8-1.03 PRECONSTRUCTION CONFERENCE


Attend a preconstruction conference with key personnel, including your assigned representative, at a time and location determined by the Engineer. Submit documents as required before the preconstruction conference. You may start work before the preconstruction conference.

Be prepared to discuss the topics and documents shown in the following table:



Topic

Document

Potential claim and dispute resolution

Potential claim forms

Contractor's representation

Assignment of Contractor's representative

DBE and DVBE

Final utilization reports

Equipment

Equipment list

Labor compliance and equal employment opportunity

Job site posters and benefit and payroll reports

Material inspection

Notice of Materials to be Used form

Materials on hand

Request for Payment for Materials on Hand form

Measurements

--

Partnering

--

Quality control

QC plans

Safety

Injury and Illness Prevention Program and job site posters

Schedule

Baseline schedule and Weekly Statement of Working Days form

Subcontracting

Subcontracting Request form

Surveying

Survey Request form

Traffic control

Traffic contingency plan and traffic control plans

Utility work

--

Weight limitations

--

Water pollution control

SWPPP or WPCP

Work restrictions

PLACs

Action submittals

--


8-1.04 START OF JOB SITE ACTIVITIES

8-1.04A General


Reserved

8-1.04B Standard Start


For a project that does not require a SWPPP, start job site activities within 15 days after receiving notice that the Contract has been approved by the Attorney General or the attorney appointed and authorized to represent the Department.

For a project that requires a SWPPP, start job site activities within 55 days after receiving notice that the Contract has been approved by the Attorney General or the attorney appointed and authorized to represent the Department.

Submit a notice 72 hours before starting job site activities. If the project has more than 1 work location, submit a separate notice for each location.

You may start job site activities before receiving notice of Contract approval if you:

1. Deliver the signed Contract, bonds, and evidence of insurance to the Department

2. Submit a 72-hour notice

3. Obtain an encroachment permit from the Department

4. Receive the Department's authorization to start

5. Perform work at your own risk

6. Perform work under the Contract


If the Contract is approved, work already performed that complies with the Contract is authorized.

If the Contract is not approved, leave the job site in a neat condition. If a facility has been changed, restore it to its former condition or an equivalent condition. The Department does not pay for the restoration.

The Department does not adjust time for work performed before Contract approval.

8-1.04C Delayed Start


Reserved

8-1.04D Early Return-Early Start


Reserved

8-1.04E Next-Day Start


Reserved

8-1.04F Flexible Start


Reserved

8-1.04G Potential Budget Impasse Start


Reserved

8-1.04H–8-1.04J Reserved

8-1.05 TIME


The contract time starts on the earlier of the following:

1. Day you start job site activities after Contract approval

2. Last day specified to start job site activities in section 8-1.04
Complete the work within the Contract time.

Meet each specified interim work-completion date.

The Engineer issues a Weekly Statement of Working Days form by the end of the following week.

The Weekly Statement of Working Days form shows:

1. Working days and non–working days during the reporting week

2. Time adjustments

3. Calculations of work completion dates, including working days remaining

4. Controlling activities



8-1.06 SUSPENSIONS


The Engineer may suspend work wholly or in part due to conditions unsuitable for work progress. Provide for public safety and a smooth and unobstructed passageway through the work zone during the suspension as specified in sections 7-1.03 and 7-1.04. Providing the passageway is force account work. The Department makes a time adjustment for the suspension due to a critical delay.

The Engineer may suspend work wholly or in part due to your failure to (1) fulfill the Engineer's orders, (2) fulfill a Contract part, or (3) perform weather-dependent work when conditions are favorable so that weather-related unsuitable conditions are avoided or do not occur. The Department may provide for a smooth and unobstructed passageway through the work during the suspension and deduct the cost from payments. The Department does not make a time adjustment for the suspension.

Upon the Engineer's order of suspension, suspend work immediately. Resume work when ordered.