Appendix a defence Cooperation Program


Appendix G: Capital Facilities Program



Download 0.54 Mb.
Page6/7
Date20.10.2016
Size0.54 Mb.
#6596
1   2   3   4   5   6   7

Appendix G: Capital Facilities Program


The Capital Facilities Program comprises approved and unapproved major and medium projects.

Major capital facilities projects are defined as having expenditure over $15m and are subject to Government approval and formal review by the Parliamentary Standing Committee on Public Works (PWC). Medium facilities projects have an expenditure of between $500,000 and $15m. Projects valued over $8m are subject to Government approval. Projects valued between $2m and $15m are required to be notified to and agreed by the PWC but may not be formally reviewed by the Committee. Projects over $15m require referral to and full consideration by the PWC, with approval granted by the Parliament. Details of approved major and medium projects are provided in this Appendix.



The Capital Facilities Program gives priority to projects that support and sustain current and future capability requirements, other government initiatives, meet legislative obligations and provide engineering and infrastructure services, in support of new projects and upgrades to existing facilities.

Approved Major Capital Facilities Projects


The table below provides details on the expenditure to 30 June 2016 on capital facilities projects and budget estimates for 2016-17. Projects valued over $500,000 are included in the table. Descriptions for major projects are provided below the table.

  1. Approved Capital Facilities Projects by State and Federal Electorate

     

    State and
    Electorate


    Total
    Estimated
    Expenditure
    $m


    Estimated
    Cumulative
    Expenditure
    to 30 June 2016
    $m


    2016-17
    Budget
    Estimate
    $m


    Facilities in support of the New Air Combat Capability (AIR 6000)[1]













    RAAF Williamtown

    NSW - Newcastle

    -

    201.4

    161.3

    RAAF Tindal

    NT - Lingiari

    -

    11.0

    81.7

    Total

     

    1,465.4

    212.4

    243.0

    Enhanced Land Force Stage 2 Works[1]













    Lone Pine Barracks

    NSW - Hunter

    -

    117.8

    -

    Puckapunyal Training Area

    Vic. - McEwan

    -

    1.9

    7.1

    Simpson Barracks, Watsonia

    Vic. - Jagajaga

    -

    20.2

    -

    RAAF Amberley

    Qld - Blair

    -

    9.6

    -

    Lavarack Barracks, Townsville

    Qld - Herbert

    -

    66.3

    -

    Townsville Training Area

    Qld - Kennedy

    -

    3.9

    -

    Greenbank Training Area

    Qld - Rankin

    -

    121.0

    -

    Gallipoli Barracks, Enoggera

    Qld - Ryan

    -

    810.6

    -

    Wide Bay Training Area

    Qld - Wide Bay

    -

    100.6

    0.5

    Kokoda Barracks, Canungra

    Qld - Wright

    -

    72.1

    -

    Cultana Training Area

    SA - Grey

    -

    2.9

    14.2

    RAAF Edinburgh

    SA - Wakefield

    -

    34.5

    -

    Majura Field Training Area

    ACT - Fraser

    -

    22.4

    -

    Total

     

    1,457.8

    1,383.7

    21.8

    Defence Logistics Transformation Program[1]













    Defence National Storage and Distribution Centre, Moorebank

    NSW - Hughes

    -

    205.4

    -

    Wadsworth Barracks, Bandiana

    Vic. - Indi

    -

    63.5

    -

    RAAF Amberley

    Qld - Blair

    -

    144.8

    -

    Lavarack Barracks, Townsville

    Qld - Herbert

    -

    131.5

    5.0

    Table 75: Approved Capital Facilities Projects by State and Federal Electorate (Continued)

     

    State and
    Electorate


    Total
    Estimated
    Expenditure
    $m


    Estimated
    Cumulative
    Expenditure
    to 30 June 2016
    $m


    2016-17
    Budget
    Estimate
    $m


    RAAF Edinburgh

    SA - Wakefield

    -

    21.9

    -

    HMAS Stirling, Rockingham

    WA - Brand

    -

    1.3

    -

    Palmer Barracks

    WA - Hasluck




    8.5

    -

    Robertson Barracks

    NT - Solomon

    -

    126.9

    -

    Total

     

