For highway construction oregon department of transportation salem, oregon


SP00196 (2015 Specifications: 11-13-14)



Download 1.02 Mb.
Page8/28
Date29.01.2017
Size1.02 Mb.
#12507
1   ...   4   5   6   7   8   9   10   11   ...   28

SP00196 (2015 Specifications: 11-13-14)



SECTION 00196 - PAYMENT FOR EXTRA WORK



(Any modifications to this Section will require Department of Justice approval. (See the Specification and Writing Style Manual, Chapter 3.))
Comply with Section 00196 of the Standard Specifications.


SP00197 (2015 Specifications: 11-13-14)



SECTION 00197 - PAYMENT FOR FORCE ACCOUNT WORK



Any modifications to this Section will require Department of Justice approval. (See the Specification and Writing Style Manual, Chapter 3.))
Comply with Section 00197 of the Standard Specifications.



SP00199 (2015 Specifications: 11-13-14)



SECTION 00199 - DISAGREEMENTS, PROTESTS, AND CLAIMS



(Any modifications to this Section will require Department of Justice approval. (See the Specification and Writing Style Manual, Chapter 3.))
Comply with Section 00199 of the Standard Specifications.


SP00210 (2015 Specifications: 11-13-14)



SECTION 00210 - MOBILIZATION



(Follow all instructions. If there are no instructions above a subsection, paragraph, sentence, or bullet, then include them in the project. The specifications may be modified to include project specific specifications, but all additions, deletions, or modifications must be sent to the ODOT Technical Resource and Senior Specifications Engineer for review and approval.)
Comply with Section 00210 of the Standard Specifications.



SP00220 (2015 Specifications: 06-11-15)



SECTION 00220 - ACCOMMODATIONS FOR PUBLIC TRAFFIC



(Follow all instructions. If there are no instructions above a subsection, paragraph, sentence, or bullet, then include them in the project. The specifications may be modified to include project specific specifications, but all additions, deletions, or modifications must be sent to the ODOT Technical Resource and Senior Specifications Engineer for review and approval.)
Comply with Section 00220 of the Standard Specifications modified as follows:
00220.02  Public Safety and Mobility- Add the following bullets to the end of the bullet list:


  • When construction equipment is operating in a closed lane, protect traffic using a truck mounted impact attenuator (TMA). Place the TMA in the closed lane in advance of the equipment, located as recommended by the manufacturer and approved by the Engineer. If the TMA is not available when the work requires its use, postpone the work until the TMA is available.




  • Provide written notification to the Engineer the week prior of proposed work.



  • Install detour signage no more than two weeks prior to date of active closure. Remove detour signage within two weeks of final closure.



(Use the following subsection .02 when the pre-construction speed is greater than 35 mph and there is trench excavation or other excavation work to be performed.)
00220.02  Public Safety and Mobility - Add the following bullet to the end of the bullet list:
When performing trench excavation or other excavation across or adjacent to a Traffic Lane on a roadway having a preconstruction posted speed greater than 35 mph, backfill the excavation, install surfacing, and open the roadway to traffic by the end of each work shift. Install a "BUMP" (W8-1-48) sign approximately 100 feet before the backfilled area and a "ROUGH ROAD" (W8-8-48) sign approximately 500 feet ahead of the "BUMP" sign. If this requirement is not met, maintain all necessary lane or shoulder closures and provide additional TCM, including flagging, at no additional cost to the Agency. Do not use temporary steel plating to reopen the roadway.
00220.03(a)  Over-Dimensional Vehicle Restrictions Add the following to the end of this subsection:
Oversize Load Accommodation - During times of anticipated over-dimensional vehicles presence, maintain a minimum usable roadway width for the highways as shown below, to allow for over-dimensional vehicles to pass through the work area.
DAYTIME SINGLE LANE (ft.) TWO LANE (ft.)
I-84 22 28

US26 (Sunset Hwy) 19 28

Tualatin Valley Highway 16 28
NIGHTTIME
All Roadways 16 28
Anticipate over-dimensional vehicles during the following sunrise and sunset periods:


  • January: between 7:00 a.m. and 5:30 p.m.

  • February: between 6:30 a.m. and 6:00 p.m.

  • March: between 7:00 a.m. and 8:00 p.m.

  • April: between 8:00 a.m. and 8:00 p.m.

  • May: between 8:00 a.m. and 8:00 p.m.

  • June: between 8:00 a.m. and 8:00 p.m.

  • July: between 8:00 a.m. and 8:00 p.m.

  • August: between 8:00 a.m. and 8:00 p.m.

  • September: between 6:00 a.m. and 8:00 p.m.

  • October: between 7:00 a.m. and 7:00 p.m.

  • November: between 6:30 a.m. and 5:30 p.m.

  • December: between 7:00 a.m. and 5:00 p.m.


(Use the following subsection .40(e-1) only when modifying closed lane restrictions. Fill in the blank with the highway name and insert the route number (e.g. I-5, US97) in the parentheses. When closed lane restrictions apply to a road that is not a highway, delete "Highway (_Route No._)" and insert the street name. Submit a Traffic Analysis Work Request Form to the Region Traffic Office for the closed lane restrictions. It's available on the web at http://www.oregon.gov/ODOT/HWY/TS/Pages/resources.aspx. Copy and paste the paragraph and bullet list as necessary for additional highways or roads.)
00220.40(e-1)  Closed Lanes - Replace this subsection, except for the subsection number and title, with the following:
One or more Traffic Lanes may be closed on the _______ Highway (_Route No._) when allowed, shown, or directed during the following periods of time except as indicated in 00220.40(e2):

00220.40(e-1)  Closed Lanes - Replace this subsection, except for the subsection number and title, with the following:
State Highways:

One or more traffic lanes may be closed on the Columbia River Highway (I-84), Sunset Highway (US26), and Tualatin Valley Highway when allowed, shown, or directed during the following periods of time except as indicated in 00220.40(e2):




  1. Columbia River Highway (I-84) and Sunset Highway

For single lane closures:


  • Between 12:01 a.m. and 5:30 a.m. and between 8:00 p.m. and midnight, Monday through Friday

  • Between 12:01 a.m. and 8:00 a.m. and between 8:00 p.m. and midnight, Saturday

  • Between 12:01 a.m. and 9:00 a.m. and between 8:00 p.m. and midnight, Sunday

For two-lane closures:



    • Between 12:01 a.m. and 5:00 a.m. and between 10:00 p.m. and midnight, Monday through Friday

  • Between 12:01 a.m. and 7:00 a.m. and between 11:00 p.m. and midnight, Saturday

  • Between 12:01 a.m. and 8:00 a.m. and between 10:00 p.m. and midnight, Sunday




  1. Tualatin Valley Highway

Westbound -



  • Between 12:01 a.m. and 6:30 a.m., between 9:00 a.m. and 3:00 p.m., and between 7:30 p.m. and midnight, Monday – Friday

  • Between 12:01 a.m. and 9:00 a.m. and between 7:00 p.m. and midnight, Saturday

  • Between 12:01 a.m. and 10:00 a.m. and between 7:00 p.m. and midnight, Sunday

Eastbound -



  • Between 12:01 a.m. and 5:30 a.m., between 9:00 a.m. and 3:00 p.m., and between 7:30 p.m. and midnight, Monday – Friday

  • Between 12:01 a.m. and 9:00 a.m. and between 7:00 p.m. and midnight, Saturday

  • Between 12:01 a.m. and 10:00 a.m. and between 7:00 p.m. and midnight, Sunday

Shoulder closures on Tualatin Valley Highway westbound or eastbound will be allowed at any time, Monday – Sunday.


 during the following periods:
Arterial Roadways:
Do not close any travel lanes and remove all barricades and objects from the roadway during the following periods:

• Between 6:30 a.m. and 9:00 a.m. and between 3:30 p.m. and 6:30 p.m., Monday

through Friday
• The following are arterial roadways:
• Cornelius Pass Road

• Cornell Road

• Baseline Road

• Farmington Road

• 185th Avenue

• Murray Boulevard

• Scholls Ferry Road

• Walker Road

• Hart Road (west of Murray Boulevard)

• 125th Avenue (north of Scholls Ferry Road)

Hall Boulevard

• Evergreen Parkway


Collector Roadways:
• Between 7:00 a.m. and 8:30 a.m. and between 4:00 p.m. and 6:00 p.m., Monday

through Friday


• The following are collector roadways:

• Imbrie Drive

• Allen Boulevard

• Hart Road (east of Murray Boulevard)

• Jenkins Road

• Aloclek Drive

• Wilkins Street

• Quantama Road

• Lois Street

• Frances Street

• Johnson Street

• Brookwood Avenue

• Millikan Way

Cedar Hills Boulevard

• Lombard Avenue

• 6th Street

• Brockman Street

• 121st Avenue


• Nimbus Avenue
(Use the following subsection .40(e-2-b) to list special events. List the names, times, and dates of the events.)
00220.40(e-2-b)  Special Events - Add the following to the end of this subsection:
The following special events will occur during this Project:
___________________

00220.40(e-2-b)  Special Events - Add the following to the end of this subsection:
The following special events will occur during this Project:


  • Starlight Parade (June 2016 and 2017)

  • Rose Festival Grand Floral Parade (June 2016 and 2017)

  • Providence Bridge Pedal (August 2016 and 2017)

  • Race for the Cure (September 2016 and 2017)

  • Portland Marathon (October 2016 and 2017)

  • Oregon International Air Show in summer or fall 1026 and again in summer or fall 2017


All event schedules will be verified by the Contractor.


