Study Request: Opportunity/Variable Cost Dispatch for Solar, Wind, Geothermal and Nuclear
Requestor: SDG&E
Requested Study Year? 2026
What is the key question you would like the study to answer?
If commercial arrangements governing the dispatch of solar, wind, geothermal and nuclear resources were (i) changed for existing resources to recognize both the opportunity costs and variable costs of operating these resources, and (ii) implemented for future resources to recognize both the opportunity costs and variable costs of operating these resources, what would Locational Marginal Prices (LMPs) be and how would WECC production costs change assuming variable O&M costs (on a $/MWh basis) would by higher as a result of increased cycling?
Summary of the study’s key load, resource, transmission, and/or policy assumptions. Note: If the 10-year study request links to the 20 year, please identify basis for the linkage between the expected 10 year study results and inputs into the 20 year study case.
2026 Common Case:
Report the following outputs for this case (the “reference case”) on a WECC-wide basis:
Average on-peak and off-peak LMPs within each of the WECC Balancing Authorities, on a monthly basis
Annual production costs (exclude opportunity costs)
Annual tons of CO2 produced
Theoretical renewable resource production that had to be curtailed to obtain model solution, by technology and location
Create an “opportunity/variable cost dispatch case” by modifying the reference case:
Remove the must-run flag for geothermal units.
Double the variable O&M cost for geothermal units.
Change the minimum output level for nuclear plants to 50% of the maximum output level.
Reduce the MW/minute ramp rates for nuclear by 50%.1
Double the variable O&M cost for nuclear plants.
Change the “hourly” modeling for all wind resources to allow the wind resources to be dispatchable:
Set the maximum capacity in each hour of the year equal to the hourly profile quantity for each corresponding hour.
Input a variable O&M cost equal to the sum of (i) variable O&M ($8.94/MWh, 2015$) and (ii) an opportunity cost based on lost Production Tax Credit (-$23/MWh 2015$ in year 2026).
Input a fuel cost of $0/MWh.
Change the “hourly” modeling for all solar resources to allow the solar resources to be dispatchable:
Set the maximum capacity in each hour of the year equal to the hourly profile quantity for each corresponding hour.
Input a variable O&M cost of $0.00/MWh.
Input a fuel cost of $0/MWh.
Report the following outputs for the “opportunity/variable cost dispatch case” on a WECC-wide basis:
Average on-peak and off-peak LMPs within each of the WECC Balancing Authorities, on a monthly basis
Annual production costs (exclude opportunity costs)
Annual tons of CO2 produced
Theoretical renewable resource production that had to be curtailed to obtain model solution, by technology and location
How will this study provide information of broad value to stakeholders in the Western Interconnection, e.g. customers, regulators, Transmission Providers?
With large increases in the amount of intermittent generation, it is likely that LMPs will be negative in some hours of the years. To date, TEPPC’s GridView analysis has not attempted to estimate the degree to which LMPs will become negative in hours when renewable resources must be curtailed in order to achieve a market solution. TEPPC’s analysis has, so far, not used opportunity costs for solar and wind resources when determining the expected output of these resources; variable costs are assumed to be $0/MWh. It would be useful to get a sense of how negative LMPs may be in various hours of the year—this information could be important in assessing the value of potential demand response programs and storage additions in grid planning. Additionally, this information will provide insights into the incentives that consumers will have to change their current consumption practices.
The differences between the “reference case” and the “variable cost case” will provide a very rough indication of the magnitude of economic savings that could be obtained by reforming existing contracts, and implementing provisions in future contracts, such that the dispatch of solar, wind, geothermal and nuclear resources recognizes the opportunity costs and variable costs associated with operating these facilities. As well, this study will provide some indication as to how higher variable O&M costs associated with increased ramping will affect grid operations.
The differences will also provide an indication of how opportunity/variable cost dispatch would change the output of renewable resources whose theoretical renewable resource production has to be curtailed to obtain a model solution.
Can you offer expertise or information to WECC to assist in the development of this study case? Describe the information or support you will be able to provide, if any.
Yes. SDG&E has experience in economic grid simulation modeling using GridView.
