Viii lid technology: case studies and watershed restoration


Figure 3. Hillside profile through a contour soakage trench



Download 343.22 Kb.
Page7/7
Date20.10.2016
Size343.22 Kb.
#5218
1   2   3   4   5   6   7

Figure 3. Hillside profile through a contour soakage trench


This runoff can then be routed into constructed contour soakage trenches which locally mimic the water-receptive conditions found in more pristine forested settings.


References



Hack, J.T. and Goodlett, J.C. (1960). Geomorphology and forest ecology of a mountain region in the central Appalachians. U.S. Geological Survey Professional Paper 347, 64 p.
Hewlett, J.D. (2003). Principles of Forest Hydrology. University of Georgia Press, 192 p.
Stormwater Retrofit of Highwood Estates Detention Basins to Enhance Water Quality Benefits

Steve Trinkaus1 and Sean Hayden2


1 Trinkaus Engineering, Southbury, CT, 06488 PH (203) 264-4558, Fax (203) 264-4559; Email: strinkaus@earthlink.net

2 Northwest Conservation District; Torrington, Connecticut 06790; 860-626-7222; 860-626-8833 (fax); Email: seanhayden@conservect.org

Abstract

This paper presents the process used to identify water quality issues in an impaired watershed and the design and construction of stormwater basin retrofits to address the impairment issue.


A 2008 Watershed plan for Northfield Brook in Connecticut identified several water quality issues which lead to the impairment of the water quality in Northfield Brook Lake. The lake, which is under the jurisdiction of the Army Corps of Engineers, is closed many times during the year for recreational swimming uses due to excessive Escherichia coli (E.coli) concentrations. The E.coli concentrations routinely exceed the US EPA standard of the geometric mean of 5 samples over a 30 day period being less than 125 CFU/100 ml. While a direct source of the E.coli was not able to be determined, non-point source runoff from a medium density residential subdivision in Thomaston, CT was considered to be a potential source.
The subdivision is served by two detention basins which are non-functioning at the current time. Due to the lack of detention, the downstream channel has experienced significant gully erosion with the result of over 1,000 cubic yards of sediment being deposited into Northfield Brook Lake.
The Northwest Conservation District (NCD) applied for and received Section 319 funding from the CT Department of Environmental Protection (DEP) to address this impairment issue by hiring a consultant to design retrofits for the failing Highwood Estates stormwater basins. The goal of the retrofits was to increase the removal of coarse and fine sediments, on which E.coli is commonly attached, and to reduce peak rates of runoff.

Watershed Track Down Survey

Northfield Brook is a stream that flows South through the Northfield section of Litchfield into Thomaston where it joins the Naugatuck River. Northfield Brook is an impaired stream that flows into the Department of Army Corps of Engineers (DOACE) Northfield Dam Flood Control Project in Thomaston, CT. The DOACE is experiencing problems of sediment build up (Figure 1) as well as elevated levels of nutrient concentration and bacteria within their facility near the toe of the watershed. As a result of these water quality degrading influences, the DOACE has been forced to close the swimming beach many times during most summers. They are even considering eliminating the pond altogether and allowing the stream to course through the project uncontrolled because of the unpredictable water quality problems.


The NCD conducted a visual track down survey assessment of the entire Northfield Brook watershed on and above the DOACE property to identify conditions responsible for the listed impairments. The goal of the track down survey was to collect information on all the possible causes of impairment and recommend and implement solutions in an effort to have the brook removed from the US EPA’s “Impaired Waters of the US” list.



Figure 1 – Northfield Lake (NCD)

The Northfield Brook is identified by the CT DEP as Local Basin #6909. The watershed is approximately 4 miles long and 2 miles wide at the widest point between the top of the watershed and the Northfield Flood Control Dam. The watershed above the Northfield Brook Lake Dam is approximately 3,700 acres and has about 10 miles of associated perennial and intermittent streams. Most of the watershed is forested, with the balance being agricultural and residential development. Agricultural land use is mostly pasture with hay fields providing the dominant crop (Table 1).


Table 1 - Current Land Cover Classifications in the Northfield Brook Watershed

Developed

12%

Forested wetland

2%

Deciduous Forest

59%

Coniferous forest

5.5%

Other Grasses & Agriculture

18%

Barren

0.5%

Turf & Grass

1.5%

Utility ROW

1.5%

Track down surveys are conducted according to a modified version of the Unified Stream Assessment (USA) method developed for small urban watersheds by the Center for Watershed Protection. Eight Impact Assessment Forms record specific information about the condition and restorability of individual problem sites identified along the stream corridor. They include Stormwater Outfalls, Severe Erosion, Impacted Buffers, Utility Impacts, Trash and Debris, Stream Crossings, Channel Modification and Miscellaneous Impacts.

