` Milestone
SpaceX Deliverables Description Launch campaign plan preliminary) Plan for Payload integration and Launch, including the facilities to be used, Payload space allocation in those facilities, and the top-level operations to be performed for both Launch Vehicle and Payload processing. Mission Integration Predicted orbit injection report Predicted
state vector information, based on a nominal trajectory optimized for the Mission. This state vector will be provided in SpaceX-defined format (reference Appendix E. Draft ICD Preliminary draft of the ICD utilizing inputs from Customer for Mission-specific requirements and other interface information to be developed and populated during the course of Mission integration. The ICD defines the Mission requirements and interfaces between Customer and SpaceX systems. Released Payload electrical interface pinout worksheet Documentation capturing the electrical interfaces of the Payload to the Launch Vehicle and documenting the end-to-end pin-out of the SpaceX and Customer built harnessing, including electrical characteristics of each pin.
SpaceX-built harness routing CAD model
SpaceX provides the Customer with a CAD model of the SpaceX-built harnessing. Mission Integration Analyses Trajectory analysis results, including collision avoidance and Monte Carlos
SpaceX will develop a nominal trajectory optimized for the Mission. This nominal trajectory will be used to determine the nominal injection state vector, develop the Launch Window, and define the Mission level deploy order and timeline. SpaceX will conduct a Monte Carlo analysis to formally quantify dispersions on the injection orbit and Launch Vehicle performance. These Monte Carlo results will serve as the verification for orbit injection accuracy requirements. This analysis includes collision avoidance. Verification of Launch
Vehicle compliance to Loads SpaceX confirms to Customer that the Launch Vehicle is compliance to the Loads MPE defined in Section 3.3. Verification of Payload clearance
SpaceX confirms clearance of the Payload using the Customer provided CAD model defined in Appendix C to the allowable Payload allowable volume defined in Appendix A. Payload separation analysis results (if required) Results of the separation analysis predicting the maximum linear and angular separation rates of the Payload upon separation from the Launch Vehicle. CubeSat deployments from Containerized deployers are not analyzed by SpaceX. Launch Campaign Readiness Review
ICD revision for signature Revision of the ICD to be signed by the Parties, having mutually reviewed and agreed to the content.
ICD compliance matrix and status Verification status/evidence sorted by verification article in accordance with the approved verification matrix within the ICD, including status for all open deliverables. Launch integration schedule update) Updated and refined schedule of Launch Site operations identifying Payload standalone activities and combined Payload/Launch Vehicle operations. Launch campaign plan update) Updated plan for Payload arrival, integration and Launch, including the facilities to be used and the operations to be performed for both Launch Vehicle and Payload processing. Launch campaign planning checklist (update) Updated Launch campaign planning checklist to track Launch campaign documentation, GSE shipment list, Customer personnel attendance, Payload details related to Launch Site operations, an OPM email distribution list, and Launch campaign action items. Launch Campaign Launch campaign arrival briefing Briefing to the Customer providing information about working at the Launch Site, including contact information,
security, SpaceX policies, transportation, medical, facility overview, hazardous operations and natural hazards (e.g. lightning, and personnel safety, reinforcing the training material Customer personnel completed prior to arrival at the Launch Site. Hazardous operations planning meetings (if required) If required, a meeting to plan and coordinate any hazardous operations that the Payload must undergo at the Launch Site. Electrical checkout results (if required) If Customer is accessing the payload after encapsulation
through the umbilical harness, SpaceX provides documentation detailing the results of the SpaceX electrical checkouts performed on the harnessing which interfaces with the Payload. Daily Launch campaign schedule updates Daily updates to the Launch Campaign schedule as coordinated in real time with the Customer. Facility environmental reports Reports of facility temperature, relative humidity and particle count are provided to the Customer point of contact. Launch Vehicle readiness certificate Signed confirmation from SpaceX to the Customer that the Launch Vehicle is ready for countdown and Launch, obtained after a Launch Readiness Review between SpaceX and the Range. Post Launch Orbit injection report Provides operational state vector information, based on best available telemetry during the flight. This state vector will be provided in the SpaceX-defined format (reference Appendix E. Customer is solely responsible for conversion, if necessary, of the data into a Customer-preferred format.