Definitions
Employer means-Project owner
Employer Representative- Any person authorised by Employer to act on their behalf
Contractor Representative- A person authorised by Contractor to act on their behalf.
Waste Material or effluent or other unwanted surplus substance that requires disposal because it cannot be re-used or recycled or there is no economic demand for it.
Responsibilities
Contractor Site Manager has overall responsibility for ensuring that the environmental controls described in this ECP are effectively implemented on Site in coordination with QA / QC Manager as well as the site HSE Manager.
Instructions Health, Safety & Environmental Impact Assessment
The Health, Safety and Environmental Assessment preparation includes an assessment of the impact of Construction activities and the Construction Camp on the environment and suggests measures to mitigate the impact.
The suggestions made are summarised in the table 1 along with the control measures that Contractor shall be undertaking.
Table 1: Environmental Issues and AJES Control Measures.
Construction
Environmental Issue
|
Suggestions
|
AJES Control Measures
|
Contaminated Land.
Contamination of Land by any accidental oil spills or any effluent during the construction activities.
|
The soil from areas of contamination shall be removed and disposed of to any approved landfill.
|
AJES shall contact the local authorities for disposing the contaminated soil in approved land fill
|
Protection of ground Waters and Wadis.
The ground waters and others water sources like Wadis are utilised for agriculture and cattle feeding by local population and weeds and plants growing in the area. This water source has to be protected from any pollution from construction activities.
|
Any wash water run-off requires a system of temporary impoundment and settling to remove silt before returning to the ground. This shall be carried out during site preparation.
Sewage must be treated and only treated water allowed to run out to ground. Sewage treatment plants shall be installed and operational along with construction camp
In isolated locations local methods shall be followed.
|
A silt retention trap shall be constructed at all wash water facilities. This retention shall allow settling of sand, silt, and grease etc. and only clear water surface shall run-off to ground.
Sewage Treatment plant shall be installed at each camp to control the sewage water out-lets.
|
Site Preparation.
|
AJES to have a traffic management system in place with temporary haul road and traffic segregation, where practicable.
Dust control measures to be implemented. Roads shall be maintained to reduce dust as practical.
|
Temporary haul roads shall be constructed and kept as clear as is practicable from sand.
Dust suppression measures shall be used to control dust such as water sprays.
|
Dust.
Dust shall be exacerbated by site activities such as stripping and vehicle movements.
The area experiences sand storms.
|
Temporary roads shall be constructed for site traffic.
Water spray bowsers shall be used.
|
Top layer of fine dust shall be graded away from traffic route as practical
Water shall be sprayed to suppress the flying of dust.
|
Noise.
Excessive Noise level created by the constant operation of plants and equipment.
|
Regular inspection of all equipment working in the project shall be done so as to maintain minimised noise levels in accordance with manufactures recommendations.
|
All equipments shall be maintained to acceptable noise level as recommended by manufacturer
Noise protection equipments shall be used by personal if require to work in high noise level areas
|
Construction Camp.
Camps shall provide accommodation, catering and sanitation for approx. all workforce personnel. Waste arising from these camps shall be significant, as shall traffic to and from the camps.
|
Sewage treatment plant to be installed in both camps.
Traffic segregation must be implemented.
Dust suppression methods must be implemented.
|
Sewage Treatment Plant shall be installed and maintained to meet the requirements arising from the sewage at camps.
Heavy traffic shall be separated from light vehicles and separated access roads maintained.
Grading the road and water spraying regularly shall control dust.
|
Oil Spillage.
The possible chances of oil leaks and spills from the fuel refilling tankers, storage tanks and from brake down of equipment shall contaminate the ground and pollute the adjacent ground water.
|
Use of Bunded storage for any oil or fuel products for containing accidental leak
Availability of recovery facilities for any leaked pollutant
Use of drip trays while refuelling or handling fuel or oil products.
|
Oil and fuel products shall be stored in bunded area for containing any accidental leak.
Recovery materials like absorbents, sand and sand bags shall be available in the vicinity to the immediate use
Drip trays shall be used to contain leaks while handling oil or refuelling.
The recovered contaminated soil and associated materials shall be collected and disposed in safe method.
| Spill Prevention and Response
Contractor should believe in prevention first and foremost by applying commitment with best practices throughout construction. However, in the event of an unforeseen natural disaster or man-made incident that results in a threat to the environment, Contractor shall be prepared to respond in a timely and effective manner that should limit environmental damage to a minimum. In many cases major pollution incidents can be prevented if appropriate pollution prevention measures are applied at an early stage. Planning of applicable methods is the key to any success, therefore both preventative measures as well as incident response strategy should be addressed as given below.
