Implementation completion and results report


Annex 4. Bank Lending and Implementation Support/Supervision Processes



Download 1.43 Mb.
Page11/12
Date01.06.2018
Size1.43 Mb.
#52646
TypeReport
1   ...   4   5   6   7   8   9   10   11   12

Annex 4. Bank Lending and Implementation Support/Supervision Processes


(a) Task Team members

Names

Title

Unit

Lending

Usaid I. El-Hanbali

Consultant

GWA07

Jose Simas

Lead Water Resources Management Specialist




Ghada Younes

Senior Lawyer




Badr Kamel

Senior Procurement Specialist

GGO05

Hisham Waly

Practice Manager

GGO25

Hani El Sadani

Senior Water Resources Engineer




Narasimham Vijay

Jagannathan



Consultant

IEGSD

Ayat Soliman

Practice Manager

GSU11

Marwa El-Moslemany

Program Assistant




Supervision/ICR

Mohamed Yahia Ahmed Said Abd El Karim

Senior Financial Management Specialist

GGO23

Abdulhamid Azad

Lead Water Resources Management Specialist

GWA05

Nina Bhatt

Practice Manager

GSU03

Bekele Debele Negewo

Program Leader

EACCF

Ahmed Shawky M. Abdel Ghany

Senior Water Resources Specialist

GWA06

Hani Abdel-Kader El Sadani Salem

Senior Water Resources Engineer




Akram Abd El-Aziz Hussein El-Shorbagi

Senior Financial Management Specialist

GGO24

Wael Ahmed Elshabrawy

Financial Management Analyst

GGO23

Jamal Abdulla Abdulaziz

Senior Procurement Specialist




Badr Kamel

Senior Procurement Specialist




Maiada Mahmoud Abdel Fatt Kassem

Finance Officer

WFALA

Enas Shaaban Mahmoud

Program Assistant

MNCEG

Heba Yaken Aref Ahmed

Operations Analyst

MNSWA

Claudine Kader

Program Assistant

GWA05

Mohab Halouda

Senior Energy Specialist

GEE05

Michael Sandoz

Irrigation Consultant

GFA03

Knut Opsal

Lead Social Development Specialist

GSU07

Mikael Sehul Mengesha

Senior Procurement Specialist




Mohamed Mehani

Operations Engineer




Jose Simas

Lead Water Resources Management Specialist






(b) Staff Time and Cost

Stage of Project Cycle

Staff Time and Cost (Bank Budget Only)

No. of staff weeks

US$ Thousands (including travel and consultant costs)

Lending




FY02

6.57

45.81

FY03

6.07

29.74

FY04

29.47

125.92

FY05

60.43

248.36

FY06

18.73

83.79

Total:

121.27

533.62

Supervision/ICR







FY06

14.04

35.90

FY07

49.42

165.70

FY08

47.36

205.20

FY09

34.66

206.88

FY10

17.07

95.77

FY11

19.55

89.52

FY12

23.38

136.39

FY13

11.45

75.26

FY14

20.00

105.08

FY15

16.05

89.57

FY16

27.34

160.85

Total:

280.32

1,366.12



Annex 5. Beneficiary Survey Results


A beneficiary survey was not undertaken.

Annex 6. Stakeholder Workshop Report and Results


A stakeholder workshop was not undertaken.

Annex 7. Summary of Borrower’s ICR and/or Comments on Draft ICR


Background

1. The IIIMP was originally a seven-year multidonor funded project implemented under the Egyptian MWRI that aimed to enhance the management of irrigation and drainage and to increase the efficiency of irrigated agriculture water use and services in the Mahmoudia and Meet Yazid command areas in the Middle and West Delta. It addressed the water management issues in the two command areas in an integrated and participatory manner.

2. The overall objective was to improve water distribution, quantity, quality, equity, and timeliness and hence to increase agricultural production and alleviate poverty. Key elements to achieve these goals were the rehabilitation and improvement of the water management infrastructure. This was accompanied by institutional reform and user participation.

