Published by department of transportation



Download 6.74 Mb.
Page102/288
Date08.01.2017
Size6.74 Mb.
#7448
1   ...   98   99   100   101   102   103   104   105   ...   288

28-2.03 CONSTRUCTION

28-2.03A General


Do not allow traffic or equipment on the LCB for at least 72 hours after the 1st application of the curing compound and completion of contraction joints. Limit the traffic and equipment on the LCB to that required for placing additional layers of LCB or paving.

28-2.03B Subgrade


Areas of the subgrade lower than the grade established by the Engineer must be filled with LCB.

28-2.03C Proportioning, Mixing, and Transporting


Proportion LCB under section 90-1.02F except the aggregate does not have to be separated into sizes.

Mix and transport LCB under section 90-1.02G except the 5th and 7th paragraphs in section 90-1.02G(6) do not apply.


28-2.03D Placing


Do not mix or place LCB if the atmospheric temperature is below 35 degrees F. Do not place LCB on frozen ground.

Unless otherwise described, construct LCB in minimum widths of 12 feet separated by construction joints. For LCB constructed monolithically in widths greater than 26 feet, construct a longitudinal contraction joint offset no more than 3 feet from the centerline of the width being constructed.

If concrete pavement will be placed on LCB, construct longitudinal construction and longitudinal contraction joints in the LCB to provide at least 1 foot of horizontal clearance from planned longitudinal construction and longitudinal contraction joints in the concrete pavement.

Construct transverse contraction joints in intervals that result in LCB areas where the lengths and widths are within 20 percent of each other. Measure the widths from any longitudinal construction or longitudinal contraction joints.

The Engineer waives the requirement for transverse contraction joints if you:

1. Submitted a notice under 28-2.01C(1)

2. Successfully field qualified LCB for 3-day compressive strength testing under section 28-2.02A.

3. Submit QC test results for 3-day compressive strength under section 28-2.01D(4).



28-2.03E Finishing


For LCB to be paved with HMA, before the curing operation texture the LCB finished surface by dragging either a broom, burlap, or a spring steel tine device. If using a spring steel tine device, the device must produce a scored surface with scores parallel or transverse to the pavement centerline. Texture at a time and in a manner that produces the coarsest texture for the method used.

For LCB to be paved with HMA, the finished surface must not vary more than 0.05 foot from the grade established by the Engineer.

For LCB to be paved with concrete pavement, do not texture LCB. Before applying curing compound, finish LCB to a smooth surface free from mortar ridges and other projections.

For LCB to be paved with concrete pavement, the finished surface must not be above the grade, or more than 0.05 foot below the grade established by the Engineer.

The finished surface must be free from porous areas.

28-2.03F Curing


After finishing LCB, cure LCB with pigmented curing compound under section 90-1.03B(3) and 40-1.03I except for LCB to be paved with concrete pavement, comply with section 36-2. Apply curing compound to the area to be paved with concrete pavement:

1. In 2 separate applications

2. Before the atmospheric temperature falls below 40 degrees F

3. At a rate of 1 gal/150 sq ft for the first application

4. At a rate of 1 gal/200 sq ft for the second application
Within 4 days after the first application, clean the surface and apply the second application.

Immediately repair damage to the curing compound or LCB.


28-2.03G Surfaces Not Within Tolerance


For LCB not to be paved with concrete pavement, remove the base where the surface is higher than 0.05 foot above the grade established by the Engineer and replace it with LCB.

For LCB to be paved with concrete pavement, remove the base where the surface is higher than the grade established by the Engineer and replace it with LCB. If authorized, grind the surface with either a diamond or carborundum blade to within tolerance. After grinding LCB to be paved with concrete pavement and after all free water has left the surface, clean foreign material and grinding residue from the surface. Apply curing compound to the ground area at a rate of approximately 1 gal/150 sq ft.

Where the surface of the LCB is lower than 0.05 foot from the grade established by the Engineer, remove the base and replace it with LCB or, if authorized, fill low areas according to the pavement material as follows:

1. For HMA pavement, fill low areas with HMA that complies with the specifications for the lowest layer of pavement. Do not fill low areas concurrently with the paving operation.

2. For concrete pavement, fill low areas with pavement concrete concurrent with the paving operation.

28-2.04 PAYMENT


The payment quantity for lean concrete base does not include lean concrete base used to fill low areas of subgrade

28-3 RAPID STRENGTH CONCRETE BASE

28-3.01 GENERAL

28-3.01A Summary


Section 28-3 includes specifications for constructing rapid strength concrete base.

