SpaceX Ride Share
6.4.3.1

INTEGRATION WORKING GROUPS
SpaceX will organize integration working group meetings on an as-needed basis to address specific issues or operations related to integration of the Payload with the Launch Vehicle. The meeting schedules and locations will be mutually agreed between the Parties.
6.4.3.2

PROGRAM REVIEWS AND MILESTONES
SpaceX will hold a program review to discuss Launch Campaign readiness at the completion of the Mission integration analysis cycle. Program milestones and timeline are defined in the Payload contract’s Statement of Work.

6.5
CUSTOMER RESPONSIBILITIES
Customer responsibilities include the following items. Timely completion is necessary to ensure that SpaceX can fulfill its responsibilities and obligations described in Section 6.6. The Parties understand that any material failure by Customer to meet its responsibilities, including any noncompliance with the Payload ICD, may result in a Customer delay requiring rebooking with applicable fees.
6.5.1

TRANSPORTATION

Customer is responsible for delivering the Payload and associated GSE to the PPF or other Launch Site facility designated by SpaceX. Customer remains responsible for environmental control of the Payload during Payload delivery, until the Payload is removed from its shipping container, including generators and fuel to maintain environmental control. Customer delivers the Payload and GSE to the Launch Site no more than six weeks prior to the Launch Date unless requested by SpaceX. Timing of delivery will be coordinated by SpaceX based on Payload and Co-
Payload(s) processing schedule. Customer arranges and executes the shipment of the Payload shipping container and all Customer-furnished
GSE from the Launch Site no later than three days after Launch. Customer is responsible for all shipping and logistics of hazardous items from the port of entry to the Launch Site, including the required labeling for storage at the Launch Site.


RIDESHARE PAYLOAD USER’S GUIDE
© Space Exploration Technologies Corp. All rights reserved. No US. Export Controlled Data.
42 Customer is responsible for obtaining any required permits, Licenses, or clearances, including from US. Customs and Border Protection for Customer’s and Customer’s Related Third Parties hardware and consumables.