PROJECT: RENOVATION OF THE FACADES AND COOLING/HEATING INSTALLATION IN PCT BUILDING (CMP 3)



Project Manager Mr. A. FAVERO

EXPECTED RESULT


IX.1 Effective, efficient, quality and customer-oriented support services both to internal clients and to external stakeholders

OBJECTIVES, SCOPE AND APPROACH- BACKGROUND




  1. The project objectives are twofold: (i)  a complete replacement of the false ceiling installation for the cooling and heating system in the upper floors of the PCT Building, and (ii) a major renovation of structural elements of all the facades of that Building (in other words, the windows per se are generally not at stake). It has been determined in recent years that the minor low-scale reactive repairs – in case of breakdowns and un-controllable excessively high or low temperature inside the offices – which have been ongoing for about 10 years, were no longer sustainable. Furthermore, a number of components of the current cooling/heating installation are no longer available on the market and spare parts can no longer be purchased, which would in the short-term put at risk the viability of the whole cooling and heating installation in the Building. The wasted energy consumption caused by the defective systems and installations and by the defective structural elements of the facades is significant and will only continue to increase year after year. A technical audit of the cooling and heating installation had been carried out in 2011; a technical audit of the facades was carried out during the first semester of 2013.

  2. The expected results of the renovation are fully operational and reliable cooling and heating installation and facades, and significant energy consumption reduction by eliminating the current wastes.

  3. The objectives of the project are to: (i) reduce energy loss (facades); (ii) reduce energy consumption (thermal false ceilings and facades); (iii) improve technical facilities to reduce the need for maintenance (thermal false ceilings and facades); (iv) improve the comfort of occupants; (v) use new, more environmentally-friendly technology; and (vi) modernize for longer life-cycles (thermal false ceilings).

OVERVIEW OF PROGRESS IN 2014 (KEY MILESTONES)


  1. In 2014, the following progress was made:

  • drafting and launch of the call for expressions of interest for the pilot/architect;

  • completion of the short-listing and evaluation of the call for expressions of interest for the pilot/architect mandate; and

  • drafting of the technical specifications for the call for tenders for the pilot/architect.




  1. Due to the delayed completion (from beginning 2014 to September 2014) of the new WIPO Conference Hall, the start of the project was delayed by nine months relative to the original plan. The timeline for the project has been extended to 2018, as reflected in the tables below.

BENEFITS REALIZATION




Expected Benefits 2017

Expected Benefits 2018

Partial improvements in technical facilities

Full improvement in technical facilities

Partial improvement in the comfort of occupants

Full improvement in the comfort of occupants




Partial reduction in energy loss thanks to improved facades




Partial reduction in energy consumption due to new thermal false ceilings




Increased life-cycle of new thermal false ceilings




Reduced cost in corrective maintenance due to new thermal false ceilings

RESOURCE UTILIZATION


Project Budget Utilization

(In Swiss francs, as at December 31, 2014)


Project Name

Project Budget

Actual Expenditure to Date

Actual Budget Utilization

Implementation Progress Rate of the Project

Renovation of the facades and cooling/heating installation of the

PCT Building (CMP3)



6,000,000

0

0%

2%



Project Budget Utilization (by Milestone)

(In Swiss francs, as at December 31, 2014)


Key Milestone

Project Budget

Actual Expenditure to Date

Actual Budget Utilization

Implementation Progress Rate by Milestone

Award of contract to the pilot/architect

124,000

0

0%

30%

Award of contracts to agents

900,000

0

0%

10%

Internal and external resource commitment

867,000

0

0%

-

Work and commissioning

4,109,000

0

0%

-

Total

6,000,000

0

0%





Project Budget Utilization (by Cost Category)

(In Swiss francs, as at December 31, 2014)


Cost Category

Project Budget

Actual Expenditure to Date

Actual Budget Utilization

Construction-related costs

3,569,000

0

0%

Honoraria

1,024,000

0

0%

Internal/external resources

867,000

0

0%

Fees

120,000

0

0%

Miscellaneous and unforeseen

420,000

0

0%

Total

6,000,000

0

0%

RISK AND MITIGATION STRATEGIES




Risk

Description

Risk Mitigation

Delay in starting project

Project delayed by one year due to the delay in completion of the new WIPO Conference Hall

Shift the project’s general schedule

Delay in starting works

The start of works will depend on the time needed to choose the technical solution, which is not expected before 2016.

Shift the works timetable

Delay in commissioning the renovation

Delay in the works schedule because of the chosen technical solution

Internal logistics for office relocations



Appraisal of the choice of technical solution

Appraisal with a view to shortening the schedule

Planning with PCT, Information and Communication Technology (ICT), and Safety and Security Coordination Service (SSCS)


Financial risk

Insufficient budget to implement the chosen technical solution

Estimated costs higher than the approved budget as a result of the construction market situation during the call for tenders from firms in 2016




Review of the choice of technical solution

Request additional funds


PROJECT TIMELINE BY MILESTONE








2014

2015

2016

2017

2018

Key Milestone

Q1

Q2

Q3

Q4

Q1

Q2

Q3

Q4

Q1

Q2

Q3

Q4

Q1

Q2

Q3

Q4

Q1

Q2

Q3

Q4

Call for expressions of interest pilot/architect

 

 

 

X

















































Call for tenders and selection of pilot/architect and engineers

 

 

 




X

X











































Comprehensive study on implementation

 

 

 










X

X





































Choice of technical solution

 

 

 
















X


































Call for tenders from firms

 

 

 



















X

X

X

























Works





































X

X

X

X













Commissioning

















































X

X









BUILDINGSRELATED PROJECTS