For all TMV's carry out servicing using manufacturers service kit.
Inspect check valves & filters (clean or replace as necessary).
Re-instate and calibrate to correct temperatures detailed below:
Area/activity
Recommended
temperature (°C)
Staff bases, ward, consulting rooms, in-patient areas, out-patient areas and general areas to which staff and visitors may have access.
41
Paediatric baths
General baths
Assisted baths
40
43
46
Showers & Hair-wash facilities
41
Bidets
38
All sinks, kitchens, pantries, slop sinks
55
Staff-only access i.e. Offices
43
Thermostatic mixing control valves (hot supply to be 55OC or greater, cold supply to be less than 20 OC to teat mixing valve fail safe).
Procedure for fail safe:
Run the hot tap and check the water temperature with a calibrated thermometer is at correct for the type outlet (according the table detailed above) (+ or - 1oC) with the control at hot.
Shut off the cold supply to the valve and ensure that the discharge shuts off within 2/3 seconds.
If a failure occurs:
strip down,
service,
repair
retest.
Reinstate the supply.
If fail safe does not work valves must be stripped & overhauled (parts replace as necessary).
The valves must then be commissioned to D08 specification.
RECORD SHEET C – LEG43 MUST BE FILLED IN AND RETURNED TO THE AUTHORISED PERSON [WATER]
Procedure:
TMV / SHOWER MAINTENANCE
Frequency:
Every 6 months
Acceptance date:
31/03/10
File Ref:
C – LEG43 [page 1 of 2]
Next review date:
31/03/11
Property:
Location:
Docket No:
Thermometer Serial No.:
BIANNUAL TEST:
Check operation of mixer, set temperature (according to guide table below) and simulate fail test (see description below). Record the pipe temperature pre TMV, record the mixed outlet (hot & cold) and NON MIXED outlet (hot & cold) temperatures. Report any defects below.
Fail Test:
A simulated cold water fail test shall be carried out following the overhaul or calibration of each valve by SLOWLY turning off the cold water to the valve and observing the water flow stopping.
A simulated hot water fail test shall be carried out following the overhaul or calibration of each valve by SLOWLY turning off the hot water to the valve and observing the water flow stopping.
Approved temperatures for TMVs settings based on activity / area where the TMV is required.
Area/activity
Recommended
temperature (°C)
Staff bases, ward, consulting rooms, in-patient areas, out-patient areas and general areas to which staff and visitors may have access.
41
Paediatric baths
General baths
Assisted baths
40
43
46
Showers & Hair-wash facilities
41
Bidets
38
All sinks, kitchens, pantries, slop sinks
55
Staff-only access i.e. Offices
43
*Where difficulty is experienced setting TMV temperature then a variation of +/- 1OC is acceptable.
Continued overleaf....
Procedure:
TMV / SHOWER MAINTENANCE
File Ref:
C – LEG43 [page 2 of 2]
Ward / Dept.
Room No.
Test done
(tick)
Outlet data
TOC OK?
Fail Test
OK
Initial & Date
6 M
Ann
WHB/Sink/ Bath/Shower etc.
TMV fitted (tick)
TMV Asset No.
Valve Type
Pre TMV TOC
Hot TOC
Cold TOC
Yes
No
Comments:
I, the undersigned, have completed the works outlined above:
Tradesperson
Name:
Signature:
Date:
Authorised Person [Water]
Name:
Signature:
Additional Docket Numbers Issued:
*** PLEASE PHOTOCOPY THIS FORM AS NECESSARY TO ACCOMMODATE ALL TMVs FOUND ON THE WARD / DEPARTMENT ***
PPM:
TMV / SHOWER MAINTENANCE
PPM Ref:
C – LEG47
Frequency:
Annually
For all TMV's carry out servicing using manufacturers service kit.
Inspect, check, strip and overhaul all valves & filters (clean or replace as necessary).
Re-instate and calibrate to correct temperatures detailed below:
Area/activity
Recommended
temperature (°C)
Staff bases, ward, consulting rooms, in-patient areas, out-patient areas and general areas to which staff and visitors may have access.
