Report of the Working Group on Petroleum & Natural Gas Sector for the XI plan


Demand Supply Gap for Petroleum Products



Download 1.87 Mb.
Page14/32
Date27.02.2018
Size1.87 Mb.
#41550
1   ...   10   11   12   13   14   15   16   17   ...   32

Demand Supply Gap for Petroleum Products


Demand of Petroleum Products

      1. The demand of petroleum products considered is as given by Sub-Group on demand estimation. The total demand for the XI and XII Plan period is as given below.

MMT

Case

2007-08

2008-09

2009-10

2010-11

2011-12

2016-17

Base

116.1

119.1

122.0

127.0

131.8

160.2

Upper

117.6

122.0

127.8

136.6

141.8

179.3

Product availability

      1. For estimating the petroleum product availability, the data obtained from various refineries have been taken into consideration. Product availability estimated (including non-refinery sources8) is as under:

Table 8.7: Petroleum Product availability during XI Plan MMT

Product

2007-08

2008-09

2009-10

2010-11

2011-12

LPG

9.1

9.7

9.3

11.0

12.8

Naphtha

15.0

14.8

15.0

17.5

18.8

MS

13.7

17.5

27.7

28.9

30.5

ATF

6.8

7.4

9.3

10.6

11.0

SKO

10.6

11.3

10.7

10.3

11.3

HSD

58.0

62.6

74.5

84.1

92.3

LDO

1.0

1.0

0.8

0.8

0.6

LOBS

0.8

0.8

0.8

1.1

1.1

FO/LSHS

14.8

15.6

15.6

10.9

9.5

Bitumen

3.7

3.9

4.0

4.0

4.4

Coke

4.1

5.4

8.3

11.0

12.8

Others

5.6

6.5

9.6

11.0

13.2

Total__143.3__156.4__185.6'>Total

143.3

156.4

185.6

201.1

218.3



      1. Projections indicate that domestic production of petroleum products would exceed the upper case demand of the XII Plan by end of XI plan itself by a large margin. By the end of XII Plan production of petroleum products is slated to increase to 286 MMT.

Surplus/ (Deficit)

      1. Based on the product availability and demand estimates as given above the product-wise surplus/ (deficit) situation has been estimated and given below.

Table 8.8: Petroleum Product surplus/(deficit) during XI Plan (MMT)

Base Case

Product

2007-08

2008-09

2009-10

2010-11

2011-12

LPG

(1.73)

(1.55)

(2.42)

(1.20)

(0.01)

Naphtha

4.61

5.28

4.52

6.33

7.23

MS

4.37

7.65

17.43

18.26

19.42

ATF

2.47

2.63

4.15

5.01

5.13

SKO

1.76

2.80

2.47

2.36

3.59

HSD

15.87

18.82

29.18

37.19

43.92

LDO

0.00

0.00

0.00

0.00

0.00

LOBS

(1.63)

(1.72)

(1.70)

(1.48)

(1.52)

FO/LSHS

1.17

1.63

2.76

(2.40)

(4.38)

Bitumen

(0.06)

(0.05)

(0.17)

(0.41)

(0.23)

Coke

(0.66)

0.67

3.59

5.79

7.11

Others

0.71

1.16

3.80

4.64

6.29

Total

26.88

37.32

63.60

74.08

86.54



Table 8.8: Petroleum Product surplus/(deficit) during XI Plan (MMT)

Upper Case

Product

2007-08

2008-09

2009-10

2010-11

2011-12

LPG

(1.73)

(1.55)

(2.42)

(1.20)

(0.01)

Naphtha

5.70

5.02

4.52

6.27

7.22

MS

3.67

7.96

17.23

17.79

18.93

ATF

2.45

2.17

3.32

3.96

3.76

SKO

1.18

1.90

1.28

0.91

1.90

HSD

15.71

18.80

28.75

36.11

42.56

LDO

0.00

0.00

0.00

0.00

0.00

LOBS

(1.63)

(1.72)

(1.70)

(1.48)

(1.52)

FO/LSHS

1.01

1.34

1.96

(3.35)

(5.48)

Bitumen

(0.10)

(0.13)

(0.29)

(0.58)

(0.45)

Coke

(0.66)

0.67

3.59

3.79

5.43

Others

0.16

(0.00)

1.56

2.24

4.19

Total

25.76

34.46

57.80

64.46

76.52



      1. While estimating surplus/deficit scenario it is assumed that MS would be sold throughout the country blended with 5 percent ethanol from 2007-08.

      2. The refineries need to maximize production of LPG, LOBS and bitumen to an extent, from the national standpoint. Further caution needs to be exercised while converting bottoms to higher end products as large deficits in industrial fuels is projected. The bottom upgradation plan needs to be realigned to local demand. Even globally, as noted elsewhere in the report, large deficit is predicted for FO and LSHS.

      3. In addition the refineries must consider the change in refinery gate price to trade parity for MS and HSD. The ratio of import parity and export parity will undergo a change every year depending upon the past experience. If ratio of exports increases then, domestic realization for MS and HSD will fall accordingly. Refinery projects require factoring the above conclusions.