Cases and Materials on Contracts



Download 0.6 Mb.
Page21/22
Date31.01.2017
Size0.6 Mb.
#13164
1   ...   14   15   16   17   18   19   20   21   22

 3. Remoteness




British Columbia Saw Mills Co. v Nettleship 1868


Note Case:

  • Cases where a party's negligence causes a remote damage are difficult

  • Discusses case from the early 1600s

    • Man is to be married to heiress

    • Horse needs a shoe on the way.

    • Blacksmith worked so unskillfully the horse was lame and the man was late

    • Heiress married another

      • Blacksmith was found liable for the loss of the marriage

 

  • Comment by F.E. Smith: even if the blacksmith knew about the wedding he couldn't be expected to apprehend that the bride would marry another due to lateness

 Hadley v Baxendale (1854)


Ratio:

  • Rule for damages in cases where breach of contract causes a remote damage:

    • Where two parties have made a contract which one of them has broken, the damages which the other party ought to receive in respect of such breach of contract should be such as:

      • First Prong - May fairly and reasonably be considered either arising naturally from such breach of contract itself; or,

      • Second Prong - Such as may reasonably be supposed to have been in the contemplation of both parties, at the time they made the contract, as the probable breach of it

        • If the special circumstances were communicated then the potential damages would have been considered.

Facts:

  • Plaintiff owns steam powered mill. The gear shaft broke.

  • Plaintiff had to send broken gear shaft to serve has model for replacement

  • Contracted with defendant to ship gear shaft

  • Delivery by defendants was delayed beyond a reasonable time

  • Plaintiff brought action against defendants for lost profit

  • Trial judge awarded damages, Defendant's appeal

Issue:

  • Can the plaintiff receive damages for lost profits caused by the defendant's delayed delivery

  • Party A contracts with B. B performs slowly, this causes a damage to A that was unknown to B.

Decision:

  • For Defendants, new trial ordered.

Reasons:

  • Proper rule for damages in cases like this:

    • Where two parties have made a contract which one of them has broken, the damages which the other party ought to receive in respect of such breach of contract should be such as:

      • May fairly and reasonably be considered either arising naturally from such breach of contract itself; or,

      • Such as may reasonably be supposed to have been in the contemplation of both parties, at the time they made the contract, as the probable breach of it

  • We're the special circumstances of the contract communicated from the outset?

    • In this case there are other reasons a mill may ship a broken gear shaft that in no way effects profits

    • The plaintiffs did not make it clear that their profits were dependant on receiving the gear shaft and so the defendants could not reasonably have been expected to know that the delay was causing lost profits



Horne v The Midland Railway Company(1873)


Ratio:

  • In calculating exceptional damages for a remote loss:

    • In order that the notice of special circumstances may have any effect, it must be given under such circumstances, as that an actual contract arises that obliges the defendant to bear the exceptional loss

Facts:

  • Plaintiffs had contract to supply shoes to a firm in London at 4s/pair

  • The shoes had to arrive on Feb. 3

  • When dropping shoes off at defendant's rail station they gave a note stating they were under contract to have them delivered by the 3rd

  • The shoes arrived on the 4th and were not accepted

  • Plaintiffs resold shoes at 2s 9d/pair

  • Defendants originally paid enough to cover the cost of resale

  • Plaintiffs further 267pounds for difference between contracted price and market price

Issue:

  • Does the note make the defendant's liable for the plaintiff's loss?

Decision:

  • For the defendant, the note did not form a contract that created liability

Reasons:

  • There has never been a case that affirmed that if notice is given the defendants will become liable for exceptional damages

  • "In order that the notice may have any effect, it must be given under such circumstances, as that an actual contract arises on the part of the defendant to bear the exceptional loss."

