.............................................................................
.............................................................................
Elsevier US
Job
code KIBChapter: Ch11-H7983 6-12-2006 9:22 p.m.
Page:378
Trimsize:7.25 in in
Fonts used Sabon & Frutiger
Margins:Top:36 pt
Gutter:66 pt
Font Size pt
Text
Width PCDepth:43 Lines
378
International
BusinessTo reduce the completion time of a project, we need to shorten a number of its activities. When we do this, however, we need to remember that. Not all the activities on the network can be shortened. The activities to be shortened must be on the critical path.
The process of shortening the completion time of a project is known as project crashing. The duration figures in the above example give the normal time for each activity of the project. Each activity
also has its crash time,
which is the least possible time it can take to complete that activity. Similarly,
the cost of an activity under normal circumstances is the activity’s normal cost and the cost of an activity under crash circumstances is its crash cost.
Now consider the following example involving the expansion of a small factory.
Example 3A small American manufacturer of leather products is expanding its factory.
The operations manager who is responsible for this project has identified a total often activities and has produced time and cost estimates for each of them. He has produced two different sets of estimated times and costs one for completing the project under normal circumstances and one for completing it under crash circumstances. This information is shown in the table below (activity durations are shown in weeks):
Activity
Normal Time
Crash Time
Normal Cost (Crash Cost ABC DEF G 4
3000 HI J 2
800 There is a bonus of $600 if the project duration can be reduced by one week, an extra bonus of $600 if the project duration can
be reduced by a second week, and another extra bonus of $600 if the project duration can be
.............................................................................
.............................................................................
Elsevier US
Job code KIB
Chapter: Ch11-H7983 6-12-2006 9:22 p.m.
Page:379
Trimsize:7.25 in in
Fonts used Sabon & Frutiger
Margins:Top:36 pt
Gutter:66 pt
Font Size pt
Text Width PC
Depth:43 Lines
International Operations Management
379
Share with your friends: