Examination of Estimates of Expenditure 2010-11


Reply Serial No.




CONTROLLING OFFICER’S REPLY TO
INITIAL WRITTEN QUESTION


CEDB(CIT)169







Question Serial No.







0198




Head :

33 Civil Engineering and Development Department

Subhead

(No. & title) :






Programme :

(1) Tourism and Recreational Development

Controlling Officer :

Director of Civil Engineering and Development

Director of Bureau :

Secretary for Commerce and Economic Development

Question :

When will the landscaped piazza at Ngong Ping and its associated improvement works be completed? What is total expenditure of the above-mentioned works? What are the works to be continued in 2010-11?

Asked by :

Hon. CHEUNG Hok-ming


Reply :

The construction of the landscaped piazza at Ngong Ping and associated improvement works will be completed in mid 2010. The estimated total expenditure of the works is $77.5 million. They will add to the tourism appeal of Ngong Ping. Whilst the works of the piazza at Di Tan have already been completed and the area opened to the public, the remaining works for Bohdi Path and a public toilet at the Ngong Ping public transport interchange will be completed in the coming months.







Signature




Name in block letters

JOHN S V CHAI

Post Title

Director of Civil Engineering and Development

Date

15.3.2010





Examination of Estimates of Expenditure 2010-11


Reply Serial No.




CONTROLLING OFFICER’S REPLY TO
INITIAL WRITTEN QUESTION


CEDB(CIT)170







Question Serial No.







0236



Head :

33 Civil Engineering and Development Department

Subhead

(No. & title) :






Programme :

(1) Tourism and Recreational Development

Controlling Officer :

Director of Civil Engineering and Development

Director of Bureau :

Secretary for Commerce and Economic Development

Question :

Regarding the construction works for the enhancement of public facilities at Ngong Ping, please provide the following information:

(a) public facilities to be included in the construction works.

(b) expenditures involved in relevant works.

(c) anticipated time for carrying out the works.

(d) the manpower to be employed.

(e) upon the completion of works, the anticipated increase in the number of visitors.




Asked by :

Hon. IP Wai-ming


Reply :

(a) Enhancement of public facilities at Ngong Ping includes a landscaped piazza with a central pedestrian Bodhi Path, a new Pai Lau and a Chinese-style garden with a pavilion and four lotus ponds around the existing Di Tan, a public toilet at the Ngong Ping public transport interchange, a roundabout and associated storm water drainage works.


(b) The estimated total expenditure of the works is $77.5 million.
(c) The construction of the works commenced in April 2008 and will be completed in mid 2010.
(d) The project will create a total of 116 jobs (100 labourers and 16 professional/technical staff), providing a total employment of about 1 700 man-months.

(e) The project will improve pedestrian flow from Ngong Ping 360 and the public transport interchange to other attractions in the vicinity including Po Lin Monastery and the Giant Buddha. It will also provide better landscaping for the Di Tan area and the nearby footpaths. It will make it more convenient to visit the cluster of tourist attractions in Ngong Ping and add to the appeal of these attractions.








Signature




Name in block letters

JOHN S V CHAI

Post Title

Director of Civil Engineering and Development

Date

15.3.2010