NCD staff worked with municipal officials in planning and conducting the surveys. This local knowledge and experience was very beneficial in identifying sources of impairments.


Water Quality Status
Currently the Northfield Brook is on the CT 2008 Impaired Waters list because at least one designated use cannot be supported, or at least one designated use is impaired. In the case of the Northfield Brook it is impaired for recreational use because of excessive E. Coli concentrations
Escherichia coli Concentration Sampling . The DOACE has been sampling for E. Coli (col/100ml) in the Northfield Lake continuously since 1995. The single sample maximum E. Coli concentration for a designated swimming area is 235 col/100ml. E. coli concentrations routinely exceed 235 col/100ml at the swimming area throughout most summers, resulting in frequent beach closures. Some samples contained well over 1000 col/100ml.
Phosphorus Concentration Sampling . The DOACE has been sampling for total phosphorus (ug/l) in the Northfield Lake since 1995. Lake water quality is quickly degraded with algae problems when phosphorus concentrations exceed 20 ug/l. Lake water sampling indicates that total phosphorus concentrations regularly exceed 20 ug/l with a few lake water samples exceeding 50 ug/l. High phosphorus concentrations have been evidenced by serious algae bloom problems during the summer and early fall.
Likely Sources of Non-Point Source Pollution

Stream Crossings . There are 27 stream crossings in the Northfield Brook Watershed. Most are stable but, the Knife Shop Road crossing is currently unstable and in danger of collapse, which would release hundreds of cubic yards of sediment into Northfield Lake.



Figure 2 - Failing Culverts (NCD)

Medium Density Residential Developments. There are several medium density developments in the watershed. Two in particular, Highwood Estates (Thomaston) & the Borough of Northfield (Litchfield) had tributary streams which were choked with filamentous algae. Non-point sources such as fertilizers, pet waste and failing septic systems are likely sources for these nutrient problems.
Stormwater Basins. The stormwater basins for the Highwood Estates in Thomaston have effectively failed. The design placed the inlet and outlet too close together, so “short circuiting” of the flow has occurred. The outlet control structures are too large to meter flows out, resulting in substantial increases of runoff volume leaving the basins every time it rains.



Figure 3 – Tributary with filamentous algae (NCD)



Figure 4 – Highwood Estates – Stormwater Basins (NCD)

The increased flows out of the basins have adversely impacted the natural receiving stream, which has resulted in the significant channel erosion shown in Figure 5. This eroded material has then created a sediment delta in Northfield Lake containing over 1,000 cubic yards of material. The sediment delta is shown in Figure 6.





Figure 5 – Gully Erosion from Figure 6 – Sediment Deposition in Lake Failing Basin

Agricultural and Livestock Access. Reviewing aerial photographs showed that agricultural activities could also be partially responsible for the impairment in the watershed. A follow up visual assessment showed unfettered access for livestock to streams and riparian areas (Figure 8 below). Livestock access to stream channels causes the following types of Water Quality degradation:


  • Destruction of the riparian vegetation,

  • Erosion of the stream channel, banks, & riparian areas and the resultant in-stream sediment deposition,

  • Introduction of nutrient loads from rich animal waste being carried into the stream by stormwater runoff,

  • Pollutant loads from animal waste being directly deposited in the stream, and

  • Degradation of stream channel stability and aquatic habitat.



Figure 7 – Livestock in stream and riparian area (NCD)

After evaluating all of the potential sources of pollutant loading in the Northfield Brook Watershed, it was determined that the failing stormwater basins in the Highwood Estates development were the largest single source of increased sediment & pollutant loading to Northfield Lake. The other potential sources were not ignored in this process. The unstable stream crossing was replaced with a bridge. The owners of the agricultural uses, particularly those with livestock uses were provided recommendations to prevent livestock from reaching the stream and riparian areas as well as funding sources from USDA.