    732.6

    703.8

    5.0

    Maritime Patrol Aircraft Replacement (AIR 7000 Phase 2B)[1]













    RAAF Edinburgh

    SA - Wakefield

    -

    5.9

    168.1

    RAAF Townsville

    Qld - Herbert

    -

    -

    -

    RAAF Pearce

    WA - Pearce

    -

    -

    -

    RAAF Darwin

    NT - Solomon

    -

    -

    -

    Total

     

    707.9

    5.9

    168.1

    Air Traffic Control Complex Infrastructure Project, AIR 5431 Phases 2 and 3 and Fixed Base Defence Air Traffic Management and Control System[1]













    RAAF Amberley

    Qld - Blair

    -

    2.3

    43.9

    Army Aviation Centre Oakey

    Qld - Groom

    -

    0.1

    2.6

    RAAF Townsville

    Qld - Herbert

    -

    -

    -

    RAAF Richmond

    NSW - Greenway

    -

    -

    -

    HMAS Albatross

    NSW - Gilmore

    -

    -

    -

    RAAF Williamtown

    NSW - Newcastle

    -

    -

    -

    RAAF East Sale

    Vic. - Gippsland

    -

    0.5

    10.4

    RAAF Woomera

    SA - Grey

    -

    -

    -

    RAAF Edinburgh

    SA - Wakefield

    -

    0.4

    7.8

    RAAF Gingin

    WA - Pearce

    -

    -

    -

    RAAF Pearce

    WA - Pearce

    -

    0.3

    5.8

    RAAF Darwin

    NT - Solomon

    -

    0.4

    6.9

    RAAF Tindal

    NT - Lingiari

    -

    0.9

    17.8

    Total

     

    409.9

    4.9

    95.1

    Battlefield Airlifter Facilities (AIR 8000 Phase 2)













    RAAF Amberley

    Qld - Blair

    370.4

    1.4

    201.0

    Table 75: Approved Capital Facilities Projects by State and Federal Electorate (Continued)

     

    State and
    Electorate


    Total
    Estimated
    Expenditure
    $m


    Estimated
    Cumulative
    Expenditure
    to 30 June 2016
    $m


    2016-17
    Budget
    Estimate
    $m


    HMAS Stirling Redevelopment Stage 3A













    HMAS Stirling, Rockingham

    WA - Brand

    366.8

    14.9

    23.4

    Growler Airborne Electronic Attack Capability Facilities (AIR 5349 Phase 3)













    RAAF Amberley

    Qld - Blair

    348.6

    13.7

    136.5

    LAND 121 Phases 3 and 4 Overlander Facilities Stage 2 [1]













    Lavarack Barracks, Townsville

    Qld - Herbert

    -

    7.5

    60.5

    Gallipoli Barracks, Enoggera

    Qld - Ryan

    -

    3.9

    42.1

    RAAF Williamtown

    NSW - Newcastle

    -

    -

    11.5

    Holsworthy Barracks, Holsworthy

    NSW - Hughes

    -

    -

    1.3

    Puckapunyal Training Area

    Vic. - McEwan

    -

    0.9

    -

    Campbell Barracks

    WA - Curtin

    -

    -

    -

    RAAF Edinburgh

    SA - Wakefield

    -

    -

    -

    Robertson Barracks

    NT - Solomon

    -

    -

    0.5

    Total

     

    276.5

    12.3

    115.9

    RAAF Williamtown Redevelopment Stage 2













    RAAF Williamtown

    NSW - Newcastle

    274.0

    6.3

    102.8

    Campbell Barracks Redevelopment













    Campbell Barracks

    WA - Curtin

    223.6

    10.5

    45.0

    HMAS Albatross Redevelopment Stage 3













    HMAS Albatross

    NSW - Gilmore

    194.2

    141.5

    39.2

    Facilities for MH-60R Seahawk Maritime Combat Helicopters (AIR 9000 Phase 8)[1]