 Note Cases


Hydraulic Engineering Co. Ltd. v McHaffie (1878)

  • A person contemplates the performance and not the breach

    • Plaintiff doesn't enter into a second contract to pay damages

    • But, is liable for injuries that he is aware his default might cause

  • Court will not imply the note as an implied condition


Rivers v George White & Sons Co. (1919)

  • Shippers have no discretion to decline the second contract as they have already accepted the first

    • (modification without consideration)

 Kinghorne v The Montreal Telegraph (1859)

  • It makes no sense that a shipper should be liable for all potential loss that might arise from a late delivery

 

Victoria Laundry Ltd. v Newman Industries Ltd. (1949)


Ratio:

  • The following is not precedent. The SCC qualifies Hadley v Baxendale as the standard in Fidler

  • When dealing with loss of profit due to unreasonable delay follow these principles:

    1. In cases of breach of contract the aggrieved party is only entitled to recover such part of the loss actually resulting as was at the time of the contract reasonably foreseeable as liable to result from the breach

    2. What was at that time reasonably foreseeable depends on the knowledge then possessed by the parties, or at all events, by the party who later commits the breach

    3. For this purpose: Knowledge possessed is either i) imputed; or, ii) actual

      • Individuals are expected to know the ordinary course of things

      • If an individual has knowledge outside the ordinary that allows them to infer the damage that would be received by the plaintiffs then the damage is recovering

    4. The contract -breaker is liable is he, having considered the question of liability, would have reasonably concluded that the loss in question was liable to result.

    5. Liability does not require the contract-breaker to know the loss would necessarily result, it is enough that there was a "serious possibility" or "real danger" that a loss would result.

Facts:

  • Defendants advertised selling two boilers they owned

  • Plaintiffs, looking to expand their business, contracted for the purchase of the boilers

  • Contract was complete on Apr. 26th

  • Plaintiffs made it very clear they wanted the boiler ASAP

  • Plaintiffs had delays getting licensing for boiler: Defendants knew they wanted it as soon as possible

  • Plaintiffs went to pick up Boiler June 5th

    • Boiler had been damaged 4 days earlier by contractors of defendant

    • Plaintiff demanded the boiler be repaired

  • The repairs were complete Oct.28th

  • Delivery was taken Nov. 8th

  • Plaintiffs sue for lost profits

  • Trial judge did not reward loss of profits

  • Plaintiffs appeal

Issue:

  • Should the plaintiffs receive damages for lost profits due to a delay in shipping the boiler they contracted to purchase from a company

  • A contracted to by a Boiler from B. B knew A wanted the boiler for business. B caused the boiler to be delayed unreasonably.

Decision:

  • For Plaintiffs

 

Reasons:

  • Defendant counsel argues that under Hadley v Baxendale no damages for lost profits can be rewarded because no communication was given at the time of contract about the possible damage resulting in a breach

  • Court summarizes the law in these cases:

    1. In cases of breach of contract the aggrieved party is only entitled to recover such part of the loss actually resulting as was at the time of the contract reasonably foreseeable as liable to result from the breach

    2. What was at that time reasonably foreseeable depends on the knowledge then possessed by the parties, or at all events, by the party who later commits the breach

    3. For this purpose: Knowledge possessed is either i) imputed; or, ii) actual

      • Individuals are expected to know the ordinary course of things

      • If an individual has knowledge outside the ordinary that allows them to infer the damage that would be received by the plaintiffs then the damage is recovering

    4. The contract -breaker is liable is he, having considered the question of liability, would have reasonably concluded that the loss in question was liable to result.

    5. Liability does not require the contract-breaker to know the loss would necessarily result, it is enough that the loss would likely result.

 

  • Applying this:

    • Defendants knew the plaintiffs wanted the boiler for business

    • Defendants were not aware at the time of contracting of the plaintiffs contracts which they stood to lose and so they cannot be expected to pay for those losses

    • Plaintiffs can recover some losses of business 



Koufos v C. Czarnikow, Ltd. (The Heron II)


Ratio:

  • Modifies Victoria Laundry in that if a loss is sufficiently likely to result from a breach the contract-breacher will be liable for the damages

Facts:

  • Plaintiff chartered defendants vessel to move pick up 3000 tons of sugar in Constanza and carry it to Basrah or Jeddah

  • This should have taken 20 days

  • Deviations caused the trip to take 29 days

  • Defendant didn't know that plaintiff's wanted to sell sugar "promptly" but knew there was a sugar market in Basrah

  • Sugar was sold but the market price had gone done shortly before

    • Sold sugar for 31 pounds 2s. 9d. / ton

    • Could have sold for 32 pounds 10 s. 0d. / ton

  • Plaintiffs want the difference as damage for breach of contract

Issue:

  • Carrier deviated course and delayed shipment by 9 days. Market value of cargo went down. Can charter recover damage for difference in market value?

