, 2017 02:00

Eastern Standard Time November 7, 2017 01:00

Central Standard Time November 7, 2017 00:00

Mountain Standard Time November 6, 2017 23:00

Pacific Standard Time November 6, 2017 22:00



Implementation Plan:

Since the implementation of e-Tag 1.8.3 changes impacts both the Electric Industry Registry (EIR) and tagging, and in an effort to provide the industry sufficient time for transitioning e-tags from one version to another, the roll out of version 1.8.3 is planned in three phases:



Phase 1: Availability of EIR functionality to support the Market Operator Role

EIR functionality to support the registration of Market Operators will be available on May 2, 2017.

As part of this phase, industry participants will be able to register under the Market Operator role in the EIR. The EIR will also start publishing the Market Operator registry data. All tags created during this phase will be 1.8.2 tags, and market adjusts from BAs/TSPs registered as market operators in the EIR via the legacy flag will still continue to work as they do today. This phase is intended to provide Market Operators sufficient time to register under the Market Operator role in the EIR.

Phase 2: E-Tag v1.8.3 Implementation

Vendors will enable the new e-Tag version at the Implementation Date. E-Tags created prior to the cut-over will be 1.8.2 e-Tags and will work as they do today. E-Tags created at and after the cut-over will be 1.8.3 e-Tags and will behave as per the 1.8.3 changes (these e-Tags may optionally have Market Operators listed on them, however, if present, these Market Operators will be required to approve e-Tags and will have the ability to perform market adjusts on these e-Tags).

after the cut-over

no later than the 1.8.2 Retirement Date Vendors will work with end users to provide the ability to determine which tags are using version 1.8.2 of the e-Tag Specification. Tag Authors will be responsible for recreating the tags. Recreation of the tags may be made at any time between the 1.8.3 Implementation Date and the 1.8.2 Retirement Date.



November 7, 2017

Download 7.1 Kb.

Share with your friends:




The database is protected by copyright ©ininet.org 2024
send message

    Main page