Spill Prevention
The following procedures shall be carried out to reduce the possibility of a spill that may be harmful to the environment or to the health and safety of the staff:
Appropriate precautions shall be taken so far as is reasonably practicable to protect storage areas and equipment from vandalism.
Stores of potentially polluting material shall be situated on an impervious base and surrounded by an impervious bund capable of containing a volume 10% greater than the store. Valves shall be checked periodically on routine HSE inspections to ascertain that they are closed.
Special consideration shall be given to any leakages arising from the surface run-off around temporary stockpiles of materials. All stationary diesel and petrol operated construction equipment shall have impervious drip trays placed beneath them during operation. Any spillages into the drip trays shall be collected for safe disposal.
Vehicles and mobile equipment shall be regularly inspected and maintained to confirm they are not leaking or dripping. Operators shall be instructed in their HSE training to notify their supervisors if there occur any problems with their vehicles whereby appropriate maintenance be given. Maintenance of construction plant maintenance shall be closely supervised and measures shall be implemented to prevent hydrocarbon contamination. These measures shall include use of drip trays, absorbent materials close at hand and careful disposal of any used materials.
Major equipment and vehicles shall be re-fuelled on an impervious base. Care shall be taken not to spill any fuel and absorbent materials be close at hand. Stationary equipment with impervious drip trays shall be re-fuelled in-situ; fuel containers shall be sealed after use and stored on an impervious base away from water bodies.
Higher levels of dust containment shall be used for contaminated excavated material than used for other material. Appropriate measures may include: use of fine water sprays to thoroughly moisten all surfaces and maintain surface moisture; use of protective fences or screens to provide shelter from winds; minimising unnecessary handling of material and enclosure of excavated material in wind proof containers prior to removal from site.
Spill Response
The magnitude of the discharge / spill shall determine the extent of the actions that have to be made necessary
The key actions in responding to a spill to minimise its environmental impact are:
An Early Detection.
Regular inspections and training shall be carried out to enable an early detection. It is everyone’s responsibility to be aware of potential pollution risks.
Notify Supervisor / Emergency Team
Notify supervisor who shall notify the Site Manager or HSE Manager. Emergency services shall be notified as necessary.
Assess Safety Risk To Humans
Only attempt containment and cleanup operations of spilled substances when it can be performed safely.
If spilled material is flammable, eliminate sources of ignition near spill area.
Personnel and neighbours are to be evacuated if they are at risk
Secure the area and establish perimeter control at a safe distance from the spill.
Stop Source of Spill.
When it can be performed safely, stop source of spill. Pollution control equipment shall be available from site administration offices, storage and re-fuelling areas.
Contain Spill (If Liquid).
Liquid spills - If the spill is liquid, its path shall be blocked or diverted and then soaked up using an absorbent material.
Gaseous spills / leaks – A gaseous leak must be stopped at source as soon as possible and shall then disperse in the air. It is not practicably possible to contain a gaseous leak but weather conditions should be checked to assess the most likely direction the pollutant shall take if it poses a risk to human health followed by the area evacuation.
No spills shall be rinsed away. Contaminated soils and clean-up materials from spills must be handled properly using personal protective equipment. These should be stored in a suitable container that is then labelled and taken away to be further stored in the appropriate location for subsequent safe disposal. Screen / cover stockpiles of polluted matter to prevent dispersion.
Dispose With Care.
Contaminated soils and used clean-up materials shall be treated as hazardous waste and be disposed of accordingly at a designated disposal site.
Document Incident.
The Site HSE Manager shall be responsible for ensuring a report is filed containing information on date, time, location, type and quantity of spilled material, description and cause of incident, action taken, name of person reporting the incident and recommended actions for ensuring the incident doesn’t reoccur.
Spill Response Materials
Spill response / pollution control materials shall be stored in a safe location on site in close proximity to the storage and waste areas. This material is to be used to contain and clean up pollution for that care shall be taken to dispose of any absorbent materials properly. They shall not be washed away. The Site HSE Manager shall keep stocks well maintained and replenished. Spill Response materials shall include the following:
Sand / Sand bags / Buckets and Shovels / Storage Containers
Sand is one of the most versatile containment materials which can be used to soak up spillages of oil, chemicals and used in sand bags to block off substances from sensitive areas or channel them to a predetermined collection point. Sand stocks must be dry and buckets with shovels readily available. Mechanical loading shovels, excavators and dump trucks may also be available for sand distribution and clean up. Storage containers for contaminated materials and earth shall be bund, located in the waste storage area, labelled and treated as hazardous waste.
