SSECTION 01040 - PLANTING



(Follow all instructions. If there are no instructions above a subsection, paragraph, sentence, or bullet, then include them in the project. The specifications may be modified to include project specific specifications, but all additions, deletions, or modifications must be sent to the ODOT Technical Resource and Senior Specifications Engineer for review and approval.)
(Use only one of the following lead-in paragraphs as instructed below.)
[ Use the following lead-in paragraph when NONE of the following subsections are included in the project special provisions. ]
Comply with Section 01040 of the Standard Specifications.
[ Use the following lead-in paragraph when ANY of the following subsections are included in the project special provisions. ]
Comply with Section 01040 of the Standard Specifications modified as follows:
(Use the following subsection .19(g) when a contract growing agreement is required.)
01040.19(g)  Contract Growing Plant Materials - Add the following sentence to the end of this subsection:
This project requires a contract growing agreement.
(Use the following subsection .20(e) when the allowable size of wood chip mulch is to be listed in the Special Provisions. Obtain the allowable size range from the Designer.)
01040.20(e)  Wood Chip Mulch - Add the following to the end of this subsection:
Provide wood chip mulch in the following size range:

(Use the following subsection .22 when pressure moisture stress sensors, timereleased water, or moisture retention chemicals are required. Delete what does not apply. Remove parentheses.)
01040.22  Water - Add the following sentence to the end of this subsection:
Provide a pressure moisture stress sensor device for this Project. (Provide timed-released water for this Project.) (Provide moisture retention chemicals for this Project.)
(Use the following subsection .49 to include minimum watering frequencies for trees and shrubs. Obtain information from the Designer. Delete what does not apply.)
01040.49  General Planting - Add the following to the end of this subsection:
The following watering frequencies are required:
Deciduous trees that are 1 1/2 inch and larger, water at a frequency of _______ .

Conifer trees that are over 4 feet tall, water at a frequency of ______ .

All shrubs, water at a frequency of _______ .
(Use the following subsection .77(d) when sod lawn is required. Obtain the schedule from the Designer.)
01040.77(d)  Sod Lawn - Add the following to the end of this subsection:
Provide sod lawn feeding, mowing, and general treatment as follows:

SP01050 (2015 Specifications: 10-15-15) (This Section requires

SP00440 & SP02190.)

SECTION 01050 - FENCES



(Follow all instructions. If there are no instructions above a subsection, paragraph, sentence, or bullet, then include them in the project. The specifications may be modified to include project specific specifications, but all additions, deletions, or modifications must be sent to the ODOT Technical Resource and Senior Specifications Engineer for review and approval.)
(Use the following paragraph when subsection 01050.43(c) is NOT included in the project.)

(Use the following lead-in paragraph when any subsection 01050.43(c)is included in the project.)
Comply with Section 01050 of the Standard Specifications modified as follows:
(Use the following subsection .43(c) on projects in Regions 4 and 5 as requested by the Designer.)
01050.43(c)  Intermediate End Posts - Add the following sentence to the end of this subsection:
Contrary to the details shown on the standard drawings, space intermediate end posts a maximum of 300 feet apart.
01050.90 Payment – Add the following pay item:
(e) Steel Picket Fence – Steel picket fence and gates will be paid for at the Contract unit price, per unit of measurement, for the following items:
Pay Item Unit of Measurement
(a) ____ Foot X ____ Inch Steel Picket Fence Single Gates, Each
In item (a) the width of the gate opening will be inserted in the first blank and the height will be inserted in the second blank.

SP01120 (2015 Specifications: 10-08-15) (This Section requires SP00440

when thrust blocks are required.)



SECTION 01120 - IRRIGATION SYSTEMS

(Follow all instructions. If there are no instructions above a subsection, paragraph, sentence, or bullet, then include them in the project. The specifications may be modified to include project specific specifications, but all additions, deletions, or modifications must be sent to the ODOT Technical Resource and Senior Specifications Engineer for review and approval.)


Comply with Section 01120 of the Standard Specifications modified as follows.
01120.00 Scope – Replace this subsection with the following:
This work consists of repairing existing irrigation systems, damaged by construction. Contractor is advised that irrigation piping and equipment may not be identified on plans and that plant growth may hide irrigation equipment. Where irrigation piping has been abandoned in place, cut pipe ends clean and cap.