Stormwater Basin Retrofits
NCD applied for and received 319 Funds to retain a consultant to design the retrofits for Highwood Estates basins. While the town owned the land surrounding both basins, the focus of the retrofits was to work within the existing footprint of the basins to affect a practical solution, yet minimize the potential cost of implementing the retrofit for the Town of Thomaston.
The first step was to inspect the basins in the field to observe the conditions in person. The smaller basin was completely non-functional with any runoff quickly entering and leaving the basin, neither detention or water quality treatment was being provided.
A survey with topographic information was obtained to provide the necessary base information for design purposes. After the survey was done, it was time to analyze the contributing watershed areas in order to design the retrofits.
Small Basin
Existing Conditions. The small basin has a 24.5 acre watershed area consisting of residential roads and ½ acre building lots. The basin consists of a small, elliptical footprint with the outlet structure located at the north end of the basin. Runoff is directed to the northeast corner of the basin by a riprap swale which conveys the runoff from the road drainage system. Due to the proximity of the inlet and outlet to each other, the runoff has cut a direct path between the two points, resulting in most of the basin not being used.
The peak rate of runoff for a 2-year storm was calculated by the HydroCAD model. Approximately 30.09 cfs is directed to the basin during this storm event. In addition, the Water Quality Volume (WQV) as found in the CT DEP 2004 Stormwater Quality Manual (Manual) was determined for the watershed. A total of 35,278 cubic feet of storage volume would need to be provided for the small basin to achieve this goal.
Retrofit Design Due to site constraints, the retrofit options were limited for this basin. First, a well-defined depressed forebay was created above the existing basin. The forebay provides 2,568 cubic feet of storage volume (7.3% of the WQV, the goal is to have 10%). The riprap swale was redirected to direct runoff into the east end of the forebay with the outlet being located at the western end. The forebay is slightly over four feet in depth. This is important as to minimize the resuspension of fine sediments in the forebay during subsequent runoff events.
The basin itself was excavated to provide a single, deep pool feature six feet in depth. A vegetated, aquatic shelf was created along the perimeter of the deep pool. The single outlet pipe was replaced with a staged orifice outlet design to provide a slight reduction of the peak rate of runoff in the basin above the permanent pool. The peak rate of runoff for the 2-year event will be reduced from 30.09 cfs to 28.87 cfs.
The regraded basin and new forebay provide a total of 5,278 cubic feet of fixed volume for water quality purposes. This is approximately 15% of the calculated WQV, but is the maximum available based upon site limitations. The features of the basin retrofit are shown in Figure 8.
Large Basin

Existing Conditions The large basin has a 28.32 acre watershed area consisting of residential roads and ½ acre building lots. The basin is approximately circular in shape. The inlet swale enters the basin in the northeast portion, while the outlet structure is located at the southeastern end. Similar to the small basin, runoff short circuits the storage area of the basin and makes a quick line in and out. The outlet control structure consists of a square 18” x 18” opening which does not provide any measure of rate reduction.
The peak rate of runoff for a 2-year storm was calculated. Approximately 30.66 cfs is directed to the basin during this storm event. In addition, the Water Quality Volume (CT DEP 2004 Stormwater Quality Manual) was determined for the watershed. A total of 41,810 cubic feet of storage volume would need to be provided for the large basin.


Ex. Stream Discharge

Redirected Riprap Swale

Basin Retrofit

New Forebay
smal

Figure 8 – Small Basin Retrofit (Trinkaus Engineering, LLC)

Retrofit Design There is more space available for this basin retrofit. A large, separate forebay was constructed above and north of the existing basin. This forebay is six feet in depth and provides a fixed storage volume of 5,285 cubic feet. This is approximately 12.6% of the required WQV which is more than the suggested 10% of the WQV for a forebay under the Manual.

The flow from the existing riprap swale was directed into the forebay at the east, with the outlet from the forebay being on the western end. A new riprap swale will direct runoff from the forebay to the northwest corner of the basin.


The larger basin size allowed for a more significant retrofit to be implemented compared to the smaller basin. A two (2) foot micro-pool was placed at the inlet of the new riprap swale. A second, deeper micro-pool was created just before the existing outlet control structure. A low flow path was created from the shallow micro-pool to the deeper one in a circuitous path.
The majority of the basin bottom will be planted to create a shallow marsh environment. Two areas will be raised by 6” to create high marsh areas which will encourage a low, slow flow path for runoff within the basin as well as maximizing the contact time between stormwater and the vegetation. A total of 17,996 cubic feet of fixed volume is provided between the forebay and permanent pool in the basin, which is approximately 43% of the required WQV.
The outlet structure was modified to create a staged orifice system. Due to the size of this basin, the 2-year peak rate of runoff will be reduced from 30.66 cfs to 5.00 cfs. This is a substantial reduction that will prevent the further erosion of the existing stream channel between the basin and Northfield Lake.
The redesigned basin is shown in Figure 9.
Pollutant Renovation Analysis
The Simple Method was used to calculate the estimated pollutant loads from the contributing watershed area for each basin on an annual basis. The effectiveness of the stormwater management system for each basin was evaluated for removal of TSS, TP, TN, Zn, TPH and DIN. Removal efficiencies for the various treatment systems were taken from both University of New Hampshire Stormwater Center and the ASCE BMP Database.


