Appendix D : Current Status of Previously Reported Top 30 Projects (Projects Reported in the Last Five Financial Years)
This table provides an update on the status of major projects reported in previous financial years. These projects were not ranked in the Top 30 projects by expenditure in 2016-17.
-
Current Status of Previously Reported Top 30 Projects (Projects Reported in the Last Five Financial Years)
DOMAIN/
Project
|
Project Number/ Phase
|
Last Financial Year reported in Top 30
|
Approved Project Expenditure $m
|
Cumulative Expenditure to 30 June 2016 $m
|
Budget Estimate 2016-17 $m
|
Status Report
|
AEROSPACE
|
|
|
|
|
|
|
Heavy Airlift- Additional C-17A
|
AIR 8000 Phase 4
|
2015-16
|
1,411
|
1,182
|
27
|
Prime Contractor: Boeing, through a FMS case with the US Air Force.
This project has delivered an additional four C-17 Globemaster III aircraft and related provisions, including an enhanced US-common electronic warfare self-protection system, to complement the four aircraft acquired under Project AIR 8000 Phase 3. All eight aircraft are now in service with the Air Force and, following the installation of the enhanced electronic warfare self-protection system on the eighth and final aircraft in fourth quarter 2016, Final Operational Capability is expected in December 2017.
|
Air to Air Refuelling Capability
|
AIR 5402
|
2015-16
|
1,822
|
1,766
|
6
|
In November 2015, Airbus Defence and Space completed all major contracted deliveries.
During 2016-17 the final spares deliveries are expected and the project will transfer residual activities to the sustainment organisation in order to finalise project closure.
|
Airborne Early Warning and Control System
|
AIR 5077 Phase 3
|
2014-15
|
3,920
|
3,583
|
23
|
This project has delivered six E-7A Wedgetail Airborne Early Warning and Control aircraft and the associated ground and support systems. The project achieved FOC in May 2015. During 2016-17 the project will transfer residual activities and associated funding in order to finalise project closure.
|
C-17 Globemaster III Heavy Airlifter
|
AIR 8000 Phase 3
|
2014-15
|
1,518
|
1,422
|
10
|
The project procured the initial four C-17 Globemaster III for Australia. Residual project tasks continue to be transitioned to in-service management agencies with the aim to achieve project closure in June 2017.
|
Table 72: Current Status of Previously Reported Top 30 Projects (Projects Reported in the Last Five Financial Years) (Continued)
DOMAIN/
Project
|
Project Number/ Phase
|
Last Financial Year reported in Top 30
|
Approved Project Expenditure $m
|
Cumulative Expenditure to 30 June 2016 $m
|
Budget Estimate 2016-17 $m
|
Status Report
|
Hornet Upgrade Project
|
AIR 5376 Phase 2
|
2011-12
|
1,883
|
1,660
|
4
|
The Classic Hornet simulator improvement program is the final approved element of the project. This improvement program is under contract and on schedule for installation and testing during early 2016, with completion in mid 2016 and Final Operational Capability scheduled for 2017.
|
Airborne Surveillance for Land Operations
|
JP 129 Phase 2
|
2012-13
|
98
|
77
|
1
|
The project has successfully delivered the majority of equipment required for the capability and has transitioned support activities to the sustainment organisation. The final equipment delivery of four One System Remote Video Terminals along with Project closure activities are planned during 2016-17.
|
Additional Chinook Helicopter Project
|
AIR 9000 Phase 5C
|
2015-16
|
642
|
444
|
31
|
Prime Contractor: Boeing Military Aircraft through US FMS case with the US Army
The project is acquiring seven CH-47F Chinook helicopters, two Transportable Flight Proficiency Simulators, maintenance training systems and associated spares. These aircraft will replace six CH-47D Chinook helicopters being withdrawn from Army service. The Chinook provides the Army with its medium-lift battlefield support helicopter capability. The new helicopters will be based at the 5th Aviation Regiment, RAAF Base Townsville, Queensland.