3. The IIIMP is regarded as a pioneer project where the policy reforms of integrated planning and development of water management service through better integration of the MWRI departments and other Government agencies are rolled out on a large scale.

4. The IIIMP implementation program was covered by five (5) components: (1) Improved and Integrated Water Management; (2) Improved On-Farm Water Management; (3) Institutional Development and Capacity Building; (4) Project Management, Coordination, and Integration; and (5) Environmental Mainstreaming.

5. The IIIMP involved a great number of sectors and departments within the MWRI as well as other ministries, in particular the MALR and Ministry of Electricity and Energy (MEE).

6. The framework for implementation, which was prepared during 2006, elaborated the IIIMP project concept as defined in the PAD and consisted of two documents:


  • A Project Implementation Plan

  • A Project Implementation Manual

7. The activities and plans described in these documents are fully in line with the IIIMP concept.

Partnership and Funding Arrangements

8. The main partnership arrangements included (a) a loan from IBRD for financing infrastructural improvements and equipment, (b) an additional loan from KfW for financing infrastructural improvements, (c) a grant from KfW for financing the TA services, (d) a grant from the Netherlands Government for the preparatory phase and institutional development and capacity-building activities relating to WUAs on the one hand and the MWRI on the other and the rehabilitation of district buildings, and (d) the GOE with a national counterpart fund budget.

9. The original project duration covered a period of approximately seven years from March 2007 to March 2014. The original closing date of the IBRD loan was March 31, 2014. However, because of the political unrest in Egypt (January 2011 and June 2013), which affected the implementation progress of the IIIMP in various ways, in March 2014, the IBRD extended its loan for another two (2) years up to March 31, 2016.

10. The original Netherlands Contribution Arrangement also covered a period of seven years, that is, from 2006 to December 2013. For similar reasons, this closing date was extended for three months up to March 31, 2014.

11. The original closing date for KfW funds (both Loan and Grant) was December 31, 2015; again for similar reason this was extended to December 31, 2016. At present, a second extension is being contemplated up to December 2017 to complete the ongoing activities in the KfW areas of the IIIMP.

Summary of Implemented Activities

12. The IIIMP is implemented through the various departments of the MWRI and the MALR (EALIP) and MEE and coordinated through a PMU and RCUs at regional level. The three RCUs (in each of the three governorates) assist the PMU in the coordination, monitoring, evaluation, and reporting. A Steering Committee has been established to provide strategic leadership for the timely and effective implementation of the IIIMP. At the governorate level, the project implementing sectors and partners are represented in a Regional Management Committee. The TA for the IIIMP includes (a) individual consultants hired directly by the PMU (and financed by the NDC) and (b) the main consultant Euroconsult Mott MacDonald in association with Mott MacDonald (United Kingdom), CES (Germany), S&H (Egypt), and CBI (Egypt), financed through the loan and grant from KfW.

13. Moreover, the PMU-IIIMP decided to make use of the MWRI’s in-house expertise in the various disciplines to establish a cost-effective mechanism for implementing the different IIIMP components through a number of task forces (TFs); the aim of these TFs was to facilitate the preparation, coordination, and implementation of the various IIIMP activities.

14. The actual activities are summarized in Table 7.1:



Table 7.1. Summary of Activities

Component

Subject

Summarized Description Activities

Component 1

Improvement and Integrated Water Management - investigations, design, and supervision

  • Main canals: 27 completed contracts, of which 13 on Mahmoudia main canal and 14 on Meet Yazid and Zawia main canals.

  • Branch canals: 36 completed contracts, 2 contracts ongoing, and 5 contracts planned.

  • Mesqa improvement works: Completed 85,347 feddans and expected 95,532 feddans.

  • Electricity medium and low voltage networks: Completed 3 contracts, ongoing 16 contracts, and planned 8 contracts.

  • Marwa development: 24,546 feddans completed and 9,525 feddans to be completed.

  • Rehabilitation of open drains: 10 contracts.

