Section VII. Sample Forms



Notes to the Purchaser on preparing the Sample Forms


The Sample Forms provided in these SBD provide standard formats for a number of the key documents that the Purchaser and Bidders will exchange in the process of bidding, awarding, and implementing the Contract. Most of the Sample Forms are to be completed and/or modified by the Purchaser to suit the particular System being procured and included in the Bidding Document before they are released to potential Bidders, or to the winning Bidder, as the case may be. In turn, the Bidders or winning Bidder must complete other forms and submit them to the Purchaser. Notes providing instructions for the Purchaser, the Bidders, and the winning Bidder have been provided. To avoid confusion, the Purchaser should remove all the instructions to the Purchaser from the final version of the Bidding Document that is released to potential Bidders.

To the fullest extent possible, the typographical aides used in the previous sections of the SBD continue in this section. General explanatory text that appears in sans serif typeface (such as this text) remains intended for the Purchaser (hence should be removed from the final version of the Bidding Document). General instructions or explanatory text aimed at Bidders and/or the winning Bidder appear in standard roman typeface, but indicators are included showing they are aimed at Bidders. Instructions that appear directly in the Forms, continue to be in italicized roman typeface, set off with square brackets and generally intended for the Bidders or the winning Bidder. If an instruction is meant for the Purchaser, it is identified as such. Purchasers are encouraged to provide as many of these Sample Forms as possible in revisable, electronic format in or with the Bidding Document. This will expedite bid preparation, reduce the number of inadvertent mistakes made by Bidders, and, as a result, simplify the evaluation.

Bid Submission Form and Contract Agreement: Except as indicated by blanks and/or instructions to fill in information, the text of the Bid Submission Form and the Contract Agreement should be left unaltered in the Bidding Document from how it appears in these SBDs. At the time of Contract award, the Purchaser has an opportunity to add the final details needed in the Contract Agreement form, by making any necessary insertions or changes to Article 1.1 (Contract Documents) and Article 3 (Effective Date) and listing only the actual Appendices that will be incorporated in the final Contract. (These Appendices should also be completed in accordance with the instructions provided at the beginning of each Appendix.)

Since the Price Schedules will form part of the final Contract, if there have been any corrections or modifications to the winning bid resulting from price corrections, pursuant to the Instructions to Bidders, these too should be reflected in the Price Schedules at the time of Contract award and appended to the Contract Agreement in Appendix 6 (Revised Price Schedules).

Price Schedules: The price breakdown given in the sample Price Schedules generally follows the usual breakdown requested for Information Technology procurement, except that further breakdowns are required (e.g., between Technologies/Goods and Services, and between Technologies and other Goods supplied domestically or from abroad) in order for the domestic preference procedure to be applied (except if the procurement falls under the 2004 Guidelines, in which case domestic preference does not apply in this SBD). It is essential that Bidders submit their prices in the manner prescribed by the Price Schedules. Failure to do so may result in loss of the preference, if applicable.

For the more straightforward or well specified Systems that are covered by the single-stage bidding process, the Purchaser is encouraged to fill in the precise System, Subsystem, component, and item/description details in the Price Schedules prior to issuance of the Bidding Document. This will result in bid pricing that is more uniform, making the comparison of bid prices more efficient and reducing the number of ambiguities that require clarification. If Bidders are left to fill in item/description details (which may be necessary for complex Systems when such details cannot be easily identified in advance by the Purchaser), the commercial evaluation becomes more difficult. Other guidance and instructions appear in the subsection containing the schedules and in the schedules themselves.

Manufacturer’s Authorizations and agreements by key subcontractors: In accordance with ITB Clauses 6.1 (b) and (c), Bidders may be required to submit, as part of their bids, Manufacturer’s Authorizations and written agreements by Subcontractors proposed for key services. For the Manufacturer's Authorization, the format provided in the SBD should be used. There is no particular format for Subcontractor agreements.

List of Proposed Subcontractors: In accordance with ITB Clause 6.3, a Bidder must submit, as part of its bid, a list of major goods and/or services that the Bidder proposes to subcontract. The list should also include the names and place of registration of the Subcontractors proposed for each item and a summary of their qualifications.

List of Software and Materials: In accordance with ITB Clause 13.1 (e) (vi) (ITB Clauses 13.1 (c) (vi) and 25.1 (e) (vi) in the two-stage SBD), a Bidder must submit, as part of its bid, a list of all the Software it will provide, assigning each item to one of the following categories: (A) System, General-Purpose, or Application Software; or (B) Standard or Custom Software. The Bidder must also submit a list of all Custom Materials. These should be recorded in the sample List of Software and Materials Table included in the Bidding Document. If provided for in the Bid Data Sheet, the Purchaser may reserve the right to assign key System Software items to a particular category.

Bidder Qualification forms: As required by ITB Clause 6.1.

Forms for securing the bid: If the BDS for ITB Clause 17 (ITB Clause 29 in the two-stage SBD) requires that bids be secured, the Purchaser should include the related form(s) in the Bidding Document, as provided in this Section of the SBD. Depending on what type of security the BDS requires, one form (Bid-Securing Declaration), two forms (Bank Guarantee and Bid Bond), or all three forms, should be included. If the Purchaser wishes to use another form, it must obtain the World Bank’s prior no-objection. Some of the variable fields (such as the duration of sanctions in case of the Bid-Securing Declaration) need to be pre-filled by the Purchaser.

Performance Security: Pursuant to GCC Clause 13.3, the successful Bidder is required to provide the Performance Security within twenty-eight (28) days of notification of Contract award.

Advance Payment Security: Pursuant to GCC Clause 13.2, the successful Bidder is required to provide a bank guarantee securing the Advance Payment, if the SCC related to GCC Clause 12.1 provides for an Advance Payment.

Installation and Operational Acceptance Certificates: Recommended formats for these certificates are included in these SBD. Unless the Purchaser has good reason to require procedures that differ from those recommended, or to require different wording in the certificates, the procedures and forms shall be included unchanged. If the Purchaser wishes to amend the recommended procedures and/or certificates, it may propose alternatives for the approval of the World Bank before release of the Bidding Document to potential Bidders.

Change Order Procedures and Forms: Similar to the Installation and Operational Acceptance Certificates, the Change Estimate Proposal, Estimate Acceptance, Change Proposal, Change Order, and related Forms should be included in the Bidding Document unaltered. If the Purchaser wishes to amend the recommended procedures and/or certificates, it may propose alternatives for the approval of the World Bank before release of the Bidding Document.



Download 1.91 Mb.