All seven CH-47Fs were delivered ahead of schedule with the final aircraft arriving at RAAF Base Townsville in August 2015; the Transportable Flight Proficiency Simulators were delivered in 2014-15. The CH-47F configuration is to be maintained in close alignment with the US Army baseline in order to improve interoperability and minimise the cost of ownership in sustainment; however, the Australian fleet will be modified slightly to meet certain Australian-unique requirements and to enable embarked operations from the new Canberra Class Landing Helicopter Dock ships. At the end of 2015, aircrew and maintainer transition training was completed and Australian Military Type Certification and Service Release of the CH-47F was granted. Initial Operational Capability was declared by Chief of Army in March 2016.
During 2016-17, the project will focus upon provision of support required for the declaration of Final Operational Capability in January 2017.
|
Rotary Wing for Land Force
|
AIR 87 Phase 2
|
2012-13
|
2,033
|
1,867
|
3
|
Project closure and the declaration of Final Operational Capability will be completed in 2016.
|
Table 72: Current Status of Previously Reported Top 30 Projects (Projects Reported in the Last Five Financial Years) (Continued)
DOMAIN/
Project
|
Project Number/ Phase
|
Last Financial Year reported in Top 30
|
Approved Project Expenditure $m
|
Cumulative Expenditure to 30 June 2016 $m
|
Budget Estimate 2016-17 $m
|
Status Report
|
JOINT
|
|
|
|
|
|
|
Military Satellite Capability – Wideband Terrestrial Infrastructure
|
JP 2008 Phase 5B1
|
2015-16
|
208
|
159
|
20
|
Tranche 1 of this project will deliver small, medium and large sized transportable satellite terminals for Australian Defence Force units and introduces into service an advanced waveform modem with associated spares.
The satellite terminals will expand the use of the Wideband Global Satellite Communications system by introducing certified terminals to Australian land forces.
Four large terminals were delivered to the Middle East Region in support of operations in late 2015. The remaining transportable terminal acceptance testing and delivery will be achieved in late 2016. The system level verification and the centralised monitoring and control system verification are scheduled for 2016-17.
The key risks for the project are the completion of the engineering reviews and the network design for the centralised monitoring and control.
|
Battlespace Communications System (Land)
|
JP 2072 Phase 1
|
2011-12
|
261
|
238
|
4
|
Activities for project closure continue, including the transfer of the scope and funding for the Battlespace Communications Systems (LAND) Integration and Test capability to a later Phase of JP 2072. Project closure is planned for mid 2016.
|
Battlespace Communications System (Land)
|
JP 2072 Phase 2A
|
2014-15
|
465
|
322
|
9
|
The rollout of digital radios and ancillary equipment has been completed with the exception of some specialised ancillary equipment and training equipment. The selection of the ancillary items is undergoing a design acceptance process for inclusion into the dismounted voice communications configurations.
Mature support contracts have been established with the major suppliers and the management of these contracts is being transitioned to the support group of the System Program Office. The legacy fleets of communications equipment are being progressively withdrawn.
|
Table 72: Current Status of Previously Reported Top 30 Projects (Projects Reported in the Last Five Financial Years) (Continued)
DOMAIN/
Project
|
Project Number/ Phase
|
Last Financial Year reported in Top 30
|
Approved Project Expenditure $m
|
Cumulative Expenditure to 30 June 2016 $m
|
Budget Estimate 2016-17 $m
|
Status Report
|
Battle Management System
|
LAND 75 Phase 3.4
|
2014-15
|
317
|
256
|
28
|
This project has delivered the Mounted Battle Management Systems including command post systems to the ADF in cooperation with LAND 125 Phase 3A (dismounted systems) and JP 2072 Phase 1 (Combat Radio System). All of the physical vehicle installations, supplies and training have been delivered to Army. Final Acceptance of the acquisition contract was achieved within the financial provision and project closure activities have commenced.
Prime Contractor: Elbit Systems Limited (ESL)
|
C-130J Large Aircraft Infrared Countermeasures (LAIRCM)
|
AIR 5416 Phase 4B2
|
2015-16
|
237
|
58
|
38
|
Prime Contractor: US Air Force Foreign Military Sales (utilising Lockheed Martin and Northrop Grumman).