    HMAS Albatross, Nowra

    NSW - Gilmore

    -

    160.7

    -

    HMAS Stirling, Rockingham

    WA - Brand

    -

    6.5

    1.6

    Twofold Bay, Eden

    NSW - Eden-Monaro

    -

    0.3

    0.5

    Total

     

    189.0

    167.5

    2.1

    Helicopter Aircrew Training System (AIR 9000 Phase 7)[1]













    HMAS Albatross, Nowra

    NSW - Gilmore

    157.1

    64.5

    60.2

    Defence Terrestrial Communications Network Facilities Upgrade (JP2047)[2]













    National

     

    130.8

    55.2

    40.7

    Table 75: Approved Capital Facilities Projects by State and Federal Electorate (Continued)

     

    State and
    Electorate


    Total
    Estimated
    Expenditure
    $m


    Estimated
    Cumulative
    Expenditure
    to 30 June 2016
    $m


    2016-17
    Budget
    Estimate
    $m


    Airfield Capital Works[1]













    RAAF Townsville

    Qld - Herbert

    -

    -

    -

    RAAF Curtin

    WA - Durack

    -

    -

    2.3

    RAAF Tindal

    NT - Lingiari

    -

    -

    31.7

    Total

     

    95.3

    -

    34.0

    Delamere Range Facilities Redevelopment













    Delamere Air Weapons Range

    NT - Lingiari

    74.4

    4.7

    49.8

    17th Construction Squadron Relocation













    RAAF Amberley

    Qld - Blair

    71.8

    21.6

    40.0

    Space Telescope (Joint Project (JP) 3029)













    Harold E Holt, Exmouth

    WA - Durack

    63.0

    8.1

    48.0

    REDFIN Infrastructure (JP 2097 Phase 1B)[1]













    Holsworthy Barracks

    NSW - Hughes

    -

    8.1

    5.2

    Campbell Barracks

    WA - Curtin

    -

    0.4

    8.9

    Defence Establishment Howard Springs

    NT - Solomon

    -

    4.0

    1.0

    Lavarack Barracks

    Qld - Herbert

    -

    0.1

    2.0

    Total

     

    50.5

    12.6

    17.1

    Facilities for Chinook Helicopter (AIR 9000 Phases 5B and 5C)













    RAAF Townsville

    Qld - Herbert

    54.8

    20.9

    11.5

    RAAF Base Amberley Sewerage Treatment Plant

     

     

     

     

    RAAF Amberley

    Qld - Blair

    13.0

    0.2

    13.0

    Low Level Bridge Repair

     

     

     

     

    Fleet Base West, Stirling

    WA - Brand

    12.8

    0.6

    6.4

    Facilities for Lead in Fighter Capability Assurance Program (AIR 5438 Phase 1)[1]

     

     

     

     

    RAAF Williamtown

    NSW - Newcastle

    -

    6.6

    -

    RAAF Pearce

    WA - Pearce

    -

    1.0

    3.8

    Total

     

    12.7

    7.6

    3.8

    JHC Facilities Upgrades - Interim Works [1]




     

     

     

    Larrakeyah / Coonawarra

    NT - Solomon

    -

    3.0

    2.7

    Table 75: Approved Capital Facilities Projects by State and Federal Electorate (Continued)

 

State and
Electorate


Total
Estimated
Expenditure
$m


Estimated
Cumulative
Expenditure
to 30 June 2016
$m


2016-17
Budget
Estimate
$m


RAAF Pearce

WA - Pearce

-

-

2.3

RAAF Townsville

QLD - Herbert

-

-

1.9

Total

 

9.8

3.0

6.8

Projects in or about to enter Defects Liability Period[3]

 

 

 

21.4

Total

 

7,762.7

2,877.9

1,551.5

Notes

  1. These projects cross state and electoral boundaries. Estimated cumulative expenditure to 30 June 2016 and expenditure estimates for 2016-17 are provided in the table per location.

  2. This project is delivering facilities at over 200 locations that cross state and electoral boundaries.

  3. This amount represents the expenditure estimates for contract administration of five completed projects during their first year in-use and construction completion of seven medium works projects that are under the $2m reporting threshold to the Public Works Committee.


New South Wales
RAAF Base Williamtown Redevelopment Stage 2

This project will sustain and improve the functionality and capability of RAAF Base Williamtown, NSW, including upgrades or replacement of critical ageing infrastructure to meet future requirements. The project is scheduled for completion by mid 2021.
HMAS Albatross Redevelopment Stage 3

This project will replace ageing and obsolete engineering services and infrastructure at HMAS Albatross. The project will also provide a combination of new and refurbished facilities to support operational and training outcomes as well as enabling functions. The project is scheduled for completion by mid 2017.
Queensland
Battlefield Airlifter Facilities (AIR 8000 Phase 2)

This project will provide facilities at RAAF Base Amberley, Qld to accommodate and support the operation of the new C-27J Battlefield Airlifter (BFA) aircraft. The project is scheduled for completion by early 2019.
Growler Airborne Electronic Attack Capability Facilities (AIR 5349 Phase 3)

This Project will provide the necessary working accommodation, maintenance, warehousing and training facilities at RAAF Base Amberley, Qld to support the introduction of the Growler Airborne Electronic Attack Capability. The project is scheduled for completion by mid 2021.
17th Construction Squadron Relocation

This project will provide facilities to collocate 17th Construction Squadron with 6th Engineer Support Regiment and 21st Construction Squadron at RAAF Base Amberley, Qld. The project is scheduled to be completed by late 2016.
Facilities for Chinook Helicopter (AIR 9000 Phases 5B and 5C)

This project will provide new and upgraded facilities to support the introduction into service of the new CH47 F Chinook Helicopter. The project will provide working accommodation, simulator facilities, aircraft hangars and workshops, storage facilities and supporting infrastructure for the Army’s 5th Aviation Regiment at RAAF Base Townsville. The project is scheduled for completion by mid 2017.
Western Australia
HMAS Stirling Redevelopment Stage 3A

This project will provide upgrades and refurbishment of existing critical shortfalls to infrastructure and facilities. The project is scheduled for completion by late 2019.
Campbell Barracks Redevelopment

This project will provide a new Headquarters for the Special Air Services Regiment, communications facilities, working accommodation, storage facilities and supporting site infrastructure at Campbell Barracks, WA. The project is scheduled for completion by late 2018.
Space Telescope (Joint Project (JP) 3029)

This project will provide facilities and infrastructure to support the operations of the Space Surveillance Telescope, which will enable ADF space surveillance capability, enhanced global surveillance capability, and an increased ability to track space debris. The project is scheduled for completion by late 2018.
Northern Territory
Delamere Range Facilities Redevelopment

This project will redevelop key range facilities and infrastructure to enable Growler and Mobile Threat Training Emitter Systems capability at Delamere Air Weapons Range, NT. The project is scheduled for completion by mid 2018.
VARIOUS Locations
New Air Combat Capability (AIR 6000 NACC)

This project will provide new and upgraded facilities and infrastructure to support the introduction of the Joint Strike Fighter at RAAF Base Williamtown Newcastle, NSW, and RAAF Base Tindal, Katherine, NT with support facilities and infrastructure provided at Defence Establishment Myambat, NSW and seven Forward Operating Bases. The project is scheduled for completion by late 2022.
Enhanced Land Force (ELF) Stage 2

This project will provide modern purpose-built facilities and supporting infrastructure for the 8th/9th Battalion the Royal Australian Regiment and supporting elements of the Army's 7th Brigade at Gallipoli Barracks in Enoggera, Brisbane. The project includes the construction of new and refurbished accommodation and training facilities, as well as common use facilities and site infrastructure upgrades at Enoggera and other Defence sites across four States and both mainland Territories.

Facilities at Townsville, Singleton, Duntroon and Watsonia will provide modern accommodation and supporting infrastructure for increased Army career training. In Sydney, at RAAF Bases Amberley and Edinburgh, and at nine other Defence Training Areas, new and refurbished facilities with site infrastructure upgrades will be provided for Army and joint enabling elements supporting the Enhanced Land Force capabilities. Facilities at Garden Island, Balmoral, HMAS Penguin, Watsonia, Puckapunyal, RAAF Base Amberley, Townsville Field Training Area, Majura Field Training Area and the Royal Military College Duntroon have been completed.



