Retroreflective Sheeting (Type III and Type IV) From QPL


SP905 (03-31-08)
SECTION 00905 - REMOVAL AND REINSTALLATION OF EXISTING SIGNS

Comply with Section 00905 of the Standard Specifications.



SP910 (10-23-08) (This Section requires SP2110.)
SECTION 00910 - WOOD SIGN POSTS

Comply with Section 00910 of the Standard Specifications.



SP940 (03-31-08) (This Section may require SP937 and SP2910.)
SECTION 00940 - SIGNS
(Follow all instructions. If there are no instructions above a subsection, paragraph, sentence, or bullet, then include them in the project but make necessary modifications to only include project specific specifications. Delete specifications that do not apply to the project.)
Comply with Section 00940 of the Standard Specifications modified as follows:
(Use the following subsection .00 when directed by the Sign Designer. If used, include SP937.)
00940.00  Scope - Add the following to the end of this subsection:
Paint the backs of aluminum substrate signs, and all metal sign supports, according to Section 00937.
00940.46  Inspection - Replace the sentences that begin "Inspection will…" and "Testing for…" with the following sentence:
Inspection will be for conformance to the plans and Specifications, and for conformance to nighttime visibility.

SP950 (03-31-08)
SECTION 00950 - REMOVAL OF ELECTRICAL SYSTEMS
(Follow all instructions. If there are no instructions above a subsection, paragraph, sentence, or bullet, then include them in the project but make necessary modifications to only include project specific specifications. Delete specifications that do not apply to the project.)
Comply with Section 00950 of the Standard Specifications modified as follows:
(Use the following subsection .02 to define the electrical systems. Obtain information from the Signal Designer. Remove the "(s)" or the parentheses, whichever is applicable.)
00950.02  Definitions - Add the following after the electrical systems definition:
The electrical system(s) to be removed under this Contract includes:


  • Existing illumination service cabinet, meter base, and photoelectronic controlrelay at US 26/OR 47



(Use the following lead-in paragraph and subsection .42 when salvaging and stockpiling removed materials. Be sure that a "public interest finding letter" is on file before including this subsection. Contact Region electrician for Region number, phone number, and all information regarding equipment to be salvaged. List materials and stockpile locations.)
Add the following subsection:
00950.42  Salvaging and Stockpiling Materials - The following materials will remain the property of the Agency. Salvage the materials and stockpile them at the locations indicated. Contact Region _____ Electrical Crew at _____________ to confirm delivery 48 hours prior to delivery.
Materials Stockpile Locations

(Use the following subsection .90 when salvaging and stockpiling removed materials.)
00950.90  Payment - Add the following paragraph to the end of this subsection:
No separate or additional payment will be made for salvaging and stockpiling materials.

SP960 (06-26-08) (This Section requires SP440 and SP442.)
SECTION 00960 - COMMON PROVISIONS FOR ELECTRICAL SYSTEMS
(Follow all instructions. If there are no instructions above a subsection, paragraph, sentence, or bullet, then include them in the project but make necessary modifications to only include project specific specifications. Delete specifications that do not apply to the project.)

Comply with Section 00960 of the Standard Specifications modified as follows:


00960.41(f)  Disposition of Waste Materials - Replace this subsection with the following subsection:
00960.41(f)  Disposal of Materials - Dispose of all materials according to 00290.20.
00960.43 Foundations - Add the following subsection:
(c) Drilled Shaft Foundations - Construct drilled shafts according to Section 00963.
00960.44(a) General - Replace the first sentence with the following sentence:
Install junction boxes at the approximate locations shown, or, if not shown, no more than 500 feet apart.

SP962 (06-04-09) (This Section requires SP440.)
SECTION 00962 - METAL ILLUMINATION AND TRAFFIC SIGNAL SUPPORTS
(Follow all instructions. If there are no instructions above a subsection, paragraph, sentence, or bullet, then include them in the project but make necessary modifications to only include project specific specifications. Delete specifications that do not apply to the project.)
Comply with Section 00962 of the Standard Specifications modified as follows:
00962.10  Materials - Add the following to the end of the material list:

High Strength Fasteners 02560.20



00962.05(c)  Illumination Supports - Add the following to the end of this subsection:
The following standard illumination pole drawings are prequalified for use on the Project:
Ameron Pole Products Division Drg. OR7, Rev. C, 1/02

Drg. OR8, Rev. C, 1/02

Drg. OR9, Rev. E, 2/02
Union Metal Corp. Drg. 71049-B18 sh 1, R3, 2/99

Drg. 71049-B18 sh 2, R3, 2/99

Drg. 71049-B19 sh 1, R3, 2/99

Drg. 71049-B19 sh 2, R3, 2/99
Northwest Signal Supply Drg. NWS2285M, 9/00
Valmont Industries Inc. Drg. DB00386 sh 1, Rev. B, 3/12/03

Drg. DB00386 sh 2, Rev. B, 3/12/03

Drg. DB00386 sh 3, Rev. B, 3/12/03

Drg. DB00387 sh 1, Rev. B, 3/12/03

Drg. DB00387 sh 2, Rev. B, 3/12/03
00962.41(b)  Disposition of Waste Materials - Replace this subsection with the following subsection:
00962.41(b)  Disposal of Materials - Dispose of all materials according to 00290.20.

