|
BMOBILE VODAFONE LIMITED
|
Document No.
|
PMO_RFP_G2
|
Effective Date
|
22/12/2014
|
RFP – PO2A SUPPLY OF HYBRID POWER SYSTEMS FOR TELECOMMUNICATION SITES
|
Revision No.
|
Final V1
|
Revision Date
|
22/12/2014
|
Request for Proposal
Supply of Hybrid Power Systems
For Wireless Telecommunication Infrastructure Sites
For Bmobile Vodafone Limited
Papua New Guinea
Solomon Islands
Phase PO2A
December , 2014
Phase PO2A – SUPPLY GENERATOR SETS FOR BMOBILE VODAFONE NETWORK DEPLOYMENT
OVERVIEW
As part of the Bmobile Vodafone Network Expansion program, throughout PNG and Solomon Islands, Bmobile hereby is calling for proposal from reputable selected Generators and Power Solution suppliers to provide Hybrid Power units to power its Mobile Telecommunication sites.
Bmobile is looking to install new and upgrade existing sites by May 1st 2015, when sites will be ready as part of Project PO2A rollout in PNG. The hybrid power units selected will also be used at Bmobile Vodafone sites in the Solomon Islands later in the year.
As a design baseline, Bmobile is looking for hybrid power solutions with;
Design shall have a design life of 10 years or over
Refuelling every 30 days
Low Capex cost
Low Opex cost
Efficient and dependable
Ability to interface with the Huawei BTS 3900 is desirable
Diesel generators to have the Deep Sea controller 7420.
DESIGN OVERVIEW
The Hybrid solution should be:
based an efficient diesel generator with an adequate battery bank to support the load.
The battery type should be sealed and maintenance free.
Output is to be – 48V DC.
Other inputs such as solar, wind and grid power should be available to the system as a plug and play modules.
The generator must not run continuously.
Normal DOD of 30-35%, this allows the site to continue if the generator doesn’t start and extends the number of cycles for the batteries.
DC distribution panel with 2 x LVD for Priority and Non-Priority load control
Maximum LVD of 50%
The hybrid power system sought is designed for Off Grid operations with a view to reduce OPEX with comparison to conventional power solutions running 24/7 generators. The site equipment will be Huawei cabinet with a -48 VDC input.
Category
|
Information Item
|
Requirements
|
Basic information
|
Country
|
PNG & Solomon Islands
|
Application scenario
|
Off-Grid and On grid sites
|
Grid condition (mean outage time)
|
On-Grid Site
|
4 hours/day with 184 Ah batteries as backup
|
Off-Grid Site
|
24 hours/day (24x7)
|
Scenario
|
Indoor/Outdoor
|
Outdoor
|
New Site/Rebuild Site
|
New Site and some replacement
|
Power Consumption
|
ON-Grid Site
|
1800-2000 W
|
OFF Grid Site
|
1800-2000 W
|
|
|
Table 1.
In principal, the expected operation of the generator (genset) is as below.
Typically the generator will run for about 30% of the time or less. For the rest of the time, the battery is discharging. A full cycle should take around one day hence the characteristics of battery, generator and load, and optimisation of the solution should support this.
The charged battery bank will dissipates to preset voltage level (DOD 30-35%), At DOD level the start signal is sent to the genset and ATS, which takes over site load and recharges the discharged batteries.
When batteries fully charged, genset stops and cycle repeats.
Solar, wind or grid input into the system to minimise generator use. This should be available as a modular option where by it can be a plug and play solution
For sites that have grid power the grid should charge the battery . If grid power is lost the batteries will discharge to DOD level. Once DOD has been reached the genset will start and take the site load and recharge the batteries until grid power returns.
SCOPE OF SUPPLY
The scope of work will include designing, supply and commissioning of complete Hybrid power solution. The installation can be done by a local contractor upon supervision from the selected supplier. The scopes are as follows:
____kw load design. Use from table 1 above.
Deep cycle Batteries @ 30-35% of normal DOD and 50% for LVD.
Off grid hybrid design shall be based on Generator-Battery scenario. Battery for 18 hours and Generator for 6 hours.
Grid design shall be based on 4 hours battery backup @ 30-35% DOD. Note: For On Grid sites we will only require the generators of a suitable capacity as deemed by the vendor.
Selection of appropriate size generator (KVA), Battery bank (Ah) and Fuel tank capacity (Lts).
