Portfolio Additional Estimates Statements 2016-17


Appendix G: Facilities and Infrastructure Program (formerly known as the Capital Facilities Program)



Download 1.39 Mb.
Page11/16
Date05.08.2017
Size1.39 Mb.
#26415
1   ...   8   9   10   11   12   13   14   15   16

Appendix G: Facilities and Infrastructure Program (formerly known as the Capital Facilities Program)


    Explanation of the Facilities and Infrastructure Program

Information is as reported in the 2016-17 Portfolio Budget Statements except for the following update:

  • As part of the Defence Integrated Investment Program, the Capital Facilities Program is now referred to as the Facilities and Infrastructure Program. This comprises of approved and yet to be approved major and medium projects.

  1. Approved Facilities and Infrastructure Projects by State and Federal Electorate

     

    State and
    Electorate


    Total
    Estimated
    Expenditure
    $m


    Cumulative
    Expenditure
    to 30 June 2016
    $m


    2016-17
    Budget
    Estimate
    $m


    2016-17
    Revised
    Estimate
    $m


    Variation
    $m


    Project Performance Update and Explanation of financial variation

    Facilities in support of the New Air Combat Capability (AIR 6000)[1]






















    RAAF Williamtown

    NSW - Newcastle

    -

    271.2

    161.3

    199.2

    37.8

    The financial variation is a result of the opportunity to deliver construction works earlier than planned.

    RAAF Tindal

    NT - Lingiari

    -

    14.8

    81.7

    100.8

    19.2

    The financial variation is a result of the opportunity to deliver construction works earlier than planned.

    Total

     

    1,477.0

    286.1

    243.0

    300.0

    57.0

     

    Table 71: Approved Facilities and Infrastructure Projects by State and Federal Electorate (Continued)

 

State and
Electorate


Total
Estimated
Expenditure
$m


Cumulative
Expenditure
to 30 June 2016
$m


2016-17
Budget
Estimate
$m


2016-17
Revised
Estimate
$m


Variation
$m


Project Performance Update and Explanation of financial variation

Enhanced Land Force Stage 2 Works[1]






















Lone Pine Barracks

NSW - Hunter

-

117.5

-

-

-




Puckapunyal Training Area

VIC - McEwan

-

1.3

7.1

6.1

-1.0

The financial variation is a result of change in delivery schedule.

Simpson Barracks, Watsonia

VIC - Jagajaga

-

20.2

-

-

-




RAAF Amberley

QLD - Blair

-

9.6

-

-

-




Lavarack Barracks, Townsville

QLD - Herbert

-

66.3

-

-

-




Townsville Training Area

QLD - Kennedy

-

3.9

-

-

-




Greenbank Training Area

QLD - Rankin

-

120.7

-

-

-




Gallipoli Barracks, Enoggera

QLD - Ryan

-

807.8

-

-

-




Wide Bay Training Area

QLD - Wide Bay

-

90.9

0.5

0.4

-0.1

The financial variation is a result of change in delivery schedule.

Kokoda Barracks, Canungra

QLD - Wright

-

72.1

-

-

-




Cultana Training Area

SA - Grey

-

3.0

14.2

12.1

-2.1

The financial variation is a result of change in delivery schedule.

RAAF Edinburgh

SA - Wakefield

-

34.5

-

-

-




Majura Field Training Area

ACT - Fraser

-

22.4

-

-

-




Total

 

1,457.8

1,370.1

21.8

18.6

-3.2

 

Table 71: Approved Facilities and Infrastructure Projects by State and Federal Electorate (Continued)

 

State and
Electorate


Total
Estimated
Expenditure
$m


Cumulative
Expenditure
to 30 June 2016
$m


2016-17
Budget
Estimate
$m


2016-17
Revised
Estimate
$m


Variation
$m


Project Performance Update and Explanation of financial variation

Defence Logistics Transformation Program[1]






















Defence National Storage & Distribution Centre, Moorebank

NSW - Hughes

-

205.7




1.7

1.7

The financial variation is a result of minor enhancement works to meet capability requirements.

Wadsworth Barracks, Bandiana

VIC - Indi

-

63.6







-




RAAF Amberley

QLD - Blair

-

145.0







-




Lavarack Barracks, Townsville

QLD - Herbert

-

131.7

5.0

-

-5.0

The financial variation is a result of additional works completed early at Lavarack Barracks, minor enhancement works at Moorebank and construction defect rectification works at Robertson Barracks.

