System testing checks the readiness and accuracy of the system to access, update and retrieve data from new files. Once
the programs become available, test data are read into the computer and processed against the files) provided for testing. If successful, the programs) is then run with “ live data. Otherwise, a diagnostic procedure is used to locate and correct errors in the program.
Inmost conversions, parallel run is conducted where the new system runs simultaneously with the old system. This method, though costly, provides added assurance against errors in the candidate system and also gives the user staff an opportunity to gain experience through operation.
In some cases, however, parallel processing in not practical. For example, it is not plausible to run parallel two online point-of-sale (POS) systems fora retail chain. In any case, after the
candidate system proves itself, the old system is phased out.