28-3.01B Definitions


final set time: Elapsed time after the initial contact of the cement and water required for the mortar sieved from the concrete to reach a penetration resistance of 4,000 psi determined under ASTM C403.

early age: Any age less than 10 times the RSC base final set time.

opening age: Age at which the RSC base achieves the specified strength for opening to traffic and construction traffic.

28-3.01C Submittals

28-3.01C(1) General


At least 10 days before placing RSC base, submit a mix design that includes:

1. Opening age

2. Proposed aggregate gradation

3. Proportions of hydraulic cement and aggregate

4. Types and amounts of chemical admixtures

5. Maximum time allowed between batching and placing

6. Final set time

7. Any special instructions or conditions such as water temperature requirements



28-3.01C(2) Quality Assurance Submittals


At least 45 days before placing RSC base, submit (1) a sample of cement from each proposed lot and (2) samples of proposed admixtures in the quantities ordered.

During RSC base activities, submit uniformity reports for hydraulic cement at least once every 30 days to METS, Attention: Cement Laboratory. Uniformity reports must comply with ASTM C917, except testing age and water content may be modified to suit the particular material.


28-3.01C(3) Quality Control Plan


Reserved

28-3.01D Quality Assurance

28-3.01D(1) General


At the preconstruction meeting be prepared to discuss the project specifications and methods of performing each item of work. Items discussed must include the processes for:

1. Production

2. Transportation

3. Placement

4. QC plan, if specified in the special provisions

5. Contingency plan

6. QC sampling and testing

7. Acceptance criteria


Beams for modulus of rupture testing must be fabricated and tested under California Test 524. The beams may be fabricated using an internal vibrator under ASTM C31. For each test, 3 beam must be fabricated and the test results averaged. No single test represents more than that day's production or 130 cu yd, whichever is less.

For early age testing, beams must be cured so the monitored temperatures in the beams and the test strip are always within 5 degrees F. The internal temperatures of the RSC base and early age beams must be monitored and recorded at intervals of at least 5 minutes. Thermocouples or thermistors connected to strip-chart recorders or digital data loggers must be installed to monitor the temperatures. Temperature recording devices must be accurate to within ±2 degrees F. Until early age testing is completed, internal temperatures must be measured at 1 inch from the top, 1 inch from the bottom, and no closer than 3 inches from any edge.

For other age testing, beams must be cured under California Test 524 except beams must be placed into sand at a time that is the earlier of either from 5 to 10 times the final set time, or 24 hours.

28-3.01D(2) Preconstruction Meeting


Reserved

28-3.01D(3) Test Strip


Reserved

28-3.01D(4) Quality Control

28-3.01D(4)(a) General

Reserved
28-3.01D(4)(b) Quality Control Manager

Reserved
28-3.01D(4)(c) Quality Control Testing

During the placement of RSC base, fabricate beams and test for the modulus of rupture:

1. At opening age

2. At 7 days after placing the first 30 cu yd

3. At least once every 130 cu yd

4. Within the final truckload
Opening age tests must be performed in the presence of the Engineer.

RSC base must have an opening age modulus of rupture of not less than 400 psi and a 7-day modulus of rupture of not less than 600 psi.


28-3.01D(5) Department Acceptance


The Department accepts RSC base based on compliance with the requirements shown in the following table:

RSC Base Requirements for Acceptance

Quality characteristic

Test method

Requirement

Modulus of rupture (min, psi at 7 days)

California Test 524

600

The Engineer adjust payment for RSC base for the 7-day modulus of rupture as follows:

1. Payment for a base with a modulus of rupture of 600 psi or greater is not adjusted.

2. Payment for a base with a modulus of rupture of less than 600 and greater than or equal to 550 psi is reduced by 5 percent.

3. Payment for a base with a modulus of rupture of less than 550 and greater than or equal to 500 psi is reduced by 10 percent.

4. Payment for a base with a modulus of rupture of less than 500 psi is not adjusted and no payment is made. Remove and replace this base.



Download 6.74 Mb.

Share with your friends:
1   ...   98   99   100   101   102   103   104   105   ...   288




The database is protected by copyright ©ininet.org 2024
send message

    Main page