  • Rehabilitation and new constriction of SSD: 97,982 feddans under contract, of which 95,385 feddans was completed at IBRD closure date (this figure included 2,458 feddans completed of new SSD systems with a remainder of 1,342 feddans to be completed).

  • Activities for mesqa WUAs and irrigation improvement: Preparation of designs and tender documents for 95,532 feddans of mesqa improvement. This included support for farmer participation and developing the capacity of the WUA to manage and operate the new infrastructure.

  • Activities for SSD improvement have contributed to the preparation of SSD improvement in 97,982 feddans. To date, approximately 97,982 feddans are awarded to contractors and more than 95,385 feddans (112% of adjusted project target) of SSD was completed by March 2016.

  • Activities for preparation for installation, commissioning, and operation of ultrasonic flow measurement devices, together with the MWRI Telemetry Directorate, who were involved in USFM calibration and commissioning.

  • Activities for main system improvement: PMU and HEPS in the field investigation, preparation of tender documents and the procurement process, and construction supervision of contracts.

Component 2

Improved On-Farm Water Management

Water crop management adaptive research

  • Adaptive research for SRI: The PMU selected 80 feddans to pilot the rice intensification system in the Nekla command area, which was taken over by EWRMP project in January 2014.

  • Investigations for water management under controlled drainage: In total, 300 feddans of controlled drainage was piloted and farmers were trained in El Baradei area; this was also taken over by the EWRMP in January 2014.

On-farm demonstrations and farmer excursions: The W10 demonstration area (4,500 feddans) was implemented and used to demonstrate improved marwa development and LLL in improved mesqa areas. Moreover, farmer excursions were organized to show farmers to show the benefits of such improvements. Some 7,000 feddans of LLL was implemented; these LLL activities are continued under the FIMP.

Irrigation advisory support services strengthening: This included setting up a number of CF pilot areas (most advanced being the Nekla Pilot scheme) and training of concerned WUAs and BCWUAs (farmers) and the MWRI staff in preparing them for continuous flow irrigation as an alternative to rotational flow; this was also taken over by the EWRMP in January 2014.

Other activities included capacity building (training for trainers courses) for IAS and CDIAS extension staff in coordination with the MWRI Training Center.



Component 3

Institutional Development and Capacity Building

This component mainly covered the establishment and strengthening of IWRIGDs, IWMDs, DWBs, BCWUAs, and WUAs.

  • 308 BCWUAs have been established.

  • Nine DWBs have been established.

  • 2,070 WUAs have been established.

  • 1,162 mesqas handed over to the WUAs and these now have full operational responsibility.

  • Three IWRIGDs were established, activated, and strengthened in Beheira, Gharbia, and Kafr El Sheikh.

  • 21 IWMDs were to be established.

  • Total number of trained beneficiaries: 15,525 (13,684 males and 1,926 females).

  • Total number of the MWRI staff trained: 1,261 (1,699 males and 370 females).

Component 4

Project Management, Coordination, and Integration

Support to the PMU and RCUs: Under this component, support was given for the establishment and operation of the PMU and the three RCUs. Moreover, a number of TFs were established for coordination of activities. The following TFs were involved: TF for high-level project coordination; TF for project coordination; TF for procurement, documentation, and finance.

Support for setup and execution of M&E program: Monitoring of the project’s implementation progress and comparison with the overall work plan for the infrastructure works involved in the IIIMP; maintaining a database for monitoring the progress of contract implementation and interim payments; monitoring water levels which are automatically registered by the WMRI at several locations in the monitored canals and drains, as well as data such as cropping patterns, productivity, salinity, pump operations, and irrigation practices. These water levels were used for estimating performance indicators; periodic evaluations on WUO functioning are carried out by the PMU and progress reporting on procurement and construction works. The PMU relied on information provided by the IIS, EPADP, HEPS, and RSUs. The PMU, assisted by the TA consultant, regularly prepared a revised ‘Procurement Plan’ to facilitate and streamline monitoring of the procurement and implementation of construction works.

