PROJECT: RENOVATION OF THE FACADES AND COOLING/HEATING INSTALLATION IN PCT BUILDING (CMP 3)
Project Manager Mr. A. FAVERO
EXPECTED RESULT
IX.1 Effective, efficient, quality and customer-oriented support services both to internal clients and to external stakeholders
OBJECTIVES, SCOPE AND APPROACH- BACKGROUND
-
The project objectives are twofold: (i) a complete replacement of the false ceiling installation for the cooling and heating system in the upper floors of the PCT Building, and (ii) a major renovation of structural elements of all the facades of that Building (in other words, the windows per se are generally not at stake). It has been determined in recent years that the minor low-scale reactive repairs – in case of breakdowns and un-controllable excessively high or low temperature inside the offices – which have been ongoing for about 10 years, were no longer sustainable. Furthermore, a number of components of the current cooling/heating installation are no longer available on the market and spare parts can no longer be purchased, which would in the short-term put at risk the viability of the whole cooling and heating installation in the Building. The wasted energy consumption caused by the defective systems and installations and by the defective structural elements of the facades is significant and will only continue to increase year after year. A technical audit of the cooling and heating installation had been carried out in 2011; a technical audit of the facades was carried out during the first semester of 2013.
-
The expected results of the renovation are fully operational and reliable cooling and heating installation and facades, and significant energy consumption reduction by eliminating the current wastes.
-
The objectives of the project are to: (i) reduce energy loss (facades); (ii) reduce energy consumption (thermal false ceilings and facades); (iii) improve technical facilities to reduce the need for maintenance (thermal false ceilings and facades); (iv) improve the comfort of occupants; (v) use new, more environmentally-friendly technology; and (vi) modernize for longer life-cycles (thermal false ceilings).
OVERVIEW OF PROGRESS IN 2014 (KEY MILESTONES)
-
In 2014, the following progress was made:
-
drafting and launch of the call for expressions of interest for the pilot/architect;
-
completion of the short-listing and evaluation of the call for expressions of interest for the pilot/architect mandate; and
-
drafting of the technical specifications for the call for tenders for the pilot/architect.
-
Due to the delayed completion (from beginning 2014 to September 2014) of the new WIPO Conference Hall, the start of the project was delayed by nine months relative to the original plan. The timeline for the project has been extended to 2018, as reflected in the tables below.
BENEFITS REALIZATION
Expected Benefits 2017
|
Expected Benefits 2018
|
Partial improvements in technical facilities
|
Full improvement in technical facilities
|
Partial improvement in the comfort of occupants
|
Full improvement in the comfort of occupants
|
|
Partial reduction in energy loss thanks to improved facades
|
|
Partial reduction in energy consumption due to new thermal false ceilings
|
|
Increased life-cycle of new thermal false ceilings
|
|
Reduced cost in corrective maintenance due to new thermal false ceilings
|
RESOURCE UTILIZATION
Project Budget Utilization
(In Swiss francs, as at December 31, 2014)
Project Name
|
Project Budget
|
Actual Expenditure to Date
|
Actual Budget Utilization
|
Implementation Progress Rate of the Project
|
Renovation of the facades and cooling/heating installation of the
PCT Building (CMP3)
|
6,000,000
|
0
|
0%
|
2%
|
Project Budget Utilization (by Milestone)
(In Swiss francs, as at December 31, 2014)
Key Milestone
|
Project Budget
|
Actual Expenditure to Date
|
Actual Budget Utilization
|
Implementation Progress Rate by Milestone
|
Award of contract to the pilot/architect
|
124,000
|
0
|
0%
|
30%
|
Award of contracts to agents
|
900,000
|
0
|
0%
|
10%
|
Internal and external resource commitment
|
867,000
|
0
|
0%
|
-
|
Work and commissioning
|
4,109,000
|
0
|
0%
|
-
|
Total
|
6,000,000
|
0
|
0%
|
|
Project Budget Utilization (by Cost Category)
(In Swiss francs, as at December 31, 2014)
-
Cost Category
|
Project Budget
|
Actual Expenditure to Date
|
Actual Budget Utilization
|
Construction-related costs
|
3,569,000
|
0
|
0%
|
Honoraria
|
1,024,000
|
0
|
0%
|
Internal/external resources
|
867,000
|
0
|
0%
|
Fees
|
120,000
|
0
|
0%
|
Miscellaneous and unforeseen
|
420,000
|
0
|
0%
|
Total
|
6,000,000
|
0
|
0%
|
RISK AND MITIGATION STRATEGIES
Risk
|
Description
|
Risk Mitigation
|
Delay in starting project
|
Project delayed by one year due to the delay in completion of the new WIPO Conference Hall
|
Shift the project’s general schedule
|
Delay in starting works
|
The start of works will depend on the time needed to choose the technical solution, which is not expected before 2016.
|
Shift the works timetable
|
Delay in commissioning the renovation
|
Delay in the works schedule because of the chosen technical solution
Internal logistics for office relocations
|
Appraisal of the choice of technical solution
Appraisal with a view to shortening the schedule
Planning with PCT, Information and Communication Technology (ICT), and Safety and Security Coordination Service (SSCS)
|
Financial risk
|
Insufficient budget to implement the chosen technical solution
Estimated costs higher than the approved budget as a result of the construction market situation during the call for tenders from firms in 2016
|
Review of the choice of technical solution
Request additional funds
|
PROJECT TIMELINE BY MILESTONE
|
2014
|
2015
|
2016
|
2017
|
2018
|
Key Milestone
|
Q1
|
Q2
|
Q3
|
Q4
|
Q1
|
Q2
|
Q3
|
Q4
|
Q1
|
Q2
|
Q3
|
Q4
|
Q1
|
Q2
|
Q3
|
Q4
|
Q1
|
Q2
|
Q3
|
Q4
|
Call for expressions of interest pilot/architect
|
|
|
|
X
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Call for tenders and selection of pilot/architect and engineers
|
|
|
|
|
X
|
X
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Comprehensive study on implementation
|
|
|
|
|
|
|
X
|
X
|
|
|
|
|
|
|
|
|
|
|
|
|
Choice of technical solution
|
|
|
|
|
|
|
|
|
X
|
|
|
|
|
|
|
|
|
|
|
|
Call for tenders from firms
|
|
|
|
|
|
|
|
|
|
X
|
X
|
X
|
|
|
|
|
|
|
|
|
Works
|
|
|
|
|
|
|
|
|
|
|
|
|
X
|
X
|
X
|
X
|
|
|
|
|
Commissioning
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
X
|
X
|
|
|