Petroleum Development Oman L. L. C. Specification for Construction Activities on Oil, Gas and Utility Facilities Projects



Download 0.69 Mb.
View original pdf
Page19/25
Date08.01.2023
Size0.69 Mb.
#60314
1   ...   15   16   17   18   19   20   21   22   ...   25
SP-2050
5.2
Static Equipment
Contractor shall be responsible for the complete installation and alignment of Static Equipment (including packages) and bringing it to a state of mechanical completion in accordance with the Technical Information and in accordance with Company and Vendor supplied information, procedures and good working practices. Contractors scope of Work for Equipment installation shall include as minimum the following
 Checking Equipment holding down or fixing arrangement plan dimensions and elevations prior to installation of the Equipment, to ensure compliance with the foundation and anchor bolt plan dimensions and elevations and advising Company of any errors or discrepancies
 Lining, levelling, alignment, orientation and plumbing of Equipment in its final position
 Installation of Equipment, internals, ancillary Equipment and all separable pieces of Equipment supplied in a knockdown condition.
 Prior to final closing up (after flushing, the Equipment shall be internally inspected by contractor to ensure cleanliness, dryness and correct assembly of


Petroleum Development Oman LLC
Version: 2.0 Effective Oct. 2017 Page 24
Specification for Construction Activities on Oil, Gas and
Utility Facilities Projects
Version: 2.0 Effective Oct. The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED. internals, etc. The final closing up (boxing up) of Equipment shall be subject to company approval.
 Preventative maintenance of all Equipment as per Company and Equipment Vendors instructions which shall include positive blinding of all Equipment nozzles to prevent the ingress of water and foreign matter, until the issue of the Completion Certificate. Contractor shall supply all oils, greasepaint, inhibitors, sheet metal blinds and all other Materials necessary for the preventative maintenance. Contractor shall provide and implement a preventative maintenance schedule for all Equipment items.