Waste Management
It is Contractor’s policy to minimise and reuse / recycle waste materials whenever possible and to dispose of remaining wastes in accordance with this Procedure.
Before wastes can be disposed of appropriately, these first need be categorised and segregated. This in practice is often made difficult due to the wide range of solid, chemical and effluent waste that needs to be segregated stored and disposed of. The Site Manager is held responsible for the allocation of a trained official to guide and control the classification, storage, handling, transport and disposal of wastes.
Waste can generally be classified as either:
Domestic and municipal waste
Non-hazardous industrial waste
Hazardous waste.
In table 2, over, the storage and disposal methods for re-usable / recyclable materials, domestic waste, non-hazardous construction waste, hazardous waste and waste water and sanitary waste are described.
Table 2: Waste Storage and Disposal Controls
Category
|
Storage
|
Disposal
|
All Wastes
|
A specific area to be designated for storage of waste before it is disposed off site.
Selected sites should stand away from water bodies, drainage ditches and be located on hard-core to minimise the risk of soil contamination.
Containers be bunded where necessary.
Fire prevention systems and pollution control equipment shall be provided for storage facilities where necessary to prevent fires or the releases of hazardous materials to the environment.
Storage areas should be made inaccessible to animals and visitors.
Storage containers shall be of sufficient size and number to contain all solid wastes generated between collections.
|
Waste shall be transported to the designated area agreed with Local Authorities which is the concerned Municipality.
Disposal of waste should take place at the designated area as necessary supervised by the Local Authorities.
Vehicles delivering waste to the disposal area should be covered where necessary to prevent dropping, leaking, sifting or blowing of solid waste from the vehicle.
Any spillages or waste lost from disposal vehicle en route to the disposal site should be promptly cleaned up.
Before starting work, the HSE Manager shall confirm that drivers have specialised training related to the handling and disposal of their cargo.
The HSE Manager shall maintain a working file keeping a record of the waste being disposed. This shall include date, time, type of waste, approx. volume of waste, and disposal method.
The landfill and incineration site shall be periodically inspected.
|
Re-usable / Recyclable
Timber
Metals
Paper
|
Re-usable material shall be kept in an orderly manner and in an accessible location.
|
The Re-usable materials shall be sent to Yard for appropriate re-cycling
|
Domestic Waste
Food Waste
Domestic Trash
|
An adequate number of containers shall be strategically placed throughout the construction areas and temporary facilities. These should be regularly collected and taken to the main waste storage area.
All food waste shall be properly stored in containers with sealed tops to minimise the possibility of vermin infestation.
|
Domestic waste shall be disposed off through the Municipality facilities.
|
Non-Hazardous Construction Waste
Combustible, e.g. non re-usable timber, card packaging wastes
Non-combustible e.g. concrete etc.
|
Construction debris and demolition material shall not be allowed to accumulate such that it presents an environmental, health and / or safety hazard.
Inert construction waste shall be segregated into combustible and non-combustible.
Flammable substances must be kept away from sources of ignition.
|
Combustible waste shall be taken to the Municipality Incineration area
Non-combustible waste shall be taken to the Landfill area.
|
Hazardous Waste:
According to UN classification hazardous wastes can be categorized as follows:
Explosives
Gases (including toxic and flammable gases)
Flammable liquids including solvents
Flammable solids
Oxidizing agents and organic peroxides
Toxic and harmful substances including toxic metals
Radioactive
Corrosives, including acids and alkalis
Other dangerous substances.
Hazardous wastes generated on site may include:
Contaminated Land
Chemical Wastes including cleaning fluids, lubricants, paints, dye, coating substances, solvents, corrosion inhibitors, biocides, emulsions etc.
Batteries/ Capacitors
Hydrocarbon Waste
Fire extinguishants
|
The Site Manager shall confirm that a trained official is allocated to guide and control the classification, storage, handling, transport and disposal of wastes.
Hazardous waste shall be retained in a secure area with an impervious bunded base.
The area shall be away from sources of ignition.
This area shall be at least 17m away from water bodies and drainage ditches.
Different types of hazardous waste shall be stored separately to avoid adverse chemical reactions and facilitate eventual treatment.
Hazardous waste shall be stored separately from non-hazardous waste.
Hazardous waste shall be stored in tightly closed leak-proof containers made of or lined with materials that are compatible with the hazardous waste to be stored. Containers shall be clearly marked with appropriate warning labels to accurately describe their contents and detailed safety precautions. Labels shall be waterproof, securely attached and written in Local language and English. Where ever possible chemicals should be kept in their original container.
