TABLE OF CONTENTS1.0 INTRODUCTION............................................................................................................21.1 Purpose 1.2 Parsons EC General Fire Protection Philosophy.....................................................2
2.0 ABOUT FIRES AND FIRE PROTECTION......................................................................33.0 DESIGN GUIDE..............................................................................................................53.1 Getting Started 3.2 Estimating The Fire Water Governing Case 3.3
Fire Water Pump, Storage, And Piping Design..........................................................6
4.0 FIRE PREVENTION AND LOSS CONTROL..................................................................84.1 Prevention 4.2 Loss Control.............................................................................................................9
5.0 SPECIAL SITUATIONS..................................................................................................185.1 Buildings 5.2 Storage Tank Farms 5.3 LPG Storage Tanks 5.4 Offshore 5.5 Cold Climate..............................................................................................................21
Appendix 1 - References......................................................................................................22
Appendix 2 – Glossary..........................................................................................................24
Appendix 3 - Examples Of Ring Main Layout........................................................................26
Appendix 4 - Examples Of Fire Water Pump Systems..........................................................27
Appendix 5 - References For Fire Fighting Equipment.........................................................28
Appendix 6 - HDPE Pipe......................................................................................................29