Annex (4) Environmental Screening Form ( B)
Environmental Screening Form (B)
1. Projects Name: ____________________________________________________
2. Project's Type (health care, educational, water, environment, other utilities) _____________________________________________________________________
3. Brief description of the project (project's components including assisting services, scope of service, number of beneficiaries, number of workers … etc) _______________________________________________________________________________________________________________________________________________________________________________________________________________
4. Brief description of the project's location (nature of location: rocky or dusty, the previous usage of the location):
__________________________________________________________________________________________________________________________________________
5. Description of the surrounding area: for a circle of 50 meters radius from the drainage point, specially locations of environmental sensitivity (utilities, constructions, land usage, water sources (1 ) … etc).
(Sketch drawing of the of the project)
6. Environmental Impacts & Mitigation Measures * (Construction & Operation Phase)
Project's Phase
|
Parameter
|
Influencing Factor
|
Mitigation Measure
|
Institution Responsible for Execution
|
Design
|
|
|
|
|
|
|
|
|
|
|
|
|
Construction
|
|
|
|
|
|
|
|
|
Operation
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
* Example for design phase: Parameter: Water, influencing factor: Disposal of wastewater, mitigating measure: design proper wastewater treatment, Responsibility: Consultatant
7. Does the project need monitoring during its operation ? (in case there is a probability of polluting water resources, or soil or air) yes No
8. In case the answer is yes, mark the monitoring issues applicable to your project:
Monitoring water sources
Monitoring the performance of health care waste disposal
Monitoring the performance of sanitary drainage system
Monitoring the cleanness of the building's yard
Monitoring the planting of trees in the building's yard
Table for Environmental monitoring during project operation
Parameter
|
Indicator
|
Location
|
No. of samples
|
Intervals
|
Responsibility
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Example: Parameter: Water, Indicator: Nitrate, Location: Albaraka well, No of samples: 4, Interval: one year, Responsibility: SFD