Hazardous chemicals shall be stored and handled in accordance with the manufacturers Material Safety Data Sheet (MSDS).
Spill prevention measures shall be adhered to.
The Site HSE Manager shall maintain a register of all hazardous waste and disposal methods. Safety Data sheets shall be consulted by the Site HSE Manager.
Equipment, materials and skills shall be readily available to deal with spillages.
Washing facilities shall be available.
|
Hazardous waste shall be disposed of in the area designated by municipality. It shall remain segregated and in the labeled storage containers.
The HSE Manager shall maintain a register of all hazardous waste and disposal methods. Safety Data sheets shall be consulted the HSE Manager.
The general points above in the ‘ALL WASTES’ section apply.
Incompatible hazardous wastes shall not be transported together.
|
Sanitary Waste and Waste Water
Waste water and sewage arising from the camp.
|
Storage / Treatment
Fresh water supplies shall be segregated from wastewater in accordance with Health Requirements of Contract Documents.
No wastewater shall be injected into the groundwater.
All wastewater shall be allowed for settling the silt before allowing to drain to the ground
All camp units shall be connected to a sewage main which run through a PVC pressure line to a treatment system located adjacent to camp.
The treatment system shall be based upon the use of an extended aeration-activated sludge process with an aeration system and solids separation using settlement, shall consist of twin streams each with adequate capacity. All treated effluent shall gravitate to a chlorine contact tank where chlorination takes place to achieve a chlorine residual of 0.5 – 1.0 ppm prior to passing to a designated collection basin located adjacent to the camp.
The facilities shall be maintained by contractor to minimise interruption.
|
The treated effluent water shall be used for irrigation and dust control after it has been analysed to confirm that it is safe for these purposes utilisation.
The sewage treatment plant shall be erected and commissioned operational during the first phase of camp occupancy.
|
Dust and Emissions
The most prevalent construction emission is fugitive dust, however, emissions of Carbon mono-oxide “CO” and related exhaust gases are likely to emerge from diesel generators as well as from activities such as on-site painting, re-fuelling of equipment, application of adhesives, waterproofing chemicals and the incomplete combustion of fuel in construction equipment. Note that none of the planned activities shall cause the release of H2S gas.
The Dust and Emissions occurrence must be controlled during construction to an acceptable level by the following controllable suggestions:
Avoid unnecessary idling of vehicles and machinery.
Fuel, paint and chemical containers be kept sealed when not directly in use.
All vehicles and Construction Plant be properly maintained to minimise excessive exhaust emission. Where possible, engines shall be located away from work areas. Should problems arise, for example defective equipment, which result in generation of fumes, gases or odours on-site, operators be instructed through their HSE Awareness Training to shut down and notify their supervisor to facilitate the appropriate mitigation response.
Dust be controlled as far as is practicable. Control measures can significantly help minimise dust in most cases, apart from in the case of sand storms. If a severe sand storm occurs, the Site Manager should decide if work needs to shut down. After the storm, the roads should be cleaned. Fugitive dust emissions should be minimised by implementing the following controls:
Water spraying. This shall be conducted at a frequency to keep the surfaces moist. Treated wastewater or ground water shall be used for this purpose.
All the concerned persons shall be required to fully cover with sheeting or spray water on open-bodied trucks hauling sand, gravel or soil between on-site and off-site areas. Any transgressions should be immediately brought to the attention of the hauler concerned by the Site HSE Manager. Failure to comply with this requirement shall result in the offender being prevented from accessing the site. If sandblasting operations are required, these operations should be located and scheduled so as to minimise noise and dusting effects on adjacent work areas.
Excavation faces not being worked should, if required, be moistened.
Deliveries of finely ground materials should be in bag form or stockpiled in specified locations where the material can be suitably covered. Minimum drop heights shall be used during material transfer. The roads around the site particularly at the site entrance shall be monitored on a regular basis. These shall be kept as clear from dust and dirt as is practicable. Should it found to be necessary, the road in the vicinity of the site entrance shall also be swept.
Construction personnel shall be required to enter the site over prepared surfaces and park in designated lots. Should problem areas arise which result in excessive dust generation on-site, workers should be instructed through their HSE Awareness Training to notify their supervisor to facilitate the appropriate response.
Traffic
The following traffic controls shall apply:
Construction area access shall be limited to only for construction vehicles.
Non-essential vehicles parking on site shall be restricted to designated areas.
Site access shall be limited to established roadways and traffic shall be routed to the site avoiding residential areas as far as is practicable.
