Assignment AIS-Production Cycle

ASSIGNMENT NO 01 [PRODUCTION CYCLE]

Question One: What are the main differences between traditional and Activity Based Costing? What factors influence management’s decision in selecting ABC?
Question Two: Smoky Mountain Corporation makes two types of hiking boots—Xtreme and the Pathfinder. Data concerning these two product lines appear below:




Xtreme

Pathfinder

Selling price per unit

$140

$99

Direct materials per unit

72

53

Direct labor cost per unit

24

12

Direct labor-hours per unit

2 DLHs

1 DLHs

Estimated annual production and sales

20,000 units

80,000 units

The company has a traditional costing system in which manufacturing overhead is applied to units based on direct labor-hours. Data concerning manufacturing overhead and direct labor hours for the upcoming year appear below:




Estimated total manufacturing overhead

$1,980,000

Estimated total direct labor-hours

120,000 DLHs

The company is considering replacing its traditional costing system with an activity-based costing system that would assign its manufacturing overhead to the following four activity cost pools (the Other cost pool includes organization-sustaining costs and idle capacity costs):