5.6 Insulation Contractor shall begin piping insulation of the line following testing and final touch up paint. Contractor shall insulate by test package as released upon completion of the testing and subsequent reinstatement. Contractor shall establish appropriate facilities at Site such as, insulation shop,
workshop, warehouse inclusive of any and all Equipment, manufacturing facilities, testing and/or
storage facilities, insulation cutting Equipment, field dispensing Equipment for foam, and special vehicles necessary to perform the Work. All facilities shall be air conditioned/ventilated where required to comply with the requirements of the Technical Information and Manufacturers recommendations/specifications.