All start-up programming and system commissioning shall be performed by a Manufacturer’s trained and certified Technician.
SYSTEM VERIFICATION
Subsequent to system start-up the System Installer shall perform a pre-test to verify that the following features are functioning properly.
All initiation devices
The Contractor shall instruct Personnel designated by the District in the proper use, basic care and maintenance of the system beyond the warranty period. Contractor shall provide up to 4-hours of in-service training with this system.
The Manufacturer shall provide factory certified training to two Technicians from the District. These Technicians shall be trained and certified as Manufacturers certified Technicians capable of performing any work on the system after the installation of the system.
All cost for training including travel, lodging, meals and per diem shall be included in the System Supplier/Installer’s bid for this project.