A – General Details



Download 1.41 Mb.
Page3/6
Date28.05.2018
Size1.41 Mb.
#51567
1   2   3   4   5   6

Key dates

SET


Thu

26th May

Overnight Overhead Rig

 

Fri

27th May

 

Steelwork/Flat Construction

Sat

28th May

Set Specials/LEDs

Construction/Dressing

Sun

29th May

Rigging Cabling/Under Set Lights/Wires

Cut Traps/Dressing

Mon

30th May

FIRST REHEARSAL ON SET

Reh

Tue

31st May

 

Reh

Wed

1st June

Programming/Sound Rig

Reh & Light

Thu

2nd June

 Camera Rig

RX 1 & 2


RX Dates

RX

Date

RX 1 & 2

2nd June

RX 3 & 4

9th June

RX 5 & 6

16th June

BREAK

RX 7 & 8

30th June

RX 9 & 10

7th July

RX 11 & 12

14th July

RX 13 & 14

21st July

RX 15 & 16

28th July

RX 17 & 18

4th August

RX 19 & 20

5th August


STRIKE


Thu

4th August

 

RX 17 & 18

Fri

5th August

 

RX 19 & 20

Sat

6th August

Derig lights from set
Strike moving Lights Overhead

Remove Flats then Steel construction.
Load & Clear




D -Relevant Health & Safety Considerations; (e.g. Asbestos, Electricity, Stabilisation Method, Working at Height, Manual Handling, Chemicals, Noise, Dust, Services , requirements for Permits etc) [PCI Aide memoire provides further guidance]

Studio Turnaround Manager to brief the crew prior to commencing construction in studio; to discuss work program, introduce key production personnel and provide induction to site; which includes site rules along with fire and emergency rules. Construction crew to conduct a walk round inspection of the work area before commencing construction. Clear lines of communication will be established between Turnaround Manager, Construction Manager, Lighting Director and Crew Supervisor; the teams do work together frequently, so relationships are already established.
Main considerations, all of which are considered with suggested controls in appropriate Risk Assessments:

  • Crews constructing the set in studio, Designer Dressing the set and Lights being rigged simultaneously - Overhead Rig scheduled at a different time to set construction, crew to be aware of order of works and who to refer issues to. (Method Statement provided by Contractor to be followed by crew – available in Green Room)

  • Any technical crew new to Studio should complete a Studio induction before commencing any technical work.

  • Studio Loading Bay is a shared area (unlike the studio and tech store).  There may be other people using and working in the loading bay at the same time as Justin’s House team. The sharing of info about each other’s work and interactions needs to be via the Studio Turnaround Manager.

  • Set is built over several days – if crew is different ensure they are briefed.

  • Staff wishing to access the grid need to complete a grid induction; with no work on studio floor during overhead rigging.

  • Danger of tools being dropped from overhead works – care to be taken by crew to secure tools/lights overhead.

  • Working at Height – 2nd floor of set/Audience Rostra/Lighting Rig – be aware of controls from general RA.

  • Mobile Elevated Work Platform - Only persons with in date cards may operate MEWPS on premises (Studio RA).

  • High Staging, items supporting people - Assembly of individual mezzanines – be aware of Working at Heights controls in place.

  • Heavy Flown Scenery – be aware of controls/Method Statement from Contractor.

  • Electrical Equipment to be fitted and tested by a competent electrician - Gaffer to oversee electrical works and ensure crew is aware of any dangers.

  • Use of hazardous substances - Substances to be stored correctly as advised/Correct PSE to be used by Crew.

  • Welding/Steel Works – Contractor crew and Studio crew to be aware of manual handling controls and safe use of power tools.

  • Angles of Set may put strain on Joints.

  • Large, bulky, difficult to grasp items – manual handling - Crews to move large objects together, test weight before lifting. Forklift trucks available (RA provided by Studio).

  • Handrail at front of balcony is low - crews to be made aware – refer to Design RA for more information.

  • Trap Doors & Puppet Runs to be cut/established under stage floor - Ensure other crew are aware of members under the stage to reduce risk of injury (Planning for these to be cut on Sunday – position supervised by Stage Manager).

  • Final Site clearance & safety check to be done on completion of works. Set to be signed over to BBC – who will take responsibility for set once construction is complete. Studio Scenic Supervisor to check set each week using guidelines provided by Contractor.

  • All Risk Assessments are kept on production shared drive and there will be copies available in the Green Room – including – BBC Risk Assessment, Studio Risk Assessment, Lighting Risk Assessment, Design Risk Assessment, Construction Risk Assessment & Method Statement from Contractor.

  • No-one to enter the studio until Turnaround Manager has agreed it is safe to enter.

  • Minor alterations to the set during production – minor alterations will be conducted by competent person with consultation from Contractor if advised by Scenic Supervisor.

E – Project Administration

Security:


Entering Studio

You are asked to enter the studio block through the Stage Door entrance which is located on the Holiday Inn side of the building nearest to BBC StudioHouse.



**On the first day, please collect your passes from Studio reception.**

You will be issued with a studio studios access pass with photo ID or guest pass, depending on your working time in the Studio block.

Passes are coded and grant access to various parts of the building depending on your job requirements. You must wear your pass at all times when on studio premises.

Passes are critical to the safety of the building and therefore your safety too. If you lose or damage your pass you must notify Stage Door Reception immediately. Arrangements will be made for your pass to be cancelled and a new pass issued. Please note that Studio reserve the right to make a charge of £25 for lost or damaged passes.


Please Note: the Loading Bay at the rear of the Studio Block is for deliveries and is therefore not a pedestrian access point.

Stage Door is open between 8am and Midnight. Studio reception staff are on duty at Stage Door from 8am to 8pm. Outside of these hours a security guard is on duty.





Download 1.41 Mb.

Share with your friends:
1   2   3   4   5   6




The database is protected by copyright ©ininet.org 2024
send message

    Main page