Activities performed:The scopes consisted of planning the work and organizing the team in undertaking: (1) Provided parameters for impact assessment of the Project Performance Monitoring System (PPMS). (2) Assessed the burrow pit area, gravel material sources, asphalt plant in relation to the requirements of the IEE. (3) Provided training seminar as part of the capacity building to local staff of the supervision team as well as the contractor on matters of environmental protection. Conducted site supervision to ascertain compliance to environmental and community safety guidelines. (4) Brought up to the attention of the Contractor certain issues pertaining to vegetation protection (with due consideration on Climate Change Adaptation Measures), air quality, noise, spoil area and land use. Specific cases were cited which need proper and immediate attention from the Contractor as well as his Sub-contractor Drafted Non-Compliance letter to Contractor on specific environmental violations. (5) Wrote the Bi-Annual Environmental Monitoring Report for the Project to be submitted to PIU and ADB.