41
Paediatric baths
General baths
Assisted baths
40
43
46
Showers & Hair-wash facilities
41
Bidets
38
All sinks, kitchens, pantries, slop sinks
55
Staff-only access i.e. Offices
43
Thermostatic mixing control valves (hot supply to be 55oC or greater, cold supply to be less than 20 OC to teat mixing valve fail safe).
Procedure for fail safe:
Run the hot tap and check the water temperature with a calibrated thermometer is at correct for the type outlet (according the table detailed above) (+ or - 1oC) with the control at hot.
Shut off the cold supply to the valve and ensure that the discharge shuts off within 2/3 seconds.
If a failure occurs:
strip down,
service,
repair
retest.
Reinstate the supply.
If fail safe does not work valves must be stripped & overhauled again (parts replace as necessary).
The valves must then be commissioned to D08 specification.
RECORD SHEET C – LEG47 MUST BE FILLED IN AND RETURNED TO THE AUTHORISED PERSON [WATER]
Procedure:
TMV / SHOWER MAINTENANCE
Frequency:
Annual
Acceptance date:
31/03/10
File Ref:
C – LEG47 [page 1 of 2]
Next review date:
31/03/11
Property:
Location:
Docket No:
Thermometer Serial No.:
ANNUAL TEST:
Check operation of mixer, set temperature (according to guide table below) and simulate fail test (see description below). Record the pipe temperature pre TMV, record the mixed outlet (hot & cold) and NON MIXED outlet (hot & cold) temperatures. Report any defects below.
Strip down and overhaul. Fit new seals and parts as required. Reset temperature (according to guide table below) and simulate fail test (see description below). Record mixed outlet and NON MIXED outlet temperatures. Report any defects below.
Fail Test:
A simulated cold water fail test shall be carried out following the overhaul or calibration of each valve by SLOWLY turning off the cold water to the valve and observing the water flow stopping.
A simulated hot water fail test shall be carried out following the overhaul or calibration of each valve by SLOWLY turning off the hot water to the valve and observing the water flow stopping.
Approved temperatures for TMVs settings based on activity / area where the TMV is required.
Area/activity
Recommended
temperature (°C)
Staff bases, ward, consulting rooms, in-patient areas, out-patient areas and general areas to which staff and visitors may have access.
41
Paediatric baths
General baths
Assisted baths
40
43
46
Showers & Hair-wash facilities
41
Bidets
38
All sinks, kitchens, pantries, slop sinks
55
Staff-only access i.e. Offices
43
*Where difficulty is experienced setting TMV temperature then a variation of +/- 1OC is acceptable.
Continued overleaf....
Procedure:
TMV / SHOWER MAINTENANCE
File Ref:
C – LEG47 [page 2 of 2]
Ward / Dept.
Room No.
Test done
(tick)
Outlet data
TOC OK?
Fail Test
OK
Initial & Date
6 M
Ann
WHB/Sink/ Bath/Shower etc.
TMV fitted (tick)
TMV Asset No.
Valve Type
Pre
TMVTOC
Hot TOC
Cold TOC
Yes
No
Comments:
I, the undersigned, have completed the works outlined above:
Competent Person
Name:
Signature:
Date:
Authorised Person [Water]
Name:
Signature:
Additional Docket Numbers Issued:
*** PLEASE PHOTOCOPY THIS FORM AS NECESSARY TO ACCOMMODATE ALL TMVs FOUND ON THE WARD / DEPARTMENT ***
Complete an inspection of each AHU as detailed below and complete record form C – LEG06. General check on overall condition of unit. Repair/renovate as required.
Check all thermal and acoustic linings.
Examine for any undue noise, vibration, lack of performance, etc. and report findings.
Check flexible connections, examine security of retaining bands, replace damaged sections if necessary.
Check security brackets and associated supports.
Check tension, alignment and condition of fan drive belts; re-tension / renew (as a complete set) as required.
Check condition of motor/drive casings and motor vent grilles and clean as required.
Check electrical connections.
Check safety guards are secure.