Do you know of other stakeholders interested in the issues on which this request is based? If so, please provide their contact information.
SDG&E believes stakeholders focused on minimizing consumer costs, and stakeholders concerned with over-generation and the possibility that renewable resources will be curtailed, will be interested in the study results.
Is the requested study necessary to meet a member Transmission Provider's compliance with its Open Access Transmission Tariff (OATT), Attachment K?
No.
Study Request # 2
Study Request: Adding Wind in New Mexico and Wyoming without New Transmission
Requestor: SDG&E
Requested Study Year? 2026
What is the key question you would like the study to answer?
From the standpoint of physical capability, how much additional wind generating capacity located in high quality wind regimes can the existing transmission system accommodate? Stated differently, at what level of additional wind generating capacity does it make sense to consider the addition of new inter-regional transmission?
Summary of the study’s key load, resource, transmission, and/or policy assumptions. Note: If the 10-year study request links to the 20 year, please identify basis for the linkage between the expected 10 year study results and inputs into the 20 year study case.
2026 Common Case with following adjustments:
Diablo Canyon nuclear plant not operating.
The following planned transmission additions not in service:
Energy Gateway Project segments:
500 kV Walla Walla-McNary
500 kV Boardman-Hemingway
500 kV Windstar-Populus
500 kV Populus–Hemingway
500 kV Aeolus-Mona
New Mexico wind scenario
Step 1:
Add 333 MW of installed wind capacity at 345 kV Guadalupe substation (bus #10116) using the E_WT_NM_EA hourly wind profile.
Add 167 MW of installed wind capacity at 345 kV Amrad substation (bus #11010) using E_WT_NM_SO hourly wind profile
Step 2:
Add 667 MW of installed wind capacity at 345 kV Guadalupe substation (bus #10116) using the E_WT_NM_EA hourly wind profile.
Add 333 MW of installed wind capacity at 345 kV Amrad substation (bus #11010) using the E_WT_NM_SO hourly wind profile.
Step 3:
Add 1000 MW of installed wind capacity at 345 kV Guadalupe substation (bus #10116) using the E_WT_NM_EA hourly wind profile. Add 500 MW of installed wind capacity at 345 kV Amrad substation (bus #11010 ) using the E_WT_NM_SO hourly wind profile.
Add 250 MW of installed wind capacity at230 kV Latham substation (bus #67499) using the E_WT_WY_CE hourly wind profile. Add 250 MW of installed wind capacity at 345 kV Laramie River Station substation (bus #73108) using the E_WT_WY_CE hourly wind profile.
Step 2:
Add 500 MW of installed wind capacity at 230 kV Latham substation (bus #67499) using the E_WT_WY_CE hourly wind profile. Add 500 MW of installed wind capacity at 345 kV Laramie River Station substation (bus #73108) using the E_WT_WY_CE hourly wind profile.
Step 3:
Add 750 MW of installed wind capacity at 230 kV Latham substation (bus #67499) using the E_WT_WY_CE hourly wind profile.
Add 750 MW of installed wind capacity at 345 kV Laramie River Station substation (bus #73108) using the E_WT_WY_CE hourly wind profile.
Monitor the following transmission facilities and paths for hourly loading and report U75, U90 and U99 metrics:
From Bus #
|
Bus Name
|
|
To Bus #
|
Bus Name
|
Transformer #
|
10025
|
B-A 345
|
|
10116
|
Guadalupe 345
|
|
10390
|
Rio Puerco 345
|
|
10025
|
B-A 345
|
|
10390
|
Rio Puerco 345
|
|
10369
|
West Mesa 345
|
|
10369
|
West Mesa 345
|
|
10370
|
West Mesa 115
|
1
|
10369
|
West Mesa 345
|
|
10371
|
West Mesa 115
|
2
|
67499
|
Latham 230
|
|
66240
|
Platte 230
|
|
10292
|
San Juan 345
|
|
10390
|
Rio Puerco 345
|
|
10248
|
Pilar 230
|
|
14211
|
Four Corners 230
|
|
10368
|
West Mesa 230
|
|
10011
|
Ambrosia 230
|
|
11111
|
Newman 345
|
|
11217
|
Afton 345
|
|
73107
|
Laramie River Station 230
|
|
65420
|
Dave Johnston 230
|
|
67499
|
Latham 230
|
|
67530
|
Echo Springs 230
|
|
67530
|
Echo Springs 230
|
|
65105
|
Bar X 230
|
|
Path #
|
Path Name
|
Location
|
8
|
Montana to North West
|
Lines between western Montana and the Pacific Northwest
|
15
|
Midway – Los Banos
|
Lines connecting central California to Midway substation at the south end of the Central Valley..
|
16
|
Idaho – Sierra
|
Border between southern Idaho and northern Nevada, connecting Midpoint to Humboldt
|
17
|
Borah west
|
Southeast Idaho, connecting Midpoint to Borah
|
19
|
Bridger West
|
Border between Southeast Idaho and Southwest Wyoming connecting Jim Bridger to Borah
|
26
|
Northern – southern California
|
Lines connecting Midway substation to Vincent substation north of Los Angeles
|
27
|
Intermountain Power Project (IPP)
|
DC line connecting Intermountain substation in central Utah with Adelanto substation in southern California
|
31
|
TOT2A
|
Extreme Southwest Colorado, lines connecting Four Corners to southern Colorado
|
36
|
TOT3
|
Lines connecting Northeast Colorado (north of Denver) and Southeast Wyoming
|
37
|
TOT3A
|
Southwest Wyoming, lines connecting Atlantic City and Mustang to Riverton and Spence
|
38
|
TOT4B
|
Northwest Wyoming, lines connecting Riverton , Spence and Casper to Midwest and Thermopolis
|
39
|
TOT 5
|
West-Central Colorado, lines connecting Blue Mesa, Basalt to Salida and Malta
|
46
|
West of Colorado River (WOR)
|
Lines between southern Nevada and southern California plus lines crossing the Colorado River at the border of Arizona and California.
|
47
|
NM1
|
Southern New Mexico, connecting Luna and Socorro to Greenlee and Springerville
|
48
|
NM2
|
Northern New Mexico, connecting Amrad and Socorro to West Mesa
|
49
|
East of Colorado River (EOR)
|
Lines connecting Phoenix area to North Gila, Colorado River substation and to southern Nevada.
|
65
|
PDCI
|
DC Line connecting Cielo station (Big Eddy area) in northern Oregon with Sylmar station in Southern California
|
66
|
COI
|
AC lines between Oregon and northern California
|
Report annual WECC-wide:
Production costs
Tons of CO2 produced
Theoretical renewable resource production that had to be curtailed to obtain model solution, by location
How will this study provide information of broad value to stakeholders in the Western Interconnection, e.g. customers, regulators, Transmission Providers?
The study results will provide foundational information that can be used to identify (i) the amount of potential “low hanging wind fruit” that can be harvested without major transmission expansion, and (ii) the specific areas of the WECC grid where an expansion of transfer capability should be considered.
Note that wind development in New Mexico and Wyoming was chosen given the high quality of the wind regimes in these locations, the comparatively low capital cost for wind relative to solar and geothermal resources, and wind’s comparative lack of coincidence with the timing of output from the fleet of renewable resources expected to exist in year 2026 (which is dominated by solar).
Can you offer expertise or information to WECC to assist in the development of this study case? Describe the information or support you will be able to provide, if any.
Yes. SDG&E has experience in studying the economics of wind resource additions, with economic grid simulation modeling using GridView, and with AC power flow analysis using PSLF.
Do you know of other stakeholders interested in the issues on which this request is based? If so, please provide their contact information.
SDG&E believes nearly all stakeholders will be interested in study results which provide an analytic basis for identifying (i) the amount of wind resource additions in high-quality wind regimes that can be pursued without the need for major new transmission, (ii) regions of the grid where expansion of the CAISO Balancing Authority would allow new wind resources to avoid contract-path based wheeling charges without risk of significant congestion-related costs, and (iii) grid locations at which new transmission may make sense to pursue.
Is the requested study necessary to meet a member Transmission Provider's compliance with its Open Access Transmission Tariff (OATT), Attachment K?
No.
Share with your friends: |