The majority of construction vehicles shall be restricted to designated parking areas for that parking regulations be established and enforced.
All road surfaces be maintained in safe and passable conditions.
Vehicle washing facilities be on site.
Environmental Friendly Practices Environmental Friendly Construction Practices
Follow all permit and environmental mitigation requirements.
Stay within project boundary. Watch for and avoid flagged exclusion zones onsite. Leave wildlife and vegetation alone. Conduct with care project activities that can affect wildlife and vegetation (e.g. clearing) to avoid unnecessary disturbance. Do not dump waste in streams, ponds, lakes, rivers, wetlands, natural drainages or other sensitive areas.
Implement and maintain erosion control and storm water measures as appropriate such as drainage ditches and trenches to divert flows away from active work areas, structures to prevent situation from reaching surface waters and sedimentation ponds to settle out storm water particulates.
Place drip pans under all standing mobile equipment.
Respond to spills by stopping the source of the spill and immediately notifying the supervisor. Contain any spill and clean it up using absorbent materials. Do not rinse spill away. Document, report type and quantity of spilled material, date, time, and cause of spill and cleanup as required.
Maintain equipment in proper operating condition. Stockpile overburden, spoil, and fill at least 50 feet from surface water and wetlands whenever possible.
Recycle treated wastewater as dust control if allowed and where practicable. Avoid using oil as a dust suppressant.
Store wastes in properly designated areas. Label all containers accurately. Store hazardous waste securely in closed containers. Ship hazardous wastes to appropriate treatment and disposal facilities per local requirements.
Do not burn anything except untreated wood.
Recycle / reuse welding rods, used batteries, used oil, solvents, paints, paper, glass, scrap wood or metal, where required and as much as possible.
Immediately stop work and notify the supervisor if human remains or archaeological artefacts are found.
Immediately stop work and notify your supervisor, if contaminated soil (unusual colouration or odour) or underground storage tanks are discovered.
Ask your Supervisor or Environment, Safety and Health representative if you have any questions.
--------------------------------
Chapter 15
Commercial
Sub Contracts
It is intended for the sake of information exchange as well as dissemination to the readers particularly those who are aspiring to appear for PE certification examinations. The data included herein is not claimed to be entirely original in essence. Based on the experience, a collection has been done & amended to my understanding of the practical aspects of contracts & engineering in the field as well as in designs. The main contract forms relating to the EPIC contracts have not been included for that constitutes a top serial level document & young engineers may not draw much benefit but nevertheless, a practical understanding of the subject may be drawn from the provided information for all examination as well as practical purposes.
-------------------------------------------------------------------------------------------------------
Contracting Co.
Plant Project
Seller technical services agreement
SubContract:
This subcontract is entered into as of the date day of month, 2025, between Contracting Co Ltd. (hereinafter called "Contractor") and ‘name a company’ organised and existing under the laws of country with its principal offices located in address (hereinafter called "Subcontractor").
Whereas, Contractor has been awarded the project for the building of Facility for Petrochemical Industry located at ‘unknown’;
And whereas, Subcontractor acknowledges that it has sufficient knowledge and understanding of the nature, the location and the infrastructure of the Jobsite:
And whereas, the Subcontractor is able to perform all specified Works in accordance with the terms and conditions of this subcontract;
Now therefore, it is agreed as follows:
Subcontractor's Work/s consist/s of provision of technical assistance and direction to Contractor during the installation and/or commissioning of Subcontractor furnished Products supplied under Purchase Order (Relevant Purchase Order Number), Equipment Description and all associated requirements which are more particularly described in relevant Exhibits. All Works specified below shall be performed by the Subcontractor in accordance with all the provisions of this subcontract, consisting of the following Subcontract Documents:
Subcontract Form of Agreement
EXHIBIT "A" General Conditions
EXHIBIT "B" Special Conditions
EXHIBIT "C" Statement of Work and Compensation/Consideration
Based on the satisfactory performance by Subcontractor of this subcontract, Contractor shall pay to Subcontractor as full consideration, agreed compensation in accordance with the prices set forth in Exhibit "C" and with the payment provisions of this subcontract.
This subcontract embodies the entire agreement between Contractor and Subcontractor and supersedes all other previous writings. The parties shall not be bound by or liable for any statement, representation, promise, inducement or understanding not set forth herein.
Contractor: Subcontractor:
Contracting Co. Ltd. ABC
Authorised Authorised
Signature: Signature:
Print Name: Print Name:
Print Title: Print Title:
Contracting Co. Ltd.
Plant Project
EXHIBIT "A"
Share with your friends: |