2’ Micro-pool

4’ Micro-pool

New Forebay

High Marsh Area

Low Marsh Area

Low Flow Path
large

Figure 9 – Large Basin Retrofit (Trinkaus Engineering, LLC)

Table 2 – Results of Simple Method and Treatment System Evaluation

Small Basin






















TSS

TP

TN

Zn

TPH

DIN

Current (lbs)

6872

29.2

215.9

17.3

163

35.3

With-Treatment (lbs)

302.6

17.2

57.6

0.2

18.6

16.2

% Removal

95.6

41.1

73.3

98.8

88.6

54.1

It can be seen by the modeling results that sediment loads will be substantially reduced by these basin retrofits and thus bacteria concentrations will also be reduced due to their affinity to attach to sediment particles.
Table 3 – Results of Simple Method and Treatment System Evaluation

Large Basin






















TSS

TP

TN

Zn

TPH

DIN

Current (lbs)

8422

34.2

257.3

20.4

205.6

42.1

With-Treatment (lbs)

264.9

10.8

97

0.8

137.7

15.6

% Removal

96.9

68.4

62.3

96.1

33.0

63.0

Implementation
As of the spring of 2012, the Town of Thomaston is soliciting bids from contractors to construct the basin retrofits by September. The goal is to have the retrofits completed prior to fall of 2012.
Conclusion
The retrofits of these two storm water basins will provide a measurable improvement to stormwater quality which will ultimately reach Northfield Lake. In addition, the cost of implementing these retrofits by the Town of Thomaston was minimized by working with the natural conditions to the maximum extent possible.
The approaches and concepts used in these retrofits can easily apply to other stormwater basins to increase the benefits of old standard detention basins.

References

CT DEP (2004); “Stormwater Quality Manual”

Hayden, Sean (June 2009); “Northfield Brook in Thomaston and Northfield, Connecticut Track Down Survey Report”

Houle, James and Roseen, Robert (2009); “University of New Hampshire Stormwater Center 2009 Annual Report”



Kitchell, A., Schueler, T. (2005); “Urban Subwatershed Restoration Manual No. 10: Unified Stream Assessment: A User’s Manual (Version 2.0)

1 This paper only concerns itself with conventional pollutants coming from the METRO system. The lake is also a listed Super-fund site with many sub-sites. These are being remediated under a different program.

2 The RTF might or might not meet the EPA CSO policy requirement to be at least as effective as primary sewage treatment.

3 No attempt has been made to bring all of the expenditures and estimated expenditures up to 2011 dollars.

4 This effort was also enhanced by US EPA’s giving more scrutiny under the National Environmental Protection Act before additional federal funds could be released for RTFs.

5 Ms. Mahoney has subsequently been re-elected, running without opposition.

6 The new plan would be a change from the previous court approved ACJ and therefore changes would need to be brought before the Court for approval.

7 Available at http://www.onondagalake.org/docs/ACJSTIPsigned16November2009.pdf. Detailed descriptions, technical plans, and related materials can be found on numerous websites, and all documents may be viewed, by appointment, at the ASLF office in Syracuse, NY.

8 See the Save the Rain website, http://www.savetherain.us.

9 As feasible state and federal owned parcels are also being evaluated for GI.

10 The Green Improvement Fund (GIF) program has been very successful. Details of it and the application can be seen on the website. See footnote 9.

11 Available at http://www.nrdc.org/water/pollution/rooftopsii/

12 Most governmental units rely on consultants to do all the heavy lifting. These consultants are motivated by profit and these usually lead them to suggest similar solutions to all problems regardless of the nuanced local situations. These solutions are often relatively easy to design and construct with little consideration for long term operating costs, ecosystems, or public support. Regulators like the tried and true methods and so permitting and related issues are simpler as well.

13 Large scale projects, in theory, need to get full environmental review under either the National Environmental Policy Act or state equivalents depending on who is funding the project. Often, however, under the guise that pollution control is a benefit to the environment, little or no review and looking at alternatives is performed.

14 Federal, state, and local procurement policies are often very rigid and out of date regarding flexibility needed for many small projects. Higher cost thresholds and other changes should be considered in these procedures. Related issues also arise as there is a desire to employ local people in “green jobs programs,” but these well intended practices often cannot be met.

15 The paucity of new construction negates the eventual effectiveness in the MS4 program to alleviate stormwater issues. Whenever new or renovation construction trips the thresholds of that program, it is implemented and enforced here as well, we hope, across the nation.

16 See previous reference to the GIF program. In the future, the County will gradually decrease this incentive program from present 100% reimbursement to lower and lower amounts as the program matures and we are closer to our final 2018 goals.

17 In some cases, engineers, landscape design professionals, and even urban foresters still either disregard the use of native plants or are actually hostile. The many arguments pro and con will not be further spelled out here, but the need to consider urban ecological issues and even how the City fits within a regional ecosystem is very important and must be considered.

18 For more information, please visit http://savetherain.us/suburban-gip-announcement/


Download 343.22 Kb.

Share with your friends:
1   2   3   4   5   6   7




The database is protected by copyright ©ininet.org 2024
send message

    Main page