RAAF Edinburgh

SA - Wakefield

-

21.9







-




HMAS Stirling, Rockingham

WA - Brand

-

1.3







-




Palmer Barracks

WA - Hasluck




8.5







-




Robertson Barracks

NT - Solomon

-

127.1




3.4

3.4

The financial variation is a result of rectification works required to meet capability requirements.

Total

 

732.6

704.8

5.0

5.1

0.1

 



    Table 71: Approved Facilities and Infrastructure Projects by State and Federal Electorate (Continued)

 

State and
Electorate


Total
Estimated
Expenditure
$m


Cumulative
Expenditure
to 30 June 2016
$m


2016-17
Budget
Estimate
$m


2016-17
Revised
Estimate
$m


Variation
$m


Project Performance Update and Explanation of financial variation

Maritime Patrol Aircraft Replacement (AIR 7000 Phase 2B)[1]






















RAAF Edinburgh

SA - Wakefield

-

23.9

168.1

100.3

-67.8

The financial variation is a result of delays due to wet weather.

RAAF Townsville

QLD - Herbert

-

-

-

-

-




RAAF Pearce

WA - Pearce

-

-

-

-

-




RAAF Darwin

NT - Solomon

-

-

-

-

-




Total

 

707.9

23.9

168.1

100.3

-67.8

 



    Table 71: Approved Facilities and Infrastructure Projects by State and Federal Electorate (Continued)

     

    State and
    Electorate


    Total
    Estimated
    Expenditure
    $m


    Cumulative
    Expenditure
    to 30 June 2016
    $m


    2016-17
    Budget
    Estimate
    $m


    2016-17
    Revised
    Estimate
    $m


    Variation
    $m


    Project Performance Update and Explanation of financial variation

    Air Traffic Control Complex Infrastructure Project, AIR 5431 Phases 2 and 3 and Fixed Base Defence Air Traffic Management and Control System[1]






















    RAAF Amberley

    QLD - Blair

    -

    -

    54.6

    32.7

    -

    The financial variation is a result of the delay in commencement of construction.

    Army Aviation Centre Oakey

    QLD - Groom

    -

    -

    -

    -

    -




    RAAF Townsville

    QLD - Herbert

    -

    -

    -

    -

    -




    RAAF Richmond

    NSW - Greenway

    -

    -

    -

    -

    -




    HMAS Albatross

    NSW - Gilmore

    -

    -

    -

    -

    -




    RAAF Williamtown

    NSW - Newcastle

    -

    -

    -

    -

    -




    RAAF East Sale

    VIC - Gippsland

    -

    -

    17.8

    10.7

    -

    The financial variation is a result of the delay in commencement of construction.

    RAAF Woomera

    SA - Grey

    -

    -

    -

    -

    -




    RAAF Edinburgh

    SA - Wakefield

    -

    -

    6.9

    4.1

    -

    The financial variation is a result of the delay in commencement of construction.

    RAAF Gingin

    WA - Pearce

    -

    -

    -

    -

    -




    RAAF Pearce

    WA - Pearce

    -

    -

    -

    -

    -




    RAAF Darwin

    NT - Solomon

    -

    -

    -

    -

    -




    RAAF Tindal

    NT - Lingiari

    -

    -

    15.8

    9.5

    -

    The financial variation is a result of the delay in commencement of construction.

    Total

     

    409.9

    -

    95.1

    57.0

    -38.1

     

    Table 71: Approved Facilities and Infrastructure Projects by State and Federal Electorate (Continued)

     

    State and
    Electorate


    Total
    Estimated
    Expenditure
    $m


    Cumulative
    Expenditure
    to 30 June 2016
    $m


    2016-17
    Budget
    Estimate
    $m


    2016-17
    Revised
    Estimate
    $m


    Variation
    $m


    Project Performance Update and Explanation of financial variation

    Battlefield Airlifter Facilities (AIR 8000 Phase 2)






















    RAAF Amberley

    QLD - Blair

    370.4

    6.3

    201.0

    61.5

    -139.5

    The financial variation is a result of change in delivery schedule and lower than anticipated subcontractor tender prices.

    HMAS Stirling Redevelopment Stage 3A






















    HMAS Stirling, Rockingham

    WA - Brand

    366.8

    3.7

    23.4

    12.0

    -11.4

    The financial variation is a result of delay relating to the design services contract.

    Growler Airborne Electronic Attack Capability Facilities (AIR 5349 Phase 3)






















    RAAF Amberley

    QLD - Blair

    348.6

    9.8

    136.5

    76.4

    -60.1

    The financial variation is a result of delays relating to industrial action impacting construction works.

    Pilot Training System Facilities Project (AIR 5428 Phase 1)[1]






















    RAAF East Sale

    VIC - Gippsland

    -

    -

    -

    90.6

    90.6

    Project has been approved since the 2016-17 Portfolio Budget Statements.

    RAAF Pearce

    WA - Pearce

    -

    -

    -

    35.6

    35.6

    Project has been approved since the 2016-17 Portfolio Budget Statements.

    RAAF Edinburgh

    SA - Wakefield

    -

    -

    -

    -

    -




    RAAF Williamtown

    NSW - Newcastle

    -

    -

    -

    -

    -




    Total

     

    329.8

    -

    -

    126.2

    126.2

     

    Table 71: Approved Facilities and Infrastructure Projects by State and Federal Electorate (Continued)

 

State and
Electorate


Total
Estimated
Expenditure
$m


Cumulative
Expenditure
to 30 June 2016
$m


2016-17
Budget
Estimate
$m


2016-17
Revised
Estimate
$m


Variation
$m


Project Performance Update and Explanation of financial variation

LAND 121 Phases 3 and 4 Overlander Facilities Stage 2[1]






















Lavarack Barracks, Townsville

QLD - Herbert

-

-

60.5

45.3

-15.2

The financial variation is a result of the delays due to contract negotiations.

Gallipoli Barracks, Enoggera

QLD - Ryan

-

-

42.1

31.5

-10.6

The financial variation is a result of the delays due to contract negotiations.

RAAF Williamtown

NSW - Newcastle

-

-

11.5

8.6

-2.9

The financial variation is a result of the delays due to contract negotiations.

Holsworthy Barracks, Holsworthy

NSW - Hughes

-

-

1.3

1.0

-0.3

The financial variation is a result of the delays due to contract negotiations.

Puckapunyal Training Area

VIC - McEwan

-

-

-

-

-




Campbell Barracks

WA - Curtin

-

-

-

-

-




RAAF Edinburgh

SA - Wakefield

-

-

-

-

-




Robertson Barracks

NT - Solomon

-

-

0.5

0.4

-0.1

The financial variation is a result of the delays due to contract negotiations.

Total

 

276.5

-

115.9

86.7

-29.2

 

RAAF Williamtown Redevelopment Stage 2






















RAAF Williamtown

NSW - Newcastle

274.0

14.1

102.8

57.4

-45.4

The financial variation is a result of change in delivery schedule.

Campbell Barracks Redevelopment






















Campbell Barracks

WA - Curtin

223.6

16.0

45.0

104.0

59.0

The financial variation is a result of the opportunity to deliver construction works earlier than planned.



    Table 71: Approved Facilities and Infrastructure Projects by State and Federal Electorate (Continued)

 

State and
Electorate


Total
Estimated
Expenditure
$m


Cumulative
Expenditure
to 30 June 2016
$m


2016-17
Budget
Estimate
$m


2016-17
Revised
Estimate
$m


Variation
$m


Project Performance Update and Explanation of financial variation

C-17 Maintenance Facility, Aircraft Apron and Associated Infrastructure






















RAAF Amberley

QLD - Blair

219.4

-

-

33.8

33.8

Project has been approved since the 2016-17 Portfolio Budget Statements.

HMAS Albatross Redevelopment Stage 3






















HMAS Albatross

NSW - Gilmore

194.2

143.1

39.2

45.6

6.5

The financial variation is a result of the opportunity to deliver construction works earlier than planned.

Facilities for MH-60R Seahawk Maritime Combat Helicopters (AIR 9000 Phase 8)[1]






















HMAS Albatross, Nowra

NSW - Gilmore

-

162.9

-

-

-




HMAS Stirling, Rockingham

WA - Brand

-

6.6

1.6

13.2

11.6

The financial variation is a result of additional work required to meet capability requirements.

Twofold Bay, Eden

NSW - Eden-Monaro

-

0.3

0.5

4.1

3.6

The financial variation is a result of additional work required to meet capability requirements.

Total

 

189.0

169.7

2.1

17.3

15.2

 

East Sale Redevelopment






















RAAF East Sale

VIC - Gippsland

185.6

169.6

-

13.1

13.1

The financial variation is a result of delay in the Fuel Farm construction.