Impact, performance, and progress M&E: Two studies were prepared by contracting E-Leaf (formerly WaterWatch). These studies (covering the summer/winter season of 2008–2009 and the winter and summer season of 2013–2014) included remote sensing studies to analyze parameters related to water use and agricultural productivity, with the aim of assessing the impact of irrigation modernization interventions in the Nile Delta. These parameters are valuable indicators of the quantity, quality, and timeliness of water delivery.

The first study formed an important input for the Baseline Study, which was prepared in 2009–2010 for summer/winter 2008–2009.



The outcome of both studies represents an important element of the IIIMP M&E activities for both the baseline study and completion report.

Component 5

Environmental Mainstreaming

Public awareness and information campaigns: Prepared awareness building pamphlets on relevant environmental issues and the distribution thereof.

Performance-based environmental M&E: Activities included collection and analysis of environmental monitoring data. A water quality measuring program was implemented by the WMRI, which formed part of the monitoring activities, mentioned under Component 4

Technical studies and management plans - activities included:

  • An update on the ESMP in 2010.

  • A scoped Environmental Impact Assessment for dredging of main canals in 2011.

  • Social mitigation studies before tendering of some of the main canal improvement works.

  • Social studies concerned with illegal squatters on the banks of the Mahmoudia Canal in 2011.

  • An updated RAP in 2011.

  • An ESMP for Nishil and Sharaf drains in Gharbia and Beheira, respectively, in 2013 and the preparation of design and tender documents.

Institutional capacity building: Environmental training courses were conducted for district drainage engineers of the IWRIGDs and formed part of the overall capacity-building training program reported under Component 3.

General

WUO and the MWRI staff institutional training sessions

Throughout the implementation period of the IIIMP, the institutional strengthening and capacity-building activities included training courses, workshops, seminars, and some overseas study tours for IWM staff and involved the MWRI project staff.

Procurement of Goods and Services

From 2007 to 2016, procurement of goods and services were financed using IBRD and NL-CA funds. The goods were mostly procured using the International Competitive Bidding and National Competitive Bidding procedures and through a shopping procedure, if within the required budget ceiling.

Table 7.2. Summary of IIIMP Progress up to March 31, 2016

Item

Unit

Target at Completion

MTR

Total Estimated Cost in LE

Awarded up to March 31, 2016

Implemented up to March 31, 2016

% Implemented Compared to Target

Civil works

Main canal

LE

150,000,000

150,000,000

168,130,031

167,802,933

111

Branch canal

LE

81,200,000

81,200,000

159,978,649

146,189,505

180

Mesqa improvement

Feddan

85,000

777,955,000

95,532

85,347

100

Electrical networks

LE

142,000,000

142,000,000

139,282,000

104,727,000

74

Mara development

Feddan

30,000

58,750,000

34,071

24,546

82

SSD

Feddan

85,000

221,500,000

97,982

95,385

112

Open drains

Contract

8

28,400,000

10

10

125

Institutional activities

Established IWMDs

District

22

9,450,000

22

22

100

Established DWBs

DWB

11

600,000

9

9

82

Established BCWUA

BCWUA

308

2,345,000

308

308

100

Established WUAs

WUA

1,618

1,100,000

2,341

2,070

130

Handover WUAs

WUA

1,530



1,162

1,162

76

Note: IWMDs were established, but one IWMD was transferred from IWRIGD Gharbia to IWRIGD New Zifta.

Summary of Budget and Expenditures

15. Actual expenditures up to the end of March 2016 amounted to US$247.35 million, of which US$118.56 million for IBRD, US$60.93 million for KfW, US$10.76 million for NL-CA, and US$57.71 million for the GOE (see table 7.3).



Table 7.3. Actual Project Expenditures (US$, millions) up to

Project Component

Budget

PAD

Budget Revised

Actual Expenditures up to March 2016

IBRD

KfW

NL-CA

GOE

Total

1. Improved and Integrated Water Management

224.90




116.00

58.40

0.26

49.99

224.65

2. Improved On-Farm Water Management

4.60




0.21

0.00

0.12

0.25

0.58

3. Institutional Development and Capacity Building

14.30




1.13

0.00

5.69

2.35

9.17

4. Project Management, Coordination, and Integration

11.00




1.23

2.53

4.66

5.09

13.49

5. Environmental Mainstreaming

5.00




0.01

0.00

0.03

0.03

0.07

Subtotal

259.80




118.56

60.93

10.76

57.71

247.96

Price and physical contingencies

40.20




n.a.