This project will provide the Air Force C-130J Hercules fleet with the Large Aircraft Infrared Counter Measures (LAIRCM) system to enhance the Electronic Warfare Self Protection of the aircraft. The LAIRCM capability design, hardware and the modification of the first four aircraft in the US are being provided via a Foreign Military Sales case. The remaining eight aircraft will be modified in Australia by Airbus Group Australia Pacific pending successful contract negotiations.
Modification of the first two aircraft is proceeding on schedule in the US. Completion of the US based LAIRCM modification effort on the first four aircraft will occur before the end of 2016 with the entire project related activities under the Foreign Military Sales case due for completion in the first half of 2017.
The key risk for this project is contractor performance maintaining the project plan, particularly with respect to the activities leading to the aircraft modification and the timely delivery of airworthiness artefacts to support the ongoing certification effort.
|
Table 72: Current Status of Previously Reported Top 30 Projects (Projects Reported in the Last Five Financial Years) (Continued)
DOMAIN/
Project
|
Project Number/ Phase
|
Last Financial Year reported in Top 30
|
Approved Project Expenditure $m
|
Cumulative Expenditure to 30 June 2016 $m
|
Budget Estimate 2016-17 $m
|
Status Report
|
Fixed Defence Air Traffic Control Surveillance Sensors
|
AIR 5431 Phase 2
|
2015-16
|
200
|
49
|
24
|
This project will provide new radars and Automatic Dependent Surveillance - Broadcast sensors to replace the aging radars located at nine Defence airfields. The new radars and sensors will support Defence Air Traffic Management and provide data to Defence’s Air Battle Management systems and Airservices Australia.
The project successfully completed System Requirements/System Definition Reviews in December 2015 and planning for Preliminary Design Review is well underway with the review occurring in May 2016.
During 2016-17 the project will continue to progress through the engineering design process, culminating in the Detailed Design Review in January 2017.
The key risks for this project are site-related, namely potential weather and subterranean issues which could result in delays to the installation program and subsequent achievement of the Initial Materiel Release and Final Materiel Release milestones.
Prime Contractor: Airbus Defence and Space GmbH
|
Indian Ocean Ultra High Frequency Satellite Communication
|
JP 2008 Phase 5A
|
2012-13
|
421
|
341
|
5
|
This project has delivered an upgraded Ultra High Frequency Satellite capability to the ADF. The associated network management system has experienced delays associated with software development. The project was re-baselined to mitigate delay and introduce an Interim Capability which will provide an Integrated Waveform capability.
|
Next Generation Satellite Communications System
|
JP 2008 Phase 4
|
2013-14
|
869
|
569
|
6
|
The satellites that make up the Wideband Global Satellite Communications System constellation have all been launched successfully and are fully operational. The project has achieved Final Materiel Release.
The project has transitioned into sustainment and project closure will complete during 2016-17.
|
Dismounted Battle Group and Below C3 System
|
LAND 125 Phase 3A
|
2011-12
|
107
|
92
|
-
|
This project is complete. Closure will be synchronised with the Land 75 Phase 3.4 project closure.
Prime Contractor: Elbit Systems Limited (ESL)
|
Table 72: Current Status of Previously Reported Top 30 Projects (Projects Reported in the Last Five Financial Years) (Continued)
DOMAIN/
Project
|
Project Number/ Phase
|
Last Financial Year reported in Top 30
|
Approved Project Expenditure $m
|
Cumulative Expenditure to 30 June 2016 $m
|
Budget Estimate 2016-17 $m
|
Status Report
|
Military Satellite Capability – Wideband Terrestrial Terminals (WTT)
|
JP 2008 Phase 3H
|
2013-14
|
45
|
39
|
-
|
Initial Materiel Release and Initial Operating Capability have been declared. All terminals have been issued to units, with some terminals now supporting operations, and introduction into service training has been completed. The project continues to pursue Technical Certification. Final Materiel Release and Final Operating Capability will be declared in 2016.
|
Battlespace Communications System (LAND)
|
JP 2072 Phase 3
|
2014-15
|
179
|
147
|
3
|
The project has delivered Tactical Data and Voice radios for installation into vehicles by project LAND 75, Battlefield Management System as part of the first Work package.