 

Decision:

For Plaintiff



Reasons:

  • Court acknowledges the use of Hadley v Baxendale and Victoria Laundry (Windsor) Ltd. v Newman Industries Ltd. And then applies these tests

    • Knowledge and intentions of parties:

      • Charterers:

        • Intended on selling sugar at basrah immediately after arrival

        • No evidence they had expected date of arrival

        • No evidence they were aware of rising or falling markets

      • Shipowner:

        • Knew nothing of the charterer's plan

 

  • Ought the shipowener have realised that the loss incurred due to breach of contract causing delay was not unlikely to result?

 

  • Court states that it is not unlikely knowledge for carrier's that prices in markets go up and down and that the breach of contract might cause the defendant's to lose profit.



Transfield Shipping Inc. v Mercator Shipping Inc. (The Achilleas)


Ratio:

  • In cases involving remote damages the court will interpret the contract to determine the liabilities which the parties may reasonably be expected to have assumed and paid for.

    • Is the loss the kind of loss that risk would be considered to be assumed for when entering into the contract

Facts:

  • Defendants had been chartering a boat (the Achilleas) from the plaintiffs for over a year

    • The latest date of delivery was set as May 2nd, 2004

  • Rates had gone up significantly for charters

  • Plaintiffs contracted with new charterer's to charter the vessel for 39,500/day; latest date for delivery May 8th, 2004

  • Defendants were unfortunately delayed, not due to their own negligence, and delivered the boat on May 11th

  • By this period rates had gone down

  • Plaintiff, renegotiated the daily rate for the new charterers down to $31,500/day in order to extend the date of delivery to May 11th

  • Plaintiffs sue for lost profit ($1,364,584.37)

Issue:

  • A charters vessel from B. A is late returning vessel to B. Delay causes B to lose next lucrative charter.

  • Is the rule that a party may recover losses which were foreseeable an external rule of law, imposed upon parties to every contract unless express contrary provisions, or is it a prima facie assumption that can be rebutted in certain contexts?

Decision:

 Reasons:



  • Defendant's argue they are only liable for the difference between the market rate and the charter rate and the market rate they were deprived by over those 9 days

  • Lots of academic works recently state that liability for damage is foudned upon the interpretation of the particular contract (it's type, form, context, intentions, etc.)

  • The original starting point for a remedy is to see what would put the plaintiff into the position he/she would be in had the contract been performed

    • Judge disagrees:

      • First determine "type" or "kind" of loss the plaintiff is seeking to be compensated for

        • Implied contractual duty; and,

        • Express contractual duty

          • The consequences of either of these duties for which the contracting party will be liable are those which the law regards as best giving effect to the express obligations assumes

            • Party will not be liable for risks which fall outside risk considerations that generally exist in contracts in a given market

  • Foreseeability will not always lead to damages:

    • A party may not be liable for foreseeable losses because they are not of the type or kind for which he can be treated as having assumed responsibility

    • How does one determine if a loss is of the same or different type?

      • "the only rational basis for the distinction is that it reflects what would have reasonably have been regarded by the contracting party as significant for the purposes of the risk he was undertaking

      • The question of whether a given type of loss is one for which a party assumed contractual responsibility involves the interpretation of the contract as a whole against its commercial background-> questions involving contractual interpretations are questions of law

 

  • In cases involving remote damages the court will interpret the contract to determine the liabilities which the parties may reasonably be expected to have assumed and paid for.

    • Is the loss the kind of loss that risk would be considered to be assumed for when entering into the contract 



Cornwall Gravel Co. Ltd. v Purolator Courier Ltd.


Class Notes:

  • Business gives job tender to a delivery man (agent of Purolator) and explicitly states that it must get to its location before 3 (so that it would be accepted for the bid)

  • Delivery man acknowledges this and states it will

  • It doesn’t

  • The delivery man in court admits that he knew what a tender was

  • The party doesn’t need to be able to predict the exact manner in which the breach occurs

    • The Types of damages that occurred had to be within the contemplation of the parties (Heron 2)

    • Or the type of damage must be expressly communicated


Download 0.6 Mb.

Share with your friends:
1   ...   14   15   16   17   18   19   20   21   22




The database is protected by copyright ©ininet.org 2024
send message

    Main page