Question: What should be first attempted if compliant fuel is unavailable?



Download 36.5 Kb.
Page12/13
Date28.04.2024
Size36.5 Kb.
#64120
1   ...   5   6   7   8   9   10   11   12   13
imo2020
Question:
Which of the following will PSC expect to see when inspecting bunker delivery notes(BDNs)? Choose all that apply. (Ref 30th September 2019 technical circular no.123 rev.1)
Number of correct alternatives: 3

Question:
What additional information is required on a Bunker Delivery Note (BDN) for fuel to be used with a scrubber vessel? ( Ref S.I 20a 6.3)
Number of correct alternatives: 1

  • Lubricity of bunker.

  • It has to explicitly state the fuel is to be used in conjunction with a scrubber as per MARPOL Annex VI Reg 14.1

  • No extra information is needed.

  • Pour point of bunker. .

What is a CoQ? (certificate of quality)


Number of correct alternatives: 1

  • A new name for a bunker delivery note

  • A certificate from the supplier sent to the vessel in advance of bunkering detailing the key characteristics of the fuel.

  • A certificate that bunker fuel has been proven compliant after being sent for analysis

  • A certificate Port authorities can issue to a vessel if it has a good record of IMO fuel compliance

Can bunkered fuel be used before it has been tested? (Ref S.I 20 27)
Number of correct alternatives: 1

  • No

  • Yes, no need for it to be tested as long as the Chief Engineer as signed and agreed all the bunkering paperwork.

  • Not without express permission from the office

  • The decision will be made by the port state authority based on the reputation of the bunker supplier

When changing between fuel batches with different viscosities, what is the maximum acceptable rate of temperature change? (Ref PowerPoint)


Number of correct alternatives: 1

  • 2ºc/min

  • 12ºc/min

  • 2ºc/hour

  • 20ºc/min

What quantity of non compliant fuel should be bunkered if FONAR procedures are being followed? (Ref PowerPoint)


Number of correct alternatives: 1

  • you can never accept non compliant fuel

  • The minimum required to get the vessel to the next reasonable source of compliant fuel

  • 1/32 of the Vessel's maximum fuel capacity

  • completely fill one tank only

What should the vessel do in areas where wash water discharge is not permitted? (Ref S.I 20b 7.2)


Number of correct alternatives: 1

What is the permittable difference in PH between the ship's inlet and overboard discharge if the vessel is manoeuvring or in transit? (MEPC 68/21 Annex 1 10.1.2)
Number of correct alternatives: 1

  • 2pH units

  • 1 pH unit

  • pH can be more basic by 5 pH units but not more acidic than 6.5

  • There is no difference

Who is responsible for updating and implementing the SIP on board?


Number of correct alternatives: 1

  • Master

Master and Chief Engineer

  • Chief Engineer

  • Chief Officer



Download 36.5 Kb.