Helicopter Aircrew Training System (AIR 9000 Phase 7)[1]






















HMAS Albatross, Nowra

NSW - Gilmore

157.1

72.1

60.2

64.7

4.5

The financial variation is a result of the opportunity to deliver construction works earlier than planned.

Defence Terrestrial Communications Network Facilities Upgrade (JP2047)[2]






















National

 

130.8

55.5

40.7

39.1

-1.5

The financial variation is a result of change in delivery schedule.

Table 71: Approved Facilities and Infrastructure Projects by State and Federal Electorate (Continued)

 

State and
Electorate


Total
Estimated
Expenditure
$m


Cumulative
Expenditure
to 30 June 2016
$m


2016-17
Budget
Estimate
$m


2016-17
Revised
Estimate
$m


Variation
$m


Project Performance Update and Explanation of financial variation

Airfield Capital Works[1]






















RAAF Townsville

QLD - Herbert

-

-

-

-

-




RAAF Curtin

WA - Durack

-

7.7

2.3

2.5

0.3

The financial variation is a result of change in delivery schedule.

RAAF Tindal

NT - Lingiari

-

8.1

31.7

35.7

3.9

The financial variation is a result of change in delivery schedule.

Total

 

95.3

15.8

34.0

38.2

4.2

 

Delamere Range Facilities Redevelopment






















Delamere Air Weapons Range

NT - Lingiari

74.4

2.0

49.8

31.5

-18.4

The financial variation is a result of the delays due to contract negotiations.

17th Construction Squadron Relocation






















RAAF Amberley

QLD - Blair

71.8

31.7

40.0

36.7

-3.3

The financial variation is a result of the delays relating to contamination issues.

Space Telescope (Joint Project (JP) 3029)






















Harold E Holt, Exmouth

WA - Durack

63.0

6.0

48.0

16.8

-31.2

The financial variation is to ensure the updated user design requirements are met.

REDFIN Infrastructure (JP 2097 Phase 1B)[1]






















Holsworthy Barracks

NSW - Hughes

-

7.1

-

-

-




Campbell Barracks

WA - Curtin

-

0.4

-

-

-




Defence Establishment Howard Springs

NT - Solomon

-

3.5

-

-

-




Lavarack Barracks

QLD - Herbert

-

0.1

-

-

-




Total

 

50.5

11.1

17.1

25.9

8.8

The financial variation is the result of enhancements to project scope.

Table 71: Approved Facilities and Infrastructure Projects by State and Federal Electorate (Continued)

 

State and
Electorate


Total
Estimated
Expenditure
$m


Cumulative
Expenditure
to 30 June 2016
$m


2016-17
Budget
Estimate
$m


2016-17
Revised
Estimate
$m


Variation
$m


Project Performance Update and Explanation of financial variation

Puckapunyal Military Area High Voltage Upgrade






















Puckapunyal Training Area

VIC - McEwan

32.7

-

-

19.9

19.9

Project has been approved since the 2016-17 Portfolio Budget Statements.

Facilities for Chinook Helicopter (AIR 9000 Phases 5B and 5C)






















RAAF Townsville

QLD - Herbert

49.8

26.7

11.5

21.0

9.5

The financial variation is a result of the opportunity to deliver construction works earlier than planned.

RAAF Base Amberley Sewerage Treatment Plant[4]

 

 

 

 

 

 

 

RAAF Amberley

QLD - Blair

13.0

-

13.0

3.1

-9.9

The financial variation is a result of the delay in commencement of construction.

Low Level Bridge Repair[4]

 

 

 

 

 

 

 

Fleet Base West, Stirling

WA - Brand

12.8

7.0

6.4

5.4

-1.0

The financial variation is a result of change in delivery schedule.

Facilities for Lead in Fighter Capability Assurance Program (AIR 5438 Phase 1)[1][4]

 

 

 

 

 

 

 

RAAF Williamtown

NSW - Newcastle

-

8.4

-

-

-




RAAF Pearce

WA - Pearce

-

1.3

3.8

0.8

-3.0

The financial variation is a result of change in delivery schedule.

