Off-site project
|
Evaluation grade
|
Ecological environment
|
Sound environment
|
Water environment
|
Ambient air
|
Airport avenue project
|
The area along the project road belongs to insensitive area of ecological environment without key environmental protection objects including natural reserves or cultural relics preservation, which is thus evaluated as Grade III.
|
There are no special sensitive points such as hospitals and sanatoriums within the scope at 200m from both sides along the road, and main environmental sensitive point is town residence area, which is thus evaluated as Grade II.
|
The project road does not cross surface water region, and the discharge quantity of sewage during construction period for road construction is small. Thus, the evaluation for surface is determined as Grade III.
|
The evaluation scope does not include Category I ambient air quality function area and the ambient quality of the main evaluation factor is not close to or beyond the standard for ambient quality. The project does not emit the special pollutants that are greatly harmful to human body health or ecological environment; the evaluation of ambient air of the project is Grade III.
|
Pipeline project
|
The impact during construction period mainly includes vegetation damage, occupancy; the evaluation grade is Grade III.
|
After construction of project, the functional area belongs to Category II Standard area regulated by GB3096-2008. Its impact on acoustic environment is mainly reflected during construction period and the impact of noise during the construction period will disappear with the ending of construction period. Considering the degree of the affected people comprehensively, the evaluation for sound environment is determined as Grade III.
|
The project is newly constructing sewage, water supply, air supply net of 4521.212m and aviation fuel transportation, which does not cause negative impact on the water environment during the operation. Judging from HJ/T2.3-93, the evaluation grade of surface water is determined as Grade III.
|
The impact of the project on the atmosphere is mainly reflected in construction period. Pollutants are mainly the construction dusts, the type of generated atmosphere pollutant is simple and the affected area is limited. According to judgment requirement of guidelines, the impact evaluation of atmosphere environment of the project is determined as Grade III.
|
Natural water replacement project of off-site drainage and around airport
|
The impact during construction period mainly includes vegetation damage, occupancy; the evaluation grade is Grade III.
|
After construction of project, the functional area belongs to Category II Standard area regulated by GB3096-2008. Its impact on acoustic environment is mainly reflected during construction period and the impact of noise during the construction period will disappear with the ending of construction period. Considering the degree of the affected people comprehensively, the evaluation for sound environment is determined as Grade III.
|
Rain discharge around the airport can be perfected through implementation of the project, thus to make positive benefits of the surrounding discharge and agricultural irrigation. Judging from HJ/T2.3-93, the evaluation grade of surface water environment is determined as Grade III.
|
The impact of the project on the atmosphere is mainly reflected in construction period. Pollutants are mainly the construction dusts, the type of generated atmosphere pollutant is simple and the affected area is limited. According to judgment requirement of guidelines, the impact evaluation of atmosphere environment of the project is determined as Grade III.
|
Reconstruction project of village road around airport
|
The area along the project road belongs to insensitive area of ecological environment without key environmental protection objects including natural reserves or cultural relics preservation, which is thus evaluated as Grade III.
|
There are no special sensitive points such as hospitals and sanatoriums within the scope at 200m from both sides along the road, and main environmental sensitive point is town residence area, which is thus evaluated as Grade III.
|
The project road does not cross surface water region, and the discharge quantity of sewage during construction period for road construction is small. Thus, the evaluation for surface is determined as Grade III.
|
The evaluation scope does not include Category I ambient air quality function area and the ambient quality of the main evaluation factor is not close to or beyond the standard for ambient quality. The project does not emit the special pollutants that are greatly harmful to human body health or ecological environment; the evaluation of ambient air of the project is Grade III.
|
110kV Maozao Line relocation and modification project of Sanqingshan Airport
|
The area long the line belongs to common area without key environmental protection objects including natural reserves or cultural relics preservation, which is thus evaluated as Grade III.
|
After operation of project, the generated main noise includes audible noise generated by brush discharge of conductor, armor clamp and insulator, which has small impact on the ambient environment; thus, the evaluation grade is Grade III.
|
The project only generates sewage in small quantity during construction period and the pollutant composition is simple; thus, make simple analysis.
|
The impact of the project on the atmosphere is mainly reflected in construction period. Pollutants are mainly the construction dusts, the type of generated atmosphere pollutant is simple and the affected area is limited. According to judgment requirement of guidelines, the impact evaluation of atmosphere environment of the project is determined as Grade III.
|
110kV Wangzao Line relocation and modification project of Sanqingshan Airport
|
The area long the line belongs to common area without key environmental protection objects including natural reserves or cultural relics preservation, which is thus evaluated as Grade III.
|
After operation of project, the generated main noise includes audible noise generated by brush discharge of conductor, armor clamp and insulator, which has small impact on the ambient environment; thus, the evaluation grade is Grade III.
|
The project only generates sewage in small quantity during construction period and the pollutant composition is simple; thus, make simple analysis.
|
The impact of the project on the atmosphere is mainly reflected in construction period. Pollutants are mainly the construction dusts, the type of generated atmosphere pollutant is simple and the affected area is limited. According to judgment requirement of guidelines, the impact evaluation of atmosphere environment of the project is determined as Grade III.
|
10kV line newly constructed project from Maojialing to Airport
|
The area long the line belongs to common area without key environmental protection objects including natural reserves or cultural relics preservation, which is thus evaluated as Grade III.
|
After operation of project, the generated main noise includes audible noise generated by brush discharge of conductor, armor clamp and insulator, which has small impact on the ambient environment; thus, the evaluation grade is Grade III.
|
The project only generates sewage in small quantity during construction period and the pollutant composition is simple; thus, make simple analysis.
|
The impact of the project on the atmosphere is mainly reflected in construction period. Pollutants are mainly the construction dusts, the type of generated atmosphere pollutant is simple and the affected area is limited. According to judgment requirement of guidelines, the impact evaluation of atmosphere environment of the project is determined as Grade III.
|
10kV line newly constructed project from Zaotou to Airport
|
The area long the line belongs to common area without key environmental protection objects including natural reserves or cultural relics preservation, which is thus evaluated as Grade III.
|
After operation of project, the generated main noise includes audible noise generated by brush discharge of conductor, armor clamp and insulator, which has small impact on the ambient environment; thus, the evaluation grade is Grade III.
|
The project only generates sewage in small quantity during construction period and the pollutant composition is simple; thus, make simple analysis.
|
The impact of the project on the atmosphere is mainly reflected in construction period. Pollutants are mainly the construction dusts, the type of generated atmosphere pollutant is simple and the affected area is limited. According to judgment requirement of guidelines, the impact evaluation of atmosphere environment of the project is determined as Grade III.
|