The final project element to be delivered is at Cultana Training Area and is scheduled for completion by late 2018.
Defence Logistics Transformation Program (DLTP)

This project will modernise and enhance the wholesale storage, distribution and land materiel functions of Joint Logistic Command units nationally to provide optimum support to Defence operations. The facilities component of the program will provide enhanced logistics facilities at Moorebank, NSW, Bandiana, Vic., Amberley and Townsville, Qld, Palmerston, NT, Edinburgh, SA and Guilford and Garden Island, WA. The project is scheduled for completion by mid 2016.
Maritime Patrol Aircraft Replacement (AIR 7000 Phase 2B)

This project will provide new and upgraded facilities and infrastructure to support the introduction of the P-8A aircraft at RAAF Base Edinburgh, SA, RAAF Base Townsville, Qld, RAAF Base Pearce, WA and RAAF Base Darwin, NT, as well as additional explosive ordnance facilities at HMAS Stirling. The project is scheduled for completion by late 2020.
Air Traffic Control Complex Infrastructure Project and AIR 5431 Phases 2 and 3, and Fixed Base Defence Air Traffic Management and Control System

This project will provide facilities across 13 bases in support of replacement Air Traffic Management Surveillance, Command and Control Systems under AIR 5431 Phases 2 and 3, incorporating the replacement of aged and degraded Air Traffic Control Towers. The project is scheduled for completion by late 2021.
LAND 121 Stage 2 (Phases 3 and 4)

This project will provide facilities across nine bases to sustain the B-vehicle fleet IAW the Basis of Issue for Army, RAAF and JLC. These facilities will maintain (workshops and repair parts storage), support (fuel points, loading ramps, wash points and weigh bridges) and sustain (shelters and hardstand) the vehicles from vehicle acquisition Phase 3A (G-Wagon), Phase 3B (Light/Light Weight and Medium/Heavy) and Phase 4 (Protected Mobility Vehicles Light). The project is scheduled for completion by mid 2019.
Facilities for the MH-60R Seahawk Maritime Combat Helicopters (AIR 9000 Phase 8)

This project will provide new and upgraded facilities for maritime helicopter operations at HMAS Albatross, NSW and HMAS Stirling, WA and at Eden, NSW. The project includes the provision of facilities for aircraft hangars and workshops, synthetic training and working accommodation primarily at HMAS Albatross as well as additional explosive ordnance facilities at HMAS Stirling and Eden. The project is scheduled for completion by mid 2017.
Helicopter Aircrew Training System (JP 9000 Phase 7)

This project will provide new and upgraded training facilities to support the introduction of the new joint Navy and Army Helicopter Aircrew Training System. The project will provide working accommodation, simulation facilities, training facilities and aircraft hangars at HMAS Albatross, NSW as well as communication rooms and helicopter operation areas at Jervis Bay Air field, ACT. The project is scheduled for completion by mid 2017.
Defence Terrestrial Communications Network Facilities Upgrade (JP 2047)

This project will provide upgraded and new communications infrastructure and supporting facilities at multiple Defence owned and leased sites across Australia. The project will support the introduction into service of the new Defence Terrestrial Communications Network. The project is scheduled for completion by late 2017.
Airfield Capital Works (Curtin, Tindal and Townsville)

This project will resurface asphalt pavement and replace airfield lighting at RAAF Base Curtin, WA, RAAF Base Tindal, NT and RAAF Base Townsville, Qld. The project is scheduled for completion by mid 2018.
REDFIN Infrastructure (JP2097 Phase 1B)

This project will provide facilities for the Special Operations Vehicle (SOV) fleet to support mobility and Networked Special Operations Capability. The project is scheduled for completion by early 2019.


Download 0.54 Mb.

Share with your friends:
1   2   3   4   5   6   7




The database is protected by copyright ©ininet.org 2024
send message

    Main page