(Use the following lead-in paragraph and subsection .47 when temporary signal wood poles are required. Check with Designer.)
Add the following subsection:
00960.47  Wood Poles - Submit wood pole designs according to 00960.02 including proposed ANSI 05.1 wood pole Class, guy anchor and span wire designs, and pole setting depths.
SP963 (05-16-08) (This Section requires SP440.)
SECTION 00963 - SIGNAL SUPPORT DRILLED SHAFTS
(Follow all instructions. If there are no instructions above a subsection, paragraph, sentence, or bullet, then include them in the project but make necessary modifications to only include project specific specifications. Delete specifications that do not apply to the project.)
Comply with Section 00963 of the Standard Specifications modified as follows:
00963.10  Materials - Add the following paragraph to the end of this subsection:
Provide the commercial grade concrete mixture with a slump of 8 inches  1 1/2 inches.
00963.90  Payment - Replace this subsection with the following subsection:
00963.90  Payment – No separate or additional payment will be made for drilled shafts supporting camera poles, variable speed signs or flashing beacons. Payment will be included in payment for “Camera Poles and Foundations,” “Radar Poles and Foundations,”“Variable Speed Sign Installation,” or “Flashing Beacon Installation.”

SP965 (02-26-09) (This Section requires ITS Specifications*.)

(* ITS Specifications are available from the ITS Unit. The ITS specifications have not been reviewed or approved by the Specifications Unit, so be sure that there are no conflicts between this 00965 special provision and the ITS specification.)
SECTION 00965 - CAMERA POLES AND FOUNDATIONS
Section 00965, which is not a Standard Specification, is included in this Project by Special Provision.
Description
Section 00965, which is not a Standard Specification, is included in this Project by Special Provision.
00965.00  Scope - This work consists of furnishing and installing the structural portions of camera poles, radar poles and pole foundations.
00965.05  Design and Performance:
(a)  Design - Design poles and foundations according to the AASHTO "Standard Specifications for Structural Supports for Highway Signs, Luminaires and Traffic Signals 4th Edition" with all interim revisions. Design factors include:


  • Basic wind speed (3 second gust) 110 mph

  • Gust factor (G) 1.14

  • Importance factor (Ir) 1.0 (50 year recurrence interval)

  • Fatigue category II

Galloping and truck gust fatigue checks are not required.


Submit for review before fabrication, all engineered details and drawings which are not prepared by the State, but are required as shown. Submit stamped working drawings according to 00150.35.
Engineered drawings for the camera pole and mounting or radar pole and mounting shall show all material descriptions, dimensioning, member size, and connection details. Include stress analysis calculations documenting that the pole meets all applicable codes, standards, and requirements that are shown.
(b)  Performance Calculations - Design the poles to support the specified cameras, radar heads and accessories. Include all portions of the effective projected area of the complete lowering system and camera or radar equipment to be mounted on the pole along with the weight when designing the pole to meet the specified deflection performance criteria. The pole top deflection shall not exceed 1 inch in a 30 mph (non-gust) wind. The calculations shall include a pole, base plate, handhole, and anchor bolt analysis. The pole calculations shall be analyzed at the pole base, at 5 foot pole intervals/segments, hand hole locations, and at any other critical pole section. At each of these locations, provide the following information:


  • The pole's diameter, thickness, section modulus, moment of inertia, and cross sectional area.

  • The centroid, weight, projected area, drag coefficient, velocity pressure, and wind force of each pole segment.

  • The axial force, shear force, primary moment, total moment, axial stress, bending stress, allowable axial stress, allowable bending stress, and combined stress ratio (CSR).

  • The pole's angular and linear deflection.

The weight of a slip base pole and its attachments above the anchor plate shall be kept to a minimum and shall not exceed 1,000 pounds. Determine the total weight of the pole with all appurtenances attached to the pole and submit this with the design calculations.


Hand hole design requirements include:


  • Calculations for the moment of inertia, section modulus, and area at the hand hole centerline that show that these values are equal to or greater than the full pipe section properties without a hand hole.

  • Calculations that show that the net area of bar forming the hand hole frame is not less than 120% of pole cross section removed.

  • Calculations that show that the combined stress ratio (CSR) for the steel pole at the centerline elevation of the hand hole is less than or equal to 0.60.


Materials
00965.10  General - Furnish materials meeting the following requirements: