For highway construction oregon department of transportation salem, oregon



Download 1.43 Mb.
Page10/38
Date29.01.2017
Size1.43 Mb.
#12506
1   ...   6   7   8   9   10   11   12   13   ...   38



(This page is only used to provide a list of standard drawings to the specification writer for listing on the plan title sheet. Remove this page before advance and final.)



NUMBER OF TRAFFIC CONTROL PLAN SHEETS: _____



(Add or delete Standard Drawings, as applicable.)



To be accompanied by Standard Drawings:



RD410 Guardrail Parts (Thrie Beam)

RD420 Energy Absorbing Terminal

RD425 Non Energy-Absorbing Terminal 3' or 4' Flare



RD500 Precast Concrete Barrier Pin and Loop Assembly

RD510 Concrete Barrier Terminal

RD530 Guardrail Transition to Concrete Barrier

RD535 Concrete Barrier (Modified) Around Median Obstacle

RD545 Precast Tall (42") Concrete Barrier

RD560 Cast-in-Place Tall Barrier Transition to Standard Concrete Barrier



BR203 Transition Concrete Bridge Rail to Guardrail



TM204 Flag Board Mounting Details

TM211 Signing Details US & Interstate Route Shields

TM212 Signing Details Oregon Route Signs

TM570 Traffic Delineators

TM575 Traffic Delineator Installation for Freeways

TM576 Traffic Delineator Installation for Non-Freeways

TM670 Wood Post Sign Supports

TM671 3 Second Gust Wind Speed Map

TM677 Sign Mounts

TM681, TM687, TM688 Perforated Steel Square Tube (PSST)Sign Support Installation and Foundation

TM800 Tables, Abrupt Edge and PCMS Details

TM810 Temporary Pavement Markers

TM820 Temporary Barricades

TM821 Temporary Sign Supports

TM830 Temporary Concrete Barrier & Rumble Strip Details

TM831, TM832 Temporary Impact Attenuators

TM840 Closure Details

TM841 Intersection Work Zone Details

TM842 Signalized Intersection Details

TM843 Multi-Lane Signalized Intersection Details

TM844 Temporary Pedestrian Access Routing

TM850 2 Lane, 2-Way Roadways

TM851, TM852, TM853 Non-Freeway Multi-Lane Sections

TM860, TM861, TM862 Freeway Sections

TM870 Bridge Construction

TM871 Blasting Zones

TM880 Freeway or Divided Highway Speed Reduction (Paving

Operations)





SSECTION 00234 - TEMPORARY PEDESTRIAN ACCESS


Section 00234, which is not a Standard Specification, is included in this Project by Special Provision.
Description
00234.00 Scope - This work consists of designing, constructing, maintaining, and removing temporary pedestrian access required for staging and constructing of permanent sidewalks and ramps as shown or directed.

00234.01 Pedestrian Access Disruption and Restoration - For each corner of each intersection:


  • Demolish existing sidewalk and curb ramps and place ADA compliant temporary ACP surfacing (temporary access) in the same work shift.

  • Keep the existing pedestrian access including concrete walks, curb ramps, crosswalks, and push buttons fully accessible, operational and open for pedestrian use until demolition of existing access and construction of temporary access.

  • Temporary pedestrian access may be used for at most 100 calendar days.

  • Complete construction of final pedestrian access as shown, including concrete walks, curb ramps, pedestrian signals and push buttons, and final or temporary crosswalks within 100 calendar days after the existing pedestrian access was disrupted.



00234.05 Submittals - Submit the following to the Engineer for approval 14 Calendar Days before the pre-construction conference:
Temporary pedestrian access plans that meet the accessibility requirements in Part 6 of the MUTCD, the American with Disabilities Act (ADA), ODOT Standard Drawing TM844, and specification section 00220.02. Provide stamped working drawings according to 00150.35 which Iinclude the following in the plans:


  • - Temporary pedestrian access to each corner of the intersection. Do not route pedestrians to adjacent intersections or mid-block for crossing the street.

