Petroleum Development Oman LLC Version: 2.0 Effective Oct. 2017 Page
18 Specification for Construction Activities on Oil, Gas and Utility Facilities Projects Version: 2.0 Effective Oct. The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
3.12 D PDMS Construction Management Solution For large projects as per CP223, contractor is required to utilize AVEVA’s D PDMS Construction Management Solution (AVEVA ERM – Enterprise Resource Management and AVEVA NET (D) Player, or an equivalent D PDMS Construction Management
Solution as advised by Company, throughout the performance and execution of the Work. Using AVEVA‘s D PDMS Construction Management Solution it is intended to
Allow a visual representation of the construction sequence (AVEVA ERM and AVEVA NET D Player.
Enable development of Installation Work Packs (IWP’s) linked
to the construction schedule, materials and other resources to control and manage construction work scopes and to do this in the context of the D model (AVEVA ERM).
Enable review of the construction progress and status by utilizing a colour coded progressing system interfacing with the D PDMS model, along with actual construction progress reporting against
installation work packs (AVEVA ERM and AVEVA NET (D) Player.