Total

300.00




118.56

60.93

10.76

57.71

247.96

16. Note that the figures for expenditures are as mentioned in the FMR report, dated March 31, 2016. Moreover, for IBRD, we use actual exchange rate (before used US$1.00 equivalent to LE 5.50). For KfW, NL-CA, and GOE, an exchange rate of LE 5.50 to the U.S. dollar was used. By June 1, 2016, the total amount of the IBRD loan (US$120 million) was disbursed, as notified by the IBRD disbursement section (the IIIMP obtained a grace period up to July 31, 2016).

Cost Recovery

17. Law 213 of 1994 provides for recovery of mesqa improvement costs from the landowners benefiting from such investments.25 The costs of pump sets are repaid within 3 years, while repayment of the cost of civil works takes place over 20 years. Costs are repaid without interest. Taken together with the fact that there is usually a significant delay between the time when the investments are made and the start of repayments, this means that, particularly in the case of the civil works, that there is a significant element of subsidy.

18. Collection of the instalments is the responsibility of the LTA. After deduction of fees for the LTA and IIS, the amount collected is paid into a revolving fund which is intended to be used for further mesqa improvement.

19. Until 2013, arrangements to start the cost recovery were delayed while a decision was being awaited as to whether the costs of electrification (low-voltage networks), should also be included. During summer 2013, a formal decision was made by the MWRI in conjunction with the Ministry of Finance that the costs of the low-voltage networks should be taken into account for the cost recovery, with repayments to be made over 15 years.



Summary of Main Lessons Learned

General

  • Initial indications show that costs and irrigation time have decreased after the improvement of the mesqa and the establishment of WUAs.

  • Improved water flows have increased crop yields, particularly at the tail end of improved branch canals.

  • Increased women participation has been observed in some WUAs and BCWUAs.

  • Conflicts between farmers on the same mesqa have decreased after improvement works were completed.

  • The exposure to contaminated irrigation water supply has been reduced at the tail end of the system through the provision of mesqa pump stations.

  • Land saving because of buried feeder pipelines from the offtakes to mesqa pumping stations and buried feeder lines and hydrants when developing the marwas.

  • The increase in land value because of improved farm infrastructure and improved environmental conditions was not taken into account in the economic analysis model used.

Electrification of Mesqa Pumping Stations

25. The Electricity Distribution Companies (EDCs) are responsible for the development and O&M of electricity distribution and as such they are best placed to undertake the additional work rather than awarding yet more contracts to private and state enterprises.



Farmer Objections

26. The use of a more flexible, yet firm approach to farmer participation could reduce problems during later stages, though this may result in more fragmented construction sites. The farmers themselves have to accept that the opportunity to participate brings with it responsibilities to ensure that all the farmers with a stake in a mesqa are fully involved in the development process and that they all accept the mesqa layout and other conditionalities.



Continuous Flow

27. A key requisite for continuous flow is the ability to measure and regulate flows into the branch canals and at present only a limited number of flow measurement devices have been installed. The regulation of flows into branch canals, particularly during periods of low flow or high demand, has to be equitable and transparent so that farmers are able to check the flows into neighboring canals. Until such time as all the branch canals have a flow meter with visual display, this is not possible.



BCWUAs

28. There have been a number of projects to establish and build the capacity of BCWUAs and DWBs; however, neither of these bodies have any legal status under Law 213 of 1994, which amends the Irrigation and Drainage Law 12 of 1984. Given the necessary powers, BCWUAs would have an important role in any future plans to introduce Integrated Water Resources Management, whereby users have a greater stake in the management and O&M of the infrastructure.