  • - Pedestrian traffic control devices and layout, including pedestrian channelizing devices

  • Temporary movable ADA compliant curb curb ramp design design and non-slip surfacing materials (if necessary)

  • - Striping modifications

  • - Signal modifications

  • - Access to bus stops and private pedestrian facilities




  • - Temporary surfacing materials


Materials
00234.10  Temporary Surfacing - Provide ACP surfacing meeting the requirements of 00745.50.
Construction
00234.40  Pedestrian Access Construction --– Construct temporary pedestrian accesses with temporary ACP per submitted and approved plans. This work includes but is not limited to the following:


  • Temporary pedestrian accesses or detours and surfacing that are within the available right-of-way and construction easements

  • Temporary signing, pedestrian channelizingation devices and other TCD needed

  • Temporary ADA ramps, including curb ramps paved with temporary AC pavement and moveable ADA compliant curb ramps

Removing and reinstalling existing curbs and sidewalks

Removing and restoring existing landscaping

Installing and removing temporary pavement markings

Installing temporary pedestrian push buttons, if required by the approved temporary pedestrian access plans



  • Other features as required by the approved plans to provide safe access for pedestrians.


00234.41 Pedestrian Access Disruption and Restoration - For each corner of each intersection:


  • Demolish existing sidewalk and curb ramps and place ADA compliant temporary AC pavement surface (temporary access) in the same work shift. Utilize temporary movable ADA compliant curb ramps per approved plan as needed while existing ramps are inaccessible.

  • Keep existing pedestrian accesses, including sidewalks, curb ramps, crosswalks, pedestrian signals and push buttons fully accessible, operational and open for pedestrian use until construction of temporary accesses have been completed.

Temporary pedestrian accesses may be in place for a maximum of 100 consecutive calendar days.

  • Once demolition of the pedestrian facilities has begun, complete construction of final pedestrian accesses as shown, including concrete sidewalks, curb ramps, pedestrian signals and push buttons, and final or temporary crosswalks within 100 consecutive calendar days.



Maintenance
00234.60  Maintenance - Maintain temporary pedestrian accesses and detour surfaces according to 00220.02, 00220.60, and 00225.
Maintain continuous pedestrian walkway and access to crosswalks and pushbuttons via a route paved with temporary AC pavement surfacing and meeting the requirements of the ADA.
Finishing and Cleaning Up
00234.70  General - When temporary pedestrian accesses are no longer needed, do the following:


  • Remove themtemporary pedestrian access facilities

  • Restore anythe area on which the temporary accesses occupied, not within the limits of final pedestrian accesses, to the original ground contours and to original conditions.




  • Dispose of material waste according to 00290.20.


Measurement
 - No measurement of quantities will be made for work performed under this Section.
It is estimated that the following approximate quantities of materials will be required:
Material Amount

Asphalt Concrete Mixture 85 ton



Payment
00234.90  Payment - The accepted quantities of work performed under this Section will be paid for at the Contract lump sum amount for the item "Temporary Pedestrian Access". Payment will be payment in full for furnishing, installing, moving, maintaining, inspecting, and removing temporary movable ADA compliant curb ramps and temporary ACP surfacing. Payment will also include moving pedestrian channelizing devices and other items as necessary for temporary pedestrian routing.
Partial payments for this item will be made as follows:


  • When the initial Contractor developed Temporary Pedestrian Access Plans are completed and accepted, and the initial pedestrian access is installed….25%

  • When 50% of the Contract is complete and Temporary Pedestrian Accesses are maintained according to the Temporary Pedestrian Access Plans, excluding advances on materials….25%

  • When 75% of the Contract is complete and Temporary Pedestrian Accesses are maintained according to the Temporary Pedestrian Access Plans, excluding advances on materials….25%

  • At completion of work covered by this section…25%

Temporary traffic control measures and traffic control devices used for controlling pedestrian access, including but not limited to; signs, barricades, channelizing devices, delineation, striping, and illumination will be paid for at Contract unit prices when pay quantities are listed in the Contract Schedule of Items. Other temporary traffic control measures and devices that are not listed in the Contract Schedule of Items are incidental to the item “Temporary Pedestrian Access”.

Payment for temporary signs will be according to 00225.91. Payment for temporary barricades and pedestrian channelizingation devices will be according to 00225.92. All other items and work will be included in the Contract lump sum amount for the item “Temporary Protection and Direction of Traffic” according to 00225.90(a-2).