Tender evaluation continues for the remaining work package which will support the development of a Tactical Communications Network.
|
High Frequency Modernisation
|
JP 2043 Phase 3A
|
2014-15
|
580
|
485
|
13
|
This project has delivered a Defence High Frequency Communications System for Defence long-range communications. The Direction Finding and Signal Enhancement capability, Project Nullarbor, entered contract in 2014 and is on track to be delivered in late 2016 with most build and integration activities being conducted in 2015-16.
Life-of-Type obsolescence remediation work is progressing as scheduled.
|
Joint Command Support Environment
|
JP 2030 Phase 8
|
2014-15
|
257
|
206
|
-
|
Final Materiel Release of the Joint Command Support Environment was achieved in late 2015. Full Acceptance Into Service for operation on the Defence Secret Network is in progress and expected to be completed in 2016.
|
NULKA PH5A Replenish Nulka Warstock
|
SEA 1397 Phase 5A
|
2014-15
|
88
|
78
|
7
|
This project is replenishing Navy’s Nulka off-board anti-ship missile decoy inventory.
The project is tracking to plan with contract closure commenced. All sub-contract obligations have been completed with contractual closure being progressed. The final decoy round assembly and delivery with the Prime Contractor will continue until March 2017 to support a smooth transition to sustainment.
A Joint Nulka Sustainment Plan with United States Navy has been agreed as in currently in the implementation phase.
Prime Contractor: BAE Systems.
|
Table 72: Current Status of Previously Reported Top 30 Projects (Projects Reported in the Last Five Financial Years) (Continued)
DOMAIN/
Project
|
Project Number/ Phase
|
Last Financial Year reported in Top 30
|
Approved Project Expenditure $m
|
Cumulative Expenditure to 30 June 2016 $m
|
Budget Estimate 2016-17 $m
|
Status Report
|
Bridging Air Combat Capability – Super Hornet Weapons
|
AIR 5349 Phase 2
|
2014-15
|
306
|
216
|
21
|
This project introduces into service a number of new weapons including the USN common AIM-9X short-range air-to-air missile, the latest version of the AIM-120 medium-range air-to-air missile, the AGM-154 Joint Stand-off Weapon and countermeasures for the Australian Super Hornet Program. These weapons will significantly enhance the Air Force’s ability to conduct air, land and maritime strike operations.
Initial delivery of new AIM-120s is scheduled for September 2016. Operational test and evaluation of the new AIM-120s and AGM-154s is planned to start from May 2017 to realise the full capability. All other weapons and countermeasures in the approved project scope have been delivered and are operational.
The key risk for this project remains schedule. Both the USAF and USN are under budgetary pressure and have identified early indications of schedule slip in their domestic programs and production contracts that may flow on to impact the Australian products.
Prime Contractor: United States Foreign Military Sales cases.
|
Follow-on Stand Off Weapon Capability
|
AIR 5418 Phase 1
|
2011-12
|
319
|
284
|
-
|
This project introduced into service the AGM-158A Joint Air-to-Surface Stand-off Missile for the Classic Hornet. The Air Force has achieved Final Operating Capability and all approved project scope has been delivered. Work to finalise the project is ongoing. The project will be closed in 2016-17.
|
Lightweight Torpedo Replacement
|
JP 2070 Phase 2
|
2013-14
|
342
|
319
|
1
|
This project has introduced the MU90 lightweight torpedo into service with the Anzac and Adelaide class frigates. Navy has achieved Final Operating Capability with the MU90 and the project will be closed in 2016-17 at the end of the initial MU90 in-service support contract.
|
New ADF Anti-Submarine Lightweight Torpedo
|
JP 2070 Phase 3
|
2011-12
|
304
|
276
|
-
|
All project scope has been delivered and the project is in closure.
