24 | Page last year’s AWP in an effort to improve monitoring of the project’s results. While last year’s plan included 10 quantitative indicators, this year’s plan includes 13. Detailed discussions were also undertaken in Q with the stakeholders to access the results of the project for the annual report for 2014. The report was submitted to the JHRA donors in a timely manner prior to the first PSC. In order to facilitate communication between
JHRA and the country office, more frequent meetings have been held bringing JHRA management, UNDP senior management and the Rule of Law Unit together. On the recommendation
of the midterm review, meetings between JHRA’s regional coordinators and component leaders have been instituted in order to tighten coordination on activities in the provinces. On the recommendation of the midterm review, a monthly newsletter is now being produced to keep donors updated about activities and successes on a more regular basis.