Fig02: Features up to 05 km. from the site

66. In view of the above mentioned features it is clear that, the site is a vacant land and no settlement or human habitation is close to the project and there are no projects / industries up to 05 (five) km. distance of the site.



4.0. Methodology
67. The various activities required for carrying out EA study have to be undertaken by several individuals and organizations, each being responsible for a specific activity.
68. The primary responsibility for carrying out an EA study of any project lies with the project proponent. For this project (SEC) primary responsibility lies to BHTPA as this agency will start some physical and construction work for the project and thereafter responsibility will be borne by the developer/investors as they will implement next segment of the project. As stated earlier the EIA/EA should be carried out in tiers. An EIA procedure should be initiated simultaneously with the project planning and that the level of efforts required for various tiers of EIA should be commensurate with the project development, throughout the stages of its identification to implementation.
69. The task of preparing the EA report consisted of the following sequential components:

    • Familiarization with and review of various project actions of the PSDSP projects;

    • Identification and screening of the environmental parameters relevant to the proposed project actions in the HTP area through a scoping process;

    • Avoidance/ mitigation measures to address the potential negative impacts, and preparation of a monitoring program during the period of project implementation;

70. Environmental assessment (EA) is an integral part of development planning. It is essential that environmental issues are properly evaluated in terms of impacts and relevance, and are integrated into each stage of the project cycle. The proposed actions under the SEC involve interventions in the implementation of various infrastructures in the project area. In conforming to the requirements of preparing an EA report, a methodology was developed in accordance with the WB’s environmental assessment guidelines. The period of preparing the EA was from 8th November 2014 to 23rd December 2014, and field visits for data collection was done on 8th – 9th November 2014 and 23rd December 2014.


5.0. Description of the Project
5.1. General
71. The design and site development strategy of the project not yet finalized. A feasibility study was done by the Infrastructure Investment Facilitation Company (IIFC), Bangladesh and in accordance with the feasibility study multiple options (three) suggested for site development. This EA study made largely based on the Master Plan described in the feasibility study.
72. As the project area falls in the earthquake region of Bangladesh and the project area is sufficiently large, high-rise buildings avoided in the feasibility study. Buildings up-to 5 storied are suggested for Multi-Tenant Building (MTB) and Hotel buildings. Other buildings are of double or single storied. Steel frame structure has been proposed for the 5-storied MTBs. Alternatively, the study also proposed to construct the buildings on RCC frame-structure. Other buildings are proposed for traditional RCC and brick structures. The study also suggests, the steel frame structure will be costlier than traditional construction, but it will take less time for construction. With this possibility of design and structure that proposed in the feasibility study, it can also think other alternatives. In fact, there are many earthquake prone countries in the world. Japan is one of them as the country sits on the “Pacific Ring of Fire”. The Ring of Fire is an area in the Pacific Ocean where the movement of the earth’s plates causes frequent earthquakes and volcanic activity. Japanese people experience the shaking of earthquake very often. But in Japan they have been built most of their multi-storied buildings resistant to earthquake. From the seismic point of view Sylhet region is less vulnerable than Japan. So, in the Sylhet HTP if buildings are built with earthquake resistant, high rise buildings beyond 5-storied can be built.
73. On the basis of IIFC feasibility study, Site development is proposed by a) raising the entire land with dredge spoils, after making a periphery earthen embankment around the project area, and keeping some water body, such as ponds and lakes in between b) alternately, the buildings may be constructed on scattered raised islands and c) buildings is to be built on pillars, keeping the ground at original low level and allowing the water to pass freely under the buildings.
74. The proposed project site is situated on the eastern side of Sylhet – Bholaganj Road (via Companiganj), about 25 km away from Sylhet Town and almost 5 km away from Companiganj Upazila Headquarter. The site is 20 km away from the Osmani International Airport and about 28 km from the Sylhet new Railway Station and Bus Terminal. The land area of the proposed site for the development of Sylhet HTP is 162.83 acres. The land is located in the Khalitazuri Beelerpar Mouza, under the Dhakkin Ronikhai Union in the Companigonj Upazila. It has a J.L number of 188, Khatian number 01 and Plot (Dag) number 25. It is a government khash land and The Ministry of Land gave their concurrence to handover these 162.83 acres of land to Bangladesh Hi-Tech Park Authority for establishing the proposed Sylhet Hi-Tech Park (SHTP). The transferring process was carried out under section 10 of “Non-Agricultural Khas Land Settlement Policy, 1995”. There is no dispute over the land and no legal impediments to use the land for developing the proposed SEC on the site.

75. The site is a non-arable flat, low land with some small sizes shallow ditches on the north side. A borrow pit which is almost 60 feet width is situated along the highway and passes on the west side of the land. The land is almost 15 feet lower than the Sylhet -Companiganj road. It remains under water for 3 to 4 months during monsoon season.

Photograph 01: View of the proposed project site