Environmental and social assessment



Download 1.32 Mb.
Page3/18
Date28.03.2018
Size1.32 Mb.
#43684
1   2   3   4   5   6   7   8   9   ...   18

The Proposed Project


The Ministry of Shipping (MoS) of GoB through the Bangladesh Inland Water Transport Authority (BIWTA) is preparing the Project to improve the IWT sector along with related infrastructure. BIWTA has approached the World Bank for financing the Project.

Location: The location map of the Project interventions is shown in Figure 1.

Proposed works: The main civil works that are proposed under the Project are as follows:



  • Component 1

    • dredging/river maintenance and provision of visual aids between Dhaka and Chittagong Corridor, including branches to Ashuganj, Narayanganj and Barisal;

    • construction and maintenance of six vessel storm shelters along the above routes; and

    • maintenance dredging of the main river ferry crossing routes (Chandpur and Shariatpur; Lakshmipor and Bhola; and Beduria and Laharhat).

  • Component 2

    • Construction of a new passenger terminal at Shasanghat near Dhaka; rehabilitation/upgradation of two existing passenger terminals at Narayanganj and Barisal; and reconstruction or new construction of an existing terminal at Chandpur

    • Construction of a new cargo terminal at Pangaon and rehabilitation/upgradation of an existing cargo terminal at Ashuganj;

    • Rehabilitation and upgradation of fourteen landing stations (launch ghats)

In addition, a third project Component includes various other activities aimed at institutional capacity development, continuous sector improvement, market development and policy framework development. Among these activities, a few may have environmental and social implications, namely: (i) minor civil works to retrofit existing buildings at the IWT Deck and Engine Personnel Training Centre (DEPTC) in Sonakanda, Narayanganj; (ii) various activities related to environmental and social sustainability of the IWT sector, including development of a water hyacinth to livestock feed and biogas pilot scheme, small-scale piloting of different river training technologies to minimize the need for continuous dredging, studies and pilot programs related to “greening” the vessel fleet, and development of a Gender Action Plan for IWT; and (iii) project preparation studies for a potential follow-on investment project on additional priority waterways, as well as studies related to climate change mitigation and adaptation opportunities in the IWT sector.

Implementation period: Dredging for improvement of IWT routes will be carried out through one or more performance based contracts over a period of seven years. The infrastructure facilities such as vessel shelters, river terminals and landing stations will be designed during the first year of implementation and the facilities will be built over a period of next two to three years. Other activities under Component 3 will likewise be designed/planned in the first years of the project and implemented in subsequent years.
    1. The Environmental and Social Assessment


Studies and documentation: This ESA executive summary has been prepared by the BIWTA and submitted to the World Bank for the Project. This report is prepared is based on field studies and data collected during August to December 2015 by various consultant teams hired by BIWTA and MoS. These studies have been documented in three volumes, (i) Environmental and Social Impact Assessment (ESIA) for Component 1, (ii) Environmental Management Framework (EMF) for the rest of the project (primarily Component 2 works), and (iii) Resettlement Policy Framework (RPF) for the overall project. All these documents are available under separate covers and have been disclosed on the BIWTA website, on the World Bank Infoshop, and have been disclosed locally in hard copy at locations accessible to project affected people.

Contents of the present document: After a description of the Bangladesh legal and administrative framework and the applicable World Bank policies in chapter 2, a project description is presented in chapter 3, followed by a discussion of project alternatives in chapter 4. A description of the physical, biological and socio-economic environment is given in chapter 5. Climate change aspects are discussed in Chapter 6. Potential adverse effects of the project are described in chapter 7 and potential cumulative impacts and concerns associated with other river related projects are presented in chapter 8. Possible mitigating measures to offset, reduce or compensate potential negative impacts of the project are included in the EMP that is summarized in chapter 9. Finally, chapter 10 provides an overview of all stakeholder consultations and activities for disclosure and access to the information.
    1. Composition of Study Team


ESA consultants: The ESA study has been carried out by BIWTA and the reports have been prepared by BIWTA and submitted to the World Bank for the Project. BIWTA has contracted Institute of Water Modeling (IWM) to prepare the ESIA for Component 1. MoS has hired two independent consultants Dr. Venkata Nukala (Environmental Specialist) and Dr. B.K.D. Raja (Social Specialist) to review and provide guidance on the work of the IWM team as they carry out their work, as well as to prepare EMF and RPF for Components 2 and 3 and this executive summary.

Environmental study team: The environmental team comprised of Zahirul Haque Khan (Team Leader), Dr. Sheikh Muhammad Abdur Rashid (River Ecologist), Mohammed Anisuzzaman Khan (Terrestrial Ecologist), Md. Mehedi Hasan Emon (Environmental Engineer), Rubayat Alam (River Hydrologist), Mohammad Abdus Salam Sikder (Coastal Hydrologist), Mohammad Ziaur Rahman (Sediment Dispersion Modeller), Md. Zahidul Islam (Agriculture Expert) Farhan Md. Zahir (Junior Water Resource Professional), Muhammad Ghulam Rasul (Junior Agriculture Professional), Afroza Mahzabeen Anannya (Junior Terrestrial Ecologist), Md. Shamsuddin (Junior River Ecologist), Md. Zahid Hasan Siddiquee (GIS Expert) and Syed Monowar Hussain (Survey Specialist/Navigation Specialist).

Social study team: The social team consisted of Khairul Matin (Sr. Socio-Development Specialist), Md. Rafiqul Islam (Media and Communications Specialist), G.M. Manzurul Mazid (Junior Socio-Development specialist), Sukhendra Narayon Chowdhury (Junior Socio- Development specialist) Md. Mustafizur Rahman ((Junior Socio-Development specialist) and M.Hamidul Islam (English-Bangla report translator).



Download 1.32 Mb.

Share with your friends:
1   2   3   4   5   6   7   8   9   ...   18




The database is protected by copyright ©ininet.org 2024
send message

    Main page