All procedures must comply with the Health and Safety at Work etc Act and COSHH regulations;
Notify all persons working in those areas served by the plant to be disinfected;
Switch off all ventilation systems containing devices to be disinfected;
Spray all internal surfaces of the humidifier section or cooler battery/cooling coil with a 5 ppm chlorine solution until all surfaces are thoroughly wetted, also flood drip trays and drainage system with the same solution and allow to stand for a minimum of two hours;
Spray all internal surfaces of the humidifier and cooler battery/cooling coil with sufficient clean water to remove all traces of the chlorine solution from the device, its drip trays and drainage system;
Restore the plant to normal operation;
If any suspicion arises as to the possible contamination of the system then the microbiologist should be requested to take swab tests from all drain trays and cooler battery/cooling coil tubes and fins;
As an alternative to steps (f) and (g) detailed above, the surfaces may be steam cleaned;
RECORD SHEET C – LEG06 MUST BE FILLED IN AND RETURNED TO THE AUTHORISED PERSON [WATER]
Procedure:
NON CRITICAL SERVICES VENTILATION SUPPLY PLANT CLEANING AND INSPECTION RECORD SHEET
Frequency:
Every 6 months
Acceptance date:
Oct’12
File Ref:
LEG06 [page 1 of 2]
Next review date:
Oct’14
Building:
Location:
System ID:
Docket No:
Item
Work description
Y
N
1
Inform departments concerned that plant is to be shut down.
2
Is the plant room secure (locked)
3
Is the ventilation plant running upon entering the plant room?
4
Is the ventilation plant adequate labelled with a unique reference / asset / plant No.
5
Is the ventilation plant safely accessible for inspection and maintenance?
6
Is the overall exterior condition of the ventilation plant in a good condition?
If ‘NO’ detail reasons…
7
Are the principle ducts of the ventilation plant lagged?
8
Are any pipework leading to the ventilation plant adequately lagged?
9
Is the position of the air intake for the ventilation plant clear of any dirty, debris, build up of rubbish and unobstructed?
10
Is the position of the air intake for the ventilation plant at least 10 meters away from any extract or foul air from other sources i.e. gas scavenging outlets?
11
Do internal lights work? (Replace faulty bulbs once isolated). Report other faults.
12
Electrically isolate power supplies to the plant and make safe and lock off.
13
Do motorised dampers close on plant shut down?
14
Remove access panels to all areas to be cleaned including batteries.
15
With inspection plates open, using a torch, are the fins of heating and chilling batteries are clear and free of lint, dust & debris?
16
Having completed a visually inspect all heating & chilling batteries is there any sign of damage and leakage, including all local control valves etc?
If possible rectify the fault, otherwise report to Authorised Person [Water] for further attention.
17
Vacuum out all ducts of the ventilation plant, heating and chilling batteries including the areas around them?
18
Are the internal drainage drip trays stainless steel?
19
Are the internal drainage drip trays fully accessible or capable of being removed for cleaning?
20
Are the internal drainage drip trays below chillers and/or humidifiers clear of any corrosion of water i.e. there is no ponding of water?
21
Are the duct work drainage drip trays clear and free flowing? (clear if required).
22
Spray chiller batteries and surrounding ductwork, drain areas and any other low points in the local ductwork with hypochlorite solution at 5ppm dilution.
Ensure that both sides of the batteries are treated.
23
If a humidifier is present is it in operation?
24
Remove all glass traps, clean with a ‘bottle brush’, fill trap with clean water and then refit unit.
Ensure there is an air break of at least 15mm between the trap and tundish.
25
Visually inspect and check mechanical drive to the plant including pulley belts, pulley tensions (where fitted) and bearings. Adjust and lubricate as required.
26
Are manometers oil levels acceptable (fill with oil if required)
27
Are all guards in a good condition and secure?
Refix guards where necessary.
28
Is the condition of associated control valves and pipework in good order?
If ‘NO’ detail reasons…
Procedure:
NON CRITICAL SERVICES VENTILATION SUPPLY PLANT CLEANING AND INSPECTION RECORD SHEET