00220.40(e-2-c) Moda Center Special Events – Do not close more than one travel lane, or any entrance or exit ramp on I-5 before 11:30 p.m. when there are Portland Trailblazers games or evening concerts at the Moda Center.
Providence Park Special Events – Do not close any ramps or travel lanes on I-5, I-405, or Sunset Highway (US 26) westbound before 11:30 p.m. when there are Portland Timber games at the Providence Park.
Zoo Lights and Summer Zoo Concerts – Do not close any travel lane on the Sunset Highway (US26) or its ramps at the Zoo interchange before 11:30 p.m. when there are Zoo Lights and Summer Zoo Concerts at the Oregon Zoo.
(Use the following lead-in paragraph when adding either of the following subsections .40(f) or .40(g). Remove the "(s)" or remove the parentheses as needed.)
Add the following subsection(s):
(Use the following subsection .40(f) when blasting, erecting bridge girders, erecting sign structures, or conducting other short duration work that can be done in periods not exceeding 20 minutes. Contact the Region Traffic Analyst for designated peak hours and days when work is allowed. Add applicable items and delete non-applicable items in the first sentence. Do not change the subsection alpha character (keep it "(f)".)
00220.40(f)  Limited Duration Road Closure - The Contractor will be permitted to close all Traffic Lanes for periods not to exceed 20 minutes in duration during blasting or erecting bridge girders and sign structures over the Traffic Lanes or _____________. This work will only be permitted between the hours of _________ and _________ on the _______________ highway.
Succeeding roadway closures will not be allowed until traffic clears from a preceding closure.
00220.40(f)  Limited Duration Road and Ramp Closure - The Contractor will be permitted to close all traffic lanes on the Sunset Highway (US26) in both directions and the following ramps for installation of a new sign bridge over the traffic lanes.


  • Zoo Interchange ramps

  • I-405 northbound and southbound ramps to US26 westbound

  • US26 eastbound to I-405 northbound and southbound ramps

  • US26 eastbound exit-ramp to Market St.

  • US26 eastbound exit-ramp to Jefferson St.

  • Jefferson St. entrance ramp to US26 westbound

  • Clay St. entrance ramp to US26 westbound

This work will only be permitted for a maximum of two (2) nights:




  • between 11:30 p.m. and 4:30 a.m., Monday through Friday

  • between 11:30 p.m. Friday and 6:00 a.m. Saturday

  • between 11:30 p.m. Saturday and 7:00 a.m. Sunday

  • between 11:30 p.m. Sunday and 4:30 a.m. Monday

Do not close the roadways until all materials and equipment are on hand or guaranteed to be delivered so that the work can be done in an efficient manner with a minimum period of road closure.


No road closure will be permitted until the area is signed according to the TCP and the requirements of Section 00225.

00220.40(g)  Limited Duration Road and Ramp Closure - The Contractor will be permitted to close all Traffic Lanes on I-84 in both directions and the following ramps for installation of two new sign bridges over the traffic lanes.


  • NE Cesar Chavez entrance ramp to I-84 eastbound

  • I-84 eastbound exit-ramp to NE 58th Ave

  • NE 60th Ave entrance ramp to I-84 eastbound

  • I-84 eastbound exit-ramp to NE 68th Ave

  • I-205 southbound entrance ramp to I-84 westbound

  • NE Haley St. entrance ramp to I-84 westbound

This work will only be permitted for a maximum of two (2) nights:




  • between 11:30 p.m. and 4:30 a.m., Monday through Friday

  • between 11:30 p.m. Friday and 6:00 a.m. Saturday

  • between 11:30 p.m. Saturday and 7:00 a.m. Sunday

  • between 11:30 p.m. Sunday and 4:30 a.m. Monday

Do not close the roadways until all materials and equipment are on hand or guaranteed to be delivered so that the work can be done in an efficient manner with a minimum period of road closure.


Do not close I-84 and Sunset Highway (US26) on the same night.
No road closure will be permitted until the area is signed according to the TCP and the requirements of Section 00225.




Download 1.02 Mb.

Share with your friends:
1   ...   4   5   6   7   8   9   10   11   ...   28




The database is protected by copyright ©ininet.org 2024
send message

    Main page