|
Table 72: Current Status of Previously Reported Top 30 Projects (Projects Reported in the Last Five Financial Years) (Continued)
DOMAIN/
Project
|
Project Number/ Phase
|
Last Financial Year reported in Top 30
|
Approved Project Expenditure $m
|
Cumulative Expenditure to 30 June 2016 $m
|
Budget Estimate 2016-17 $m
|
Status Report
|
Evolved Seasparrow Missile (ESSM) Upgrade
|
SEA 1352 Phase 1
|
2015-16
|
400
|
184
|
10
|
This project will upgrade and replenish the existing Evolved Sea Sparrow Missile capability to ensure that the Navy’s surface combatant force can defeat the evolving regional anti ship missile threat.
The Project is participating in cooperative development of the ESSM Block 2 missile and is planning to procure ESSM Block 2 to replace the current ESSM stock. Australian involvement also includes Australian ship integration studies.
Significant activities planned for 2016-17 include achieving Missile Critical Design, signature of the Consortium’s Production Memorandum of Understanding and completion of all integration studies before Intermediate Pass is sought from Government in the first quarter of 2017.
|
Standard Missile-2 Conversion and Upgrade
|
SEA 4000 Phase 3.2
|
2013-14
|
114
|
66
|
4
|
This project is converting the rail launched Standard Missile 2 Block IIIA missiles, currently employed with Adelaide class frigates, to a vertical launch configuration suitable for employment with Hobart class destroyers. In addition, a proportion of the stock will be upgraded to the more capable Block IIIB configuration.
The project remains on track and within budget to support the planned Operational Test and Evaluation and Operational Capability of Hobart class destroyers. The Final Materiel Release is being amended from June 2019 to May 2021 to account for the revised transition schedule associated with delays to the Hobart class destroyers.
|
LAND
|
|
|
|
|
|
|
Light and Lightweight Capability (LLC) Field Vehicles, Modules and Trailers
|
LAND 121 Phase 3
|
2015-16
|
1,018
|
864
|
37
|
This project will deliver approximately 2,150 G-Wagons, 540 modules and 1,800 trailers. The G-Wagons, together with the trailers and a range of modules, will be used by the Army and the Air Force for training, and to support domestic security and emergency response efforts. The vehicles will also be employed on Humanitarian Assistance/Disaster Relief and low-threat operations. The project is currently in the materiel release phase of delivering to units.
During 2016-17, this project will finalise delivery of vehicles and trailers to units.
|
Table 72: Current Status of Previously Reported Top 30 Projects (Projects Reported in the Last Five Financial Years) (Continued)
DOMAIN/
Project
|
Project Number/ Phase
|
Last Financial Year reported in Top 30
|
Approved Project Expenditure $m
|
Cumulative Expenditure to 30 June 2016 $m
|
Budget Estimate 2016-17 $m
|
Status Report
|
Mulwala Redevelopment Project
|
JP 2086 Phase 1
|
2013-14
|
371
|
362
|
5
|
This project will deliver a modernised propellant manufacturing facility at the Commonwealth owned Mulwala Munitions Factory, to replace the existing, but now obsolete, plant that dates back to the 1940s. The modernised facility will meet more stringent and contemporary environmental, work, health and safety standards. The factory manufactures propellants for incorporation into ADF munitions, and is operated by Thales Australia Limited on behalf of the Commonwealth.
A Deed of Completion for this project has been agreed with the contractor, and Final Acceptance was awarded on 30 April 2015.
During 2016-17, the five major defects identified at Final Acceptance will be remediated to enable the project to close by the end of 2016.
The project remains on the Project of Concern list pending completion of the final defect.
|
Digital Terminal Control System (DTCS)
|
LAND 17 Phase 1B
|
2013-14
|
121
|
93
|
-
|
The project has delivered 152 Digital Terminal Control Systems. This capability allows artillery forward observers and joint terminal attack controllers to identify targets with greater accuracy through the use of precision targeting software. It also provides the means to digitally request fire support from land, sea or airborne weapon systems.
