6.10 Punishment mechanism


As the manager of the environmental management plan of the project, Shangrao Sanqingshan Co., Ltd has the obligation to restrict the behaviors of the contractors of the project. The contract agreement includes the article of environmental protection, see appendix, and clear the relevant articles of punitive measures for violating the article of environmental protection.

Principles for punitive measures are:

(1) When the contractor has the conditions of violating the article of environmental protection during the construction, the client has the right to put forward a written warning and supervise the contractor to correct promptly and take remedial action. Before the contractor takes corrective action and obtains the confirmation of relevant environmental protection administrative department and the contractor, the client has the right to refuse to pay for residual contract payment. The contractor shall take responsibility for all expenses caused by remedial measures because the contractor violates the articles of environmental protection.

(2) The contract also shall take responsibility for the liability for damage because the contractor violates the articles of environmental protection in the contract.


6.11 Estimation of environmental protection costs


The environmental impact mitigation measure costs, monitoring costs and other costs in the environment management plan of “Jiangxi Shangrao Sanqingshan Airport Project” are shown in Table 7-1.

Table 6-11-1 Estimation Table of Environmental Protection Costs

Items

Name of project expenses

Rough estimate value (10,000 Yuan)

Environmental protection investment during the period of construction and operation

Sewage treatment

Sewage treatment system (project investment)

485

912

Water reuse system (project investment)

175

Rain and sewage pipeline network (project investment)

220

Waste water, waste sedimentation pond, latrines during the construction period

2

Oil water separator

30

Solid waste

Garbage temporary storage station (project investment)

10

Ground water

Oil depot area, groundwater monitoring wells of downstream of the sewage treatment plant

4

Ecology

Vegetation and afforestation recovery in the airfield, terminal area (project investment)

670.89

Forest vegetation recovery costs (already included in forestry researching investment)

721

Bird prevention facilities

183

Water conservation measures costs (already included in the water conservation investment)

231.97

Protection of plants (camphor) transplanting costs

541.61

Drainage works investment in the airport

Broadening reinforcing downstream gully lines of the airport outfall

440

Rural roads reconstruction costs

Reconstructing the blocked rural roads due to the construction of the airport

510.6

Environmental monitoring costs

Construction period

1.3

Operation period

4.6

Personnel training costs

Training for contractors and environmental specialists in the construction sites

6

Training for the environmental supervision engineers

9

Training for Sanqingshan Airport Limited and its environmental managers

3

7. Public Consultation and Information Disclosure

7.1 Methods of public consultation and information disclosure


According to the requirements of nation and World Bank, there are two times of public consultation and two times of information disclosure for the Jiangxi Shangrao Sanqingshan airport. The main methods are to issue the project information to the public, particularly the affected people, in the regions with direct influence by this project, including the outline of environmental impact assessment, the first draft of the report of environmental impact assessment and environmental management plan, as well as the Environemntal Management Framework. After the public knows the situations, working group of environmental impact assessment visits the public, hold various public meetings, issue questionnaires to the public, collect their opinions, suggestions and requirements, and give feedback to them.