Design shall include
battery boxes (with cooling facility),
equipment cabinet,
Appropriate rating rectifiers system,
DC distribution panel with 2 x LVD for Priority and Non-Priority load control
Control system to operate system according to selected scenario. The system controller must accurately manage charge and discharge cycles, including charge voltage, charge duration, charge rate and depth of discharge. There should be an option to limit the charging current of the batteries by the user.
Full NMS monitoring integration using remote management and SNMP output to Solarwinds
The network operator or service organization can prove the hybrid cost savings
Ensure operation remains optimal
Manage the response to faults
Support battery warranty of 3 years,
Lightning protection, cabling, and auxiliaries, earthing and manuals.
Equipment configuration shall be for outdoor installation.
All cabinets and battery boxes shall be waterproof, windproof and anti-corrosion and have the capability to withstand the weather and remote locations of PNG, All cabinets, tanks, and gensets must be provided with anti-theft locking systems.
2(a) GENERATOR SPECIFICATION AND REQUIREMENTS
All generators based on its ratings will be supplied with all basic features as per Table 2 – Basic Generator Specification below.
Generator
|
-Diesel
-Integrated tank minimum 250 litre for ON Grid sites and 1000 Litre base tank for OFF Grid sites , with anti theft mechanism for the tank and generator.
-Min service interval 1000 hours with Extended Service with secondary oil filtration system installed.
-Outdoor silenced min 85 dba @1 meter
|
Monitoring and control
|
Full monitoring and remote control for start and stop of generator.
Web based
Ability to host IP camera
Generator to be equipped with Deep Sea Controller model -7420.
|
Storage type
Batteries
|
Sealed maintenance free
Sufficient capacity
Readily available to PNG market
|
Equipment average load
|
1.8 – 2 Kw
|
Protection
|
Environmental protection for outdoor use and anti theft for both fuel tank and generator.
Lightening protection
Over-voltage protection
|
Table 2 – Basic Generator specification
Other required information to be included in your proposal but not limited to;
Pre sale support
|
Ordering, design requirement, connectivity with on site power equipment, site layout confirmation (tower base mount etc) and successful bidder may be invited to setup model site/demonstration of solution.
|
Post sales support
|
Spare part and maintenance kits supply. Frame supply contract 6 years and over. One contact for PNG and SI. Warranty for Maintenance including repair and return of parts.
|
Training
|
On site customer training, for staff and nominated contractors. Objective; over time to handle all maintenance and trouble shoot skills in-house. Basic, Advance and Specialised (such as Controller programming etc). Training and resource plan. Training sites consider PNG and SI.
|
Delivery
|
Lead time to deliver from PO, CIF POM, LAE (PNG) and Honiara (SI), Port of origin, route to PNG and SI, number of units fitting in one container
|
Factory
|
Location, capacity to manufacture, closing periods
|
Phase PO2A - ORDER LIST and SUMMARY TEMPLATE
Lae: 45 sets are to be delivered to Lae, PNG, of these 26 will be used as off grid systems with full hybrid solution and 19 will be utilised as On Grid for which only generators will be needed.
Honiara SI: 3 sets of Off Grid full hybrid units are to be delivered to Honiara Solomon islands.
REFERENCE DOCUMENT BE INCLUDED IN YOUR RESPONSE
Detail specifications of solution supplied are to:
Include technical, data sheets and physical specifications, for generators and all associated equipment proposed.
Include Full battery specification sheets, including technical, physical and DOD curves.
Include detail and clear schematics of overall connectivity of proposed solution, including, earthing, protection, performance monitoring and control.
Include Controller wiring diagrams
Above includes any 3rd parties systems in the proposals.
Information on the network control system.
RFP TIMELINE
Issue of RFP: Monday 22 December , 2014
Closing date: Wednesday 14 January , 2015, 17:00 hrs.
Successful bidder notified: Wednesday 19 January, 2015.
Bmobile Vodafone at its discretion may change Closing date and time. Any such changes shall apply to all bidders.
EVALUATION
Evaluation will be on the basis of technical and commercial proposal
Please note:
The commercial proposal will be required to be submitted after being qualified for the technical solution.
Proven quality of solution, meeting requirement and ability to demonstrate the use by other customers.
The ability of the system to improve OPEX,
Pricing,
Presales and post sales support
Capability to deliver and support.
The attached evaluation template should be filled by all vendors.
PRICING VALIDITY AND TERMS
Quotations are to be valid for 60 days, from date of submission to Bmobile.
All prices are to be in US$
Preferred prices are to be FOB and quote for shipping to PNG, Lae and SI, Honiara separately. If unable to do so, clearly specify trading term.
REQUEST FOR FURTHER INFORMATION
Send by email to rfp@bmobile.com.pg
Share with your friends: |