The final control terminal software and the support systems have been delivered to allow the full operating capability milestone to be met on schedule in March 2016. The project is scheduled to close in Q2 2016.
|
Replacement Artillery
|
LAND 17 Phase 1A
|
2013-14
|
158
|
158
|
-
|
This project has completed delivery of the Towed Howitzers and the battle management system. The Course Correcting Fuze element has been transferred to LAND 17 Phase 1C.1 (Additional Lightweight Towed Howitzers), and the project was closed in Apr 2015.
|
Counter - Rocket, Artillery and Mortar (C-RAM) Project
|
LAND 19 Phase 7A
|
2012-13
|
265
|
186
|
-
|
This project has delivered a 'sense and warn' force protection capability.
During 2016-17, this project will complete support arrangements for the counter-rocket, artillery and mortar systems and will be closed.
|
Table 72: Current Status of Previously Reported Top 30 Projects (Projects Reported in the Last Five Financial Years) (Continued)
DOMAIN/
Project
|
Project Number/ Phase
|
Last Financial Year reported in Top 30
|
Approved Project Expenditure $m
|
Cumulative Expenditure to 30 June 2016 $m
|
Budget Estimate 2016-17 $m
|
Status Report
|
Australian Protected Route Clearance Capability
|
JP 154 Phase 3A
|
2012-13
|
36
|
36
|
-
|
The project has delivered the Protected Route Clearance equipment to the Army's combat engineers and transitioned the capability to sustainment. The Project completed introduction into service, including some residual work to integrate the mine roller to the in-service Bushmaster. This project was closed in March 2016.
|
Bushranger Protected Mobility Vehicle
|
LAND 116 Phase 3
|
2015-16
|
1,251
|
1,032
|
6
|
This project will deliver approximately 1,050 vehicles, across its five production periods, in seven variants. The vehicles provide protected land mobility to the Army’s combat units and Air Force Airfield Defence Guards. The delivery of Production Period 5 vehicles Commenced in July 2013 and will conclude in September 2016.
During 2016-17, this project will deliver the final 12 of the 214 Production Period 5 vehicles and will support delivery of the Full Operational Capability scheduled for December 2016.
The key risk for this project is incorporating all production line engineering changes into updated support documentation to allow project closure to proceed on schedule over 2017.
|
M-113 Upgrade
|
LAND 106
|
2012-13
|
791
|
791
|
-
|
This project has delivered 431 M-113 AS4 vehicles in seven variants, Appliqué Armour and Integrated Logistic Support. The final air and sea transportation certification is complete and the project was closed in 2014-15.
|
Table 72: Current Status of Previously Reported Top 30 Projects (Projects Reported in the Last Five Financial Years) (Continued)
DOMAIN/
Project
|
Project Number/ Phase
|
Last Financial Year reported in Top 30
|
Approved Project Expenditure $m
|
Cumulative Expenditure to 30 June 2016 $m
|
Budget Estimate 2016-17 $m
|
Status Report
|
Mounted Combat Reconnaissance Capability
|
LAND 400 Phase 2
|
2015-16
|
117
|
14
|
41
|
Prime Contractor: Not in contract.
This project will deliver around 225 Combat Reconnaissance Vehicles and support systems that will replace the current Australian Light Armoured Vehicle (ASLAV) capability.
During 2016-17 the project will conduct a review of the Australian Industry Involvement aspects of this project phase to ensure alignment with the 2016 Defence Industry Policy Statement.
The review will inform the Risk Mitigation Activities (RMA) that shortlisted tenderers will be invited to participate in. The RMA will validate technical compliance through a Test and Evaluation program; improve Australian Industry involvement, assess cost and capability trade-off options.
These activities will enable the development of options, differentiated by both cost and capability levels, for presentation to Government at Second Pass.