SECTION 02001 - CONCRETE


Comply with Section 02001 of the Standard Specifications modified as follows:

02001.20(a)  Strength - Replace Table 020011 with the following Table 020011:
Table 02001-1

Concrete Strength and Water/Cementitious

Material (w/cm) Ratio

Type of

Concrete

Strength

(psi)

Maximum

w/cm Ratio

Structural

3300

0.50

3300

(Seal)


0.45

4000

0.48

4000

(Deck)


0.40

HPC4000

0.40

5000 and above

0.40 1

HPC5000

and above



0.40

Drilled Shaft

4000

0.48

Paving

4000

0.44

1 PPCM's with cast-in-place decks and no
entrained air may have w/cm as follows:

5000 psi - 0.48;  5500 psi - 0.44;  6000 psi and up - 0.42





02001.20(c)  Slump - Add the following paragraph to the end of this subsection:
For drilled shaft concrete, maintain a minimum slump of 6 inches throughout the drilled shaft placement, including temporary casing extraction.

02001.32(a)  Trial Batch - Add the following sentences to the end of the paragraph:
Notify the Engineer at least 48 hours before making each trial batch. The Engineer may witness the preparation and testing.
02001.32(b)  Plastic Concrete - Replace this subsection, except for the subsection number and title, with the following:
For each trial batch, test the temperature, slump, density, and air content and compute the w/cm ratio and yield according to the following test methods:
Test Test Method
Sampling Fresh Concrete WAQTC TM 2

Slump AASHTO T 119

Density AASHTO T 121

Yield AASHTO T 121

Air Content AASHTO T 152

Concrete Temperature AASHTO T 309

Molding Concrete Specimens AASHTO T 23 or R 39 1

WaterCement Ratio 2


1 Cast cylinders in singleuse plastic molds

2 Use ODOT's Field Operating Procedure for AASHTO T 121 in the MFTP
02001.32(d)  Length Change Tests - Replace this subsection, except for the subsection number and title, with the following:
For all HPC and Silica Fume Concrete (SFC) mix designs, make at least three specimens from the trial batch for length change testing. Test samples according to ASTM C 157. Sample prisms shall have a square, 4 by 4 inch crosssection. Wet cure the samples until they have reached an age of 28 days, including the period in the molds. Store and measure samples according to ASTM C 157, section 11.1.2. Report length change results at 28 days.
Test Test Method Acceptance Value

Length Change ASTM C 157 -0.045% max. at 28 days


02001.32(e)  Permeability Tests - Replace the paragraph that begins "Permeability tests are…" with the following:
Test Test Method Acceptance Value

Permeability AASHTO T 277 1,000 coulombs max. at 90 days


Permeability tests are not required when HPC and SFC mix designs contain cementitious material with 66 percent portland cement, 30 percent fly ash, and 4 percent silica fume.
02001.34  Current Mix Designs - Replace this entire subsection, including subsection .34(a) and .34(b), with the following subsection:
02001.34  Current Mix Designs - Mix designs that meet the requirements for the specified class of concrete and are currently being used or have been used within the past 12 months on any project, public or private may be submitted for review.
(a)  Length Change Tests - For all HPC and SFC mix designs make at least three specimens for length change testing. Test samples according to ASTM C 157. Wet cure the samples until they have reached an age of 28 days, including the period in the molds. Store and measure samples according to ASTM C 157, section 11.1.2. Report length change results at 28 days.
Test Test Method Acceptance Value

Length Change ASTM C 157 -0.045% max. at 28 days


(b)  Permeability Tests - For alternate HPC mix designs make at least three specimens for permeability testing. Prepare, cure, dry and test according to AASHTO T 277. Report permeability in coulombs at 90 days.
Test Test Method Acceptance Value

Permeability AASHTO T 277 1,000 coulombs max. at 90 days


Permeability tests are not required when HPC and SFC mix designs contain cementitious material with 66 percent portland cement, 30 percent fly ash, and 4 percent silica fume.

02001.35(h)  Plastic Concrete Tests - Add the following paragraph and bullets to the end of this subsection:
For drilled shaft concrete, report the following additional information:
The total time estimate from initial batching through drilled shaft placement, including haul time, placing concrete, and temporary casing extraction.

Initial slump test results and subsequent results at 15 minute intervals, verifying a minimum slump of 6 inches is maintained for the total time estimated for drilled shaft placement, including temporary casing extraction. Report data in a table or graph format.