icaew diploma in ifrss assignment 1 paper 17 oct 2011
2 of 13




BLANK PAGE


ICAEW\DIPLOMA IN IFRSs Page
3 of 13
1(a)
The following costs were incurred in 2010 in the design and construction of anew office building over a nine-month period during 2010:
$'000
Feasibility study
8 Architects' fees
100 Site clearance (by external demolition professionals)
80 Construction materials
600 Cost of own inventories used in the construction (net realisable value if sold outside the company $24,000)
30 Internal construction staff salaries during period of construction
360 External contractor costs
2,400 Income from renting out part of site as storage depot during early phase of construction
(12)
3,566