Total

 

12.7

9.7

3.8

0.8

-3.0

 

Table 71: Approved Facilities and Infrastructure Projects by State and Federal Electorate (Continued)

 

State and
Electorate


Total
Estimated
Expenditure
$m


Cumulative
Expenditure
to 30 June 2016
$m


2016-17
Budget
Estimate
$m


2016-17
Revised
Estimate
$m


Variation
$m


Project Performance Update and Explanation of financial variation

JHC Facilities Upgrades - Interim Works[1][4]




 

 

 

 

 

 

Larrakeyah / Coonawarra

NT - Solomon

-

4.6

2.7

-

-1.4

The financial variation is a result of the works at Larrakeyah/Coonawarra being complete.

RAAF Pearce

WA - Pearce

-




2.3

2.5

-1.2

The financial variation is a result of a delay to the delivery schedule.

RAAF Townsville

QLD - Herbert

-




1.9

-

-1.0

The financial variation is a result of changes to project scope.

Total

 

9.8

4.6

6.8

3.2

-3.7

 

Shoal Bay Receiving Station Facilities Upgrade[4]






















Shoal Bay Receiving Station Facilities

NT - Solomon

8.0

0.3

-

7.1




Project has been approved since the 2016-17 Portfolio Budget Statements.

Projects in or about to enter Defects Liability Period[3]

 

 

 

21.3

14.2

-7.1

 

Total

 

8,533.2

3,043.5

1,551.5

1,442.7

-115.9

 

Notes

  1. These projects cross state and electoral boundaries. Estimated cumulative expenditure to 30 June 2016 and expenditure estimates for 2016-17 are provided in the table per location.

  2. This project is delivering facilities at over 200 locations that cross state and electoral boundaries.

  3. This amount represents the expenditure estimates for contract administration of 22 completed projects during their first year in-use and construction completion of five medium works projects that are under the $2m reporting threshold to the Public Work.

  4. Indicates the medium works projects, as per Note 3.

    Explanation of Projects

Information is as reported in the 2016-17 Portfolio Budget Statements except for the following updates:
Queensland
17th Construction Squadron Relocation

This project will provide facilities to collocate 17th Construction Squadron with 6th Engineer Support Regiment and 21st Construction Squadron at RAAF Base Amberley, Qld. The project is scheduled to be completed by early 2017.
Facilities for Chinook Helicopter (AIR 9000 Phases 5B and 5C)

The project is scheduled for completion by late 2017.
C-17 Maintenance Facility, Aircraft Apron and Associated Infrastructure

This project will provide C-17 aircraft maintenance facilities at RAAF Base Amberley. Works include a hanger, workshops, apron to accommodate eight C-17 aircraft, explosive ordnance facilities and associated infrastructure. The project is scheduled for completion in late 2019.
Victoria
Puckapunyal High Voltage Project

The project will provide an essential upgrade to the High Voltage power supply and reticulation network at the Puckapunyal Military Area, Victoria. The Project is scheduled for completion in late 2017.
Western Australia
HMAS Stirling Redevelopment Stage 3A

This project will provide upgrades and refurbishment of existing critical shortfalls to infrastructure and facilities. The project is scheduled for completion by early 2020.
Various Locations
New Air Combat Capability (AIR 6000 NACC)

This project will provide new and upgraded facilities and infrastructure to support the introduction of the Joint Strike Fighter at RAAF Base Williamtown, Newcastle, NSW, and RAAF Base Tindal, Katherine, NT with support facilities and infrastructure provided at Defence Establishment Myambat, NSW and several Forward Operating Bases. The project is scheduled for completion by late 2022.
Defence Logistics Transformation Program (DLTP)

The facilities component of the program will provide enhanced logistics facilities at Moorebank, NSW, Bandiana, VIC, Amberley and Townsville, QLD, Palmerston, NT, Edinburgh, SA and Guilford and Garden Island, WA. Additional enhancement works are being undertaken at Moorebank and Robertson Barracks. These final works are scheduled for completion by early 2017.




Defence Terrestrial Communications Network Facilities Upgrade

This project will provide infrastructure and supporting facilities at multiple Defence owned and leased sites across Australia. The project will support the introduction into service of the Defence Terrestrial Communications Network. Construction activities will be complete by October 2018.
AIR 5428 Phase 1 - Pilot Training System Facilities Project

The project will provide fit-for-purpose facilities to support the modern joint training system being delivered by the AIR5428-1 Capability Project, with the facilities planned to be delivered at RAAF Base East Sale (Victoria), RAAF Base Pearce and Gingin (Western Australia), RAAF Base Williamtown (New South Wales) and RAAF Base Edinburgh (South Australia). The project is scheduled for completion in late 2019.