The key risk for the project during 2016-17 are delays to the completion of the Australian Industry Involvement review leading to slippage in commencement of the Risk Mitigation Activities.
|
Table 72: Current Status of Previously Reported Top 30 Projects (Projects Reported in the Last Five Financial Years) (Continued)
DOMAIN/
Project
|
Project Number/ Phase
|
Last Financial Year reported in Top 30
|
Approved Project Expenditure $m
|
Cumulative Expenditure to 30 June 2016 $m
|
Budget Estimate 2016-17 $m
|
Status Report
|
MARITIME
|
|
|
|
|
|
|
Amphibious Ships (LHD)
|
JP 2048 Phase 4A/B
|
2015-16
|
3,093
|
2,785
|
19
|
LHD #1 was delivered to the Navy in October 2014 and commissioned as HMAS <<Canberra>> in November 2014.
LHD #2 was delivered to the Navy in October 2015 and commissioned as HMAS <<Adelaide>> in December 2015.
The project is now focused on transition of supporting products to the sustainment organisation and close-out of residual defects, deficiencies and associated testing, which is programmed to complete in late 2016.
Project and Materiel Acquisition Agreement closure is scheduled and on track for October 2017.
Prime contractor: BAE Systems Australia Maritime
|
Amphibious Watercraft Replacement
|
JP 2048 Phase 3
|
2014-15
|
238
|
178
|
-
|
The third and final batch of four craft arrived in Australia in November 2015. After successful installation and testing of the military communication and navigation systems, the final four craft were delivered to Navy on 7 Mar 2016.
The Project achieved Integrated Logistics Support Certification (Final) on 29 Feb 2016 and are currently transitioning the support products to the sustainment organisation.
Final Materiel Release and Full Operational Capability has moved from February 2016 (as scheduled) to June 2016 due to the delay of the Landing Helicopter Dock (LHD)/LHD Landing Craft interface trials from 4th Quarter 2015 to 2nd Quarter 2016.
Project and Materiel Acquisition Agreement closure is scheduled and on track for December 2016.
Prime contractor: Navantia
|
Anzac Anti-ship Missile Defence
|
SEA 1448 Phase 2A
|
2014-15
|
387
|
364
|
16
|
During 2016-17, this project will continue with the Anti Ship Missile Defence Follow-On-Ship upgrade work on HMA Ships Parramatta, Toowoomba and Stuart.
|
Table 72: Current Status of Previously Reported Top 30 Projects (Projects Reported in the Last Five Financial Years) (Continued)
DOMAIN/
Project
|
Project Number/ Phase
|
Last Financial Year reported in Top 30
|
Approved Project Expenditure $m
|
Cumulative Expenditure to 30 June 2016 $m
|
Budget Estimate 2016-17 $m
|
Status Report
|
MARITIME
|
|
|
|
|
|
|
Anzac Anti-ship Missile Defence
|
SEA 1448 Phase 2B
|
2015-16
|
679
|
617
|
39
|
This project will deliver a phased array radar system to the Anzac Class Frigates for target indication/tracking, mid-course guidance and target illumination for the Evolved Sea Sparrow Missile, and a new dual navigation radar system to replace the existing navigation radar suite.
During 2016-17, this project will continue with the Anti Ship Missile Defence (ASMD) Follow-On Ship upgrade work on HMA Ships Parramatta, Toowoomba and Stuart.
The key risk for this project is the supply and efficient management of shipyard resources required to maintain schedule with three ships in the ASMD Upgrade and Refit Program at any one time.
Prime Contractor: CEA Technologies Proprietary Limited and the Warship Asset Management Agreement (between Commonwealth of Australia, BAE Systems, Saab Australia and Naval Ship Management (Australia)).
|
SM-1 Replacement Project
|
SEA 1390 Phase 4B
|
2013-14
|
418
|
354
|
9
|
Project deliverables have been transitioned to in-service sustainment. Chief of Navy agreed the Final Operating Capability in June 2015. Formal project closure is scheduled to complete during 2016-17.
|
Future Submarine - Acquisition
|
SEA 1000 Phase 1A
|
2015-16
|
299
|
195
|
49
|
Prime Contractor: Not in contract
This project will deliver Australia's Future Submarine capability.
During 2016-17, the Project will continue planning and mobilising to deliver a rolling acquisition program for the delivery of 12 regionally superior Future Submarines including the sovereign capability for operation and sustainment.
|
Share with your friends: |