Advance warning sign spacing is dependent upon the length of the ramp and the exact location of signs is determined in the field. Spacing of the signs should be as long as practicable. A minimum lane width of 12 ft on exit ramps should be maintained.

Section 6G.18 Work in the Vicinity of a Grade Crossing

Standard:

01 When grade crossings exist either within or in the vicinity of a TTC zone, lane restrictions, flagging, or other operations shall not create conditions where vehicles can be queued across the tracks. If the queuing of vehicles across the tracks cannot be avoided, a uniformed law enforcement officer or flagger shall be



provided at the crossing to prevent vehicles from stopping on the tracks, even if automatic warning devices are in place.

SUPPORT


Work in the vicinity of a highway-rail grade crossing is shown in Layout 6J-14.

Guidance:

04 Early coordination with the railroad company or light rail transit agency should occur before work starts.


Section 6G.19 Temporary Traffic Control During Nighttime Hours

Support:


01 Chapter 6D and Sections 6F.74 and 6G.05 contain additional information regarding the steps to follow when pedestrian or bicycle facilities are affected by the worksite.
02 Conducting highway construction and maintenance activities during night hours could provide an advantage when traditional daytime traffic control strategies cannot achieve an acceptable balance between worker and public safety, traffic and community impact, and constructability. The two basic advantages of working at night are reduced traffic congestion and less involvement with business activities. However, the two basic conditions that must normally be met for night work to offer any advantage are reduced traffic volumes and easy set up and removal of the traffic control patterns on a nightly basis.
03 Shifting work activities to night hours, when traffic volumes are lower and normal business is less active, might offer an advantage in some cases, as long as the necessary work can be completed and the worksite restored to essentially normal operating conditions to carry the higher traffic volume during non-construction hours.

04 Although working at night might offer advantages, it also includes safety issues. Reduced visibility inherent in night work impacts the performance of both drivers and workers. Because traffic volumes are lower and congestion is minimized, speeds are often higher at night necessitating greater visibility at a time when visibility is reduced. Finally, the incidence of impaired (alcohol or drugs), fatigued, or drowsy drivers might be higher at night.

05 Working at night also involves other factors, including construction productivity and quality, social impacts, economics, and environmental issues. A decision to perform construction or maintenance activities at night normally involves some consideration of the advantages to be gained compared to the safety and other issues that might be impacted.

Guidance:

06 Considering the safety issues inherent to night work, consideration should be given to enhancing traffic controls (see Section 6G.04) to provide added visibility and driver guidance, and increased protection for workers.


07 In addition to the enhancements listed in Section 6G.04, consideration should be given to providing additional lights and retroreflective markings to workers, work vehicles, and equipment.

Option:


08 Where reduced traffic volumes at night make it feasible, the entire roadway may be closed by detouring traffic to alternate facilities, thus removing the traffic risk from the activity area.

GUIDANCE


Because typical street and highway lighting is rarely adequate to provide sufficient levels of illumination for work tasks, temporary lighting should be provided where workers are active to supply sufficient illumination to reasonably safely perform the work tasks.

Temporary lighting for night work should be designed such that glare does not interfere with driver visibility, or create visibility problems for truck drivers, equipment operators, flaggers, or other workers.

09 Consideration should be given to stationing uniformed law enforcement officers and lighted patrol cars at night work locations where there is a concern that high speeds or impaired drivers might result in undue risks for workers or other drivers.



Standard:

10 Except in emergencies, temporary lighting shall be provided at all flagger stations.


Support:

11 Desired illumination levels vary depending upon the nature of the task involved. An average horizontal luminance of 5 foot candles can be adequate for general activities. An average horizontal luminance of 10 foot candles can be adequate for activities around equipment. Tasks requiring high levels of precision and extreme care can require an average horizontal luminance of 20 foot candles.