Establishment, Strengthening, and Operating of WUOs

29. The overall manpower and technical staff within IAS and CDIAS involved in this work was underestimated, more so if this same staff was involved in participatory design activities and problem solving during construction.

30. The introduction of an IWM system requires a long-term effort well beyond the completion date of the project and its construction activities.

Monitoring and Evaluation

31. Establishment of a centralized management information system would considerably streamline activities and information flows. The management information system should contain data on contracts signed, implementation progress, and individual target objects (for example, main and branch canals, mesqas, marwas, WUAs).

32. Remote Sensing Analysis (RSA) can provide additional dimensions. Main contributions of RSA to results monitoring improvements in irrigation and drainage have been the high reliability when identifying main cropping pattern, the overall calculation of water consumption, and crop growth/biomass. The outcomes of RSA and field monitoring ideally support each other. Aligning seasonal RSA with field monitoring activities is considered essential.

33. In view of small average field sizes in the Egyptian Delta, the use of high-resolution images (<10 m) should be considered to reduce interference of different crops grown in adjacent fields. As high-resolution images are more costly, certain study areas could be carefully selected, for example, in line with field surveys being done.



Post-completion Support in General

34. The implementing agencies are all project oriented and once the works are complete, there is no support for the farmers in terms of specialist training, workshop, and spare parts; building the capacity of the WUA, IWMDs, and DWBs; operation and management of irrigation infrastructure; and so on. In theory, the MALR is charged with agricultural extension, but this tends to focus on crop and livestock production, not on the particular skills needed to operate an irrigation system efficiently. It would be relevant to reserve a special budget line within the MWRI Training Center overall annual budget allocation for training and strengthening of farmers (WUAs), IWMDs, and DWBs.



Main Conclusion and Recommendations

35. The IIIMP is widely considered as a pioneer project, where the policy reforms of integrated planning and development of water management service through better integration of the MWRI departments and other Government agencies are rolled out on a large scale.

36. Implementation of the IIIMP to date has been difficult because of complex conditions in the field, including the political upheavals during 2011 and 2012, which extended to the rural areas being served and the limited capacity of some local contractors; the combination of these factors caused delays in implementation, which could not be foreseen at the start-up of implementation and as a consequence also had their effect on the disbursement rate.

37. However, with the approved extension of the IBRD loan from March 2014 to March 2016, the IIIMP managed to use the completed IBRD loan of US$120 million and fulfilled most of the revised results indicators, which were amended during the MTR.

38. Long-term sustainability of the IIIMP, however, requires additional support, especially in the field of capacity building of beneficiaries, to ensure long-term sustainability. The IIIMP has created an unprecedented momentum and expectations within the Delta region and its local population. However, not all expectations have been met as yet. Nevertheless, the contribution in the field of institutional strengthening and capacity building within the IIIMP implementation program, particularly with regard to the WUOs, has been of primordial importance and remains important.

39. The MWRI foresees a continuation in the field of mesqa development in other parts of the Nile Delta and Upper Egypt, building on the experiences gained under the IIIMP.

40. With the experiences gained, however, the PMU would propose to have the existing Agricultural Cooperatives actively involved in the establishment of the WUAs instead of the IIS as they have a more intimate knowledge of the farmers’ organizational structures at the field level, whereas the IIS has limited staff available for such activities, particularly so when the IIS has to be involved at the same time in the designs and construction supervision.

41. In such a case, the MWRI could arrange for a protocol between the MWRI and these agricultural cooperatives.

42. Moreover, in any future endeavor we would recommend having a separate loan in parallel with the MEE to provide for electricity networks in the future areas of mesqa improvement without the direct inference from the MWRI, similar to the scenario of Assuit Barrage (where the loan for civil works is assigned to the MWRI and a separate loan is assigned to the MEE). If the pilot(s) of supplying solar energy for the mesqa pumping stations show that this is a feasible option, this could become an alternative energy source.




Download 1.43 Mb.

Share with your friends:
1   ...   4   5   6   7   8   9   10   11   12




The database is protected by copyright ©ininet.org 2024
send message

    Main page