SIMOPS / Operations
Planning and CommunicatingDP Conference Houston October 9-10, 2007 Page Completion Drilling Field Array Setting
ROV Support For Completion Supplies Crew Change - Crew Boat Crew
Change - Chopper Route Survey SIMOPS Table 3: Vessel SIMOPS Identification Table for Pre-Construction / Construction / Operations of
SIMOPS Number 3 and 4 From Table 1 When comparing Table 3 to Table 1, it is clear that this schedule has become more
detailed than the one before, and as the SIMOPS becomes nearer, the schedule should be refined even more. At this stage the current maps (approved for construction) and overall field layouts and the newly revised schedule needs to be sent to the same groups as before (restated below so the reader does not have to go back to look at the team members involved) along with added construction team members (
bolded) for review and comment along with asking the question which topics the group would like
to be placed on the agenda, espically on the DP side of the project before actual meetings are held. This shipment of information should be sent at least 30 or more days before the project begins to give the members of the team time to comment before the meetings begin. Remember, this is to prepare fora Huge kickoff meeting. The groups which was referred to having members of several disciplines from the Oil and Gas operator’s side and the construction contractor’s side which should include at a minimum (as
noted before - Exploration Geophysical Group Members
-
Drilling Group Members - Operations Group Members
-
Construction Group Members - Regulatory Group Members
-
GIS / Survey Group
Members With the addition of -