Section 6G.20 Installation, Maintenance and Inspection of TTC

GUIDANCE

Prior to installing any traffic control device, it should be inspected for condition, reflectorization and standard shape, size, color and message. If the device is not standard or in good condition, it should be replaced immediately. See Section 6K (the Field Manual) for Quality Standards.

Existing signs that do not apply or conflict with temporary traffic control should be removed or covered. If the sign is removed it should be carefully stored for re-installation when the temporary traffic control zone is removed.

SUPPORT

When covering a sign, care should be taken not to damage the sign face. When placing another hard material over the sign face, plastic spacers need to be inserted to avoid scratching the sign face. Translucent materials and materials that may become damaged by the weather are not acceptable coverings.

Temporary traffic control zone signs that are installed prior to the start of work also need to be covered, rotated or folded to avoid giving the driver an erroneous message.

STANDARD

When work is not in progress and the hazard no longer exists, devices shall be covered or removed.

Traffic control devices shall be installed in the order that drivers will see them, starting with the sign or device that is furthest from the work space.

OPTION

If traffic in both directions will be affected, such as work in the center lanes, the devices can be placed in both directions at the same time.

GUIDANCE

When one direction of traffic will be directed into the opposing lanes of traffic, all traffic controls for the opposing traffic should be installed first.

The devices should be removed as soon as the work is completed and they are no longer needed. Devices should be removed in the opposite order from which they were installed. Devices closest to the work space should be removed first.

SUPPORT

After the temporary traffic control zone is inplace, it is helpful to inspect the zone by driving through the zone. Driver's actions and reactions should be noted and if any problems are encountered, they should be quickly corrected.

GUIDANCE

Any major modifications to the Traffic Control Plan or standard layouts and the reasons for the modifications should be documented.

SUPPORT

During the life of a temporary traffic control zone, maintenance is needed. On short term operations, vehicles may knock over cones which then need to be placed upright. For intermediate term and long term operations, accidents, weather, dirt and vandalism may affect the traffic control devices.

GUIDANCE

A regular plan for inspection and maintenance should be implemented to ensure that all devices remain functional and in good repair throughout the life of the temporary traffic control zone. If problems are encountered, they should be corrected immediately and documented.

GUIDANCE

Any hazard (i.e. pothole, washout, damaged guardrail) should be repaired as soon as possible. However, when the hazard cannot be immediately repaired, or is not directly in the traveled way, it should be marked. Hazards should be marked with a reflectorized drum(s) or Type I or Type II barricade(s) with a Type A, low intensity flashing warning light attached.

SUPPORT

Other problems may be noted during routine inspections which may indicate a problem with the driver's perception of the zone. Skid marks, broken glass and devices continually knocked over may indicate a lack of advance warning or other problem with the temporary traffic control.

GUIDANCE

The zone should be reviewed during day and night to determine the problem and take appropriate corrective action.

SUPPORT

The frequency of inspection and maintenance will vary depending on the project size, duration, volume of traffic and complexity of the zone. Good communication and clear lines of responsibility will assist in resolving problems promptly.



MN LANGUAGE

MN LANGUAGE

MN LANGUAGE

MN LANGUAGE

MN LANGUAGE but COMPLAINT

MN LANGUAGE but COMPLAINT

MN LANGUAGE but COMPLAINT


MN LANGUAGE but COMPLAINT

Additional MN Guidance


MN Guidance
MN Guidance


MN Guidance


MN Standard

MN Standard

Refers to MN Drop off Guidance


MN Guidance

MN Guidance

THIS SECTION IN THE FED MUTCD DOES NOT
MAKE SENSE IN THIS LOCATION AND
ACTUALLY USES THE DESCRIPTION OF A DETOUR


THIS IS THE INFORMATION FROM MNMUTCD
REGARDING TLTW ROADWAYS


MN GUIDANCE

MN STANDARDs

MN GUIDANCE


MN GUIDANCE

MN GUIDANCE

MN SECTION ADDED