Pacific Gas and Electric Company
Waiver of “Significant Transmission Project” Status
Table 1 and 2 update the planned transmission and generation projects, respectively, in PG&E service area that were presented in PG&E’s 2012, 2013, 2014, and 2015 Annual Progress Report. These projects were granted the waiver of “Significant Transmission Project” status for the purpose of Project Coordination Review Process.
Table 3 and 4 list the planned transmission and generation projects, respectively, in PG&E service area requesting waiver of “Significant Transmission Project” status. The purposes of these projects are for serving local load, to enhance or maintain local reliability, and/or to reduce local capacity requirements. These projects are not expected to have significant impacts on the operation of the Western Interconnected System. PG&E requests waivers of the “Significant Transmission Project” status for the purpose of Project Coordination Review Process.
Table 1
Planned Transmission Projects
Waiver of “Significant Transmission Project” Status Granted in 2012, 2013, 2014, 2015 and 20161
PROJECT NAME
|
PROJECT DESCRIPTION
|
DATE IN SERVICE
|
Moraga Transformer No. 2 Capacity Increase
|
Replace Transformer number 2, 230/115 kV at Moraga Substation with a 420 MVA rated unit.
|
In Service
|
Contra Costa – Moraga 230 kV Reconductoring
|
Reconductor the Contra Costa - Moraga 230 kV DCTL with larger capacity conductors.
|
In Service
|
Weber 230/60 kV Transformer Nos. 2 and 2A Replacement
|
Replace Weber 230/60 kV Transformer Nos. 2 and 2a with a new transformer rated at least 300 MVA with LTC and associated equipment
|
In Service
|
Los Banos-4C779 #1 230kV Line Reconductoring Project
|
Reconductor 4.5 miles of the Los Banos - Panoche 230 kV No. 1 Line with a higher capacity conductor
|
In Service
|
Embarcadero-Potrero 230 kV Project
|
Construct a new 230 kV underground cable to connect Embarcadero and Potrero substations.
|
In Service
|
Midway Fault Duty Mitigation Project
|
Install reactors at 230 kV side of Midway transformer banks 11, 12 and 13.
|
Apr-17
|
Contra Costa sub 230kV Switch Replacement
|
Replace 230 kV Switch No. 239 at Contra Costa Substation that currently limits the Contra Costa PP-Contra Costa Sub 230 kV Line to 1600 Amps. Any other limiting element will be replaced as well.
|
Dec-17
|
Warnerville-Wilson 230 kV Series Reactor
|
Install a 230 kV multi-step Reactor totaling 50.5 ohms, and associated equipment at Wilson Substation, on the Warnerville-Wilson 230 kV line
|
Dec-17
|
PROJECT NAME
|
PROJECT DESCRIPTION
|
DATE IN SERVICE
|
Gregg-Herndon #2 230 kV Line Circuit Breaker
|
Replace limiting terminal equipment on the Herndon-Gregg #2 230 kV Line at Herndon substation.
|
Mar-18
|
Ashlan-Gregg and Ashlan-Herndon 230 kV Reconductor
|
Reconductor limiting sections of Ashlan-Gregg and Ashlan-Herndon 230 kV sections with higher rated conductors.
|
May-18
|
Glenn 230/60 kV Transformer No. 1 Replacement
|
Replace the existing 230/60 kV Transformer No. 1 and regulator at Glenn with a new 3-phase, 230/60 kV with a Load Tap Changer.
|
Dec-18
|
Wheeler Ridge Voltage Support
|
Install three 75 MVAR steps of mechanically switched capacitors on the Wheeler Ridge 230 kV bus, expand the 230 kV bus as necessary reconductor 0.5 miles of the Wheeler Ridge-Lakeview 70 kV line and transfer Copus from the Old River-Copus 70 kV line to the Wheeler Ridge-Lakeview 70 kV line.
|
Mar-19
|
Kearney-Herndon 230 kV Line Reconductor
|
Reconductor 10 miles of the Kearney - Herndon 230 kV Line
|
Mar-19
|
Morro Bay 230/115 kV Transformer
|
Install an additional 230/115 kV transformer at Morro Bay Substation rated for 200 MVA or higher.
|
Apr-19
|
Borden 230 kV Voltage Support
|
This project proposes to loop the Wilson-Gregg 230 kV Line into Borden Substation (Borden) and install 200 MVARs of mechanically switched capacitors on the Borden 230 kV bus.
|
May-19
|
Estrella Substation
|
Construct a new Estrella 230/70 kV substation, with Breaker and a Half (BAAH) bus configuration , approximately 5 miles east of the existing Paso Robles Substation. Install one 45 MVA distribution 230/12 kV, 2 feeder breakers and associated outlets
|
May-19
|
Diablo Canyon Voltage Support Project
|
Install a +150/-75 MVAR Reactive support device at Diablo Canyon 230 kV Substation
|
Jul-19
|
Eight Mile - Lodi Re-conductoring Economic Project
|
Reconductor 2.3 miles of the Lodi - Eight Mile 230 kV Line with higher capacity conductors.
|
Sep-19
|
Kern PP 230 kV Area Reinforcement Project
|
• Convert Kern PP 230 kV double bus single breaker arrangement to breaker and a half
• Replace limiting equipment on Kern PP 230/115 kV transformer No. 4 as necessary to achieve full transformer rating
Install a 230/115 kV Transformer Special Protection Scheme at Kern 115 kV to mitigate overloads of Kern PP Transformer Nos. 3, 4, and 5
|
Mar-20
|
Monta Vista 230 kV Bus Upgrade
|
Install bus-sectionalizing and bus-parallel breakers on the Monta Vista 230 kV bus
|
Apr-20
|
Tulucay 230/60 kV Transformer No.1 Capacity Increase
|
This project proposes to replace Tulucay Circuit Breaker No. 62 and all of its associated switches with a circuit breaker rated at 2000 Amps or higher. Any other associated terminal equipment will also be replaced as necessary
|
Apr-20
|
PROJECT NAME
|
PROJECT DESCRIPTION
|
DATE IN SERVICE
|
Wheeler Ridge Junction Substation
|
Construct a new 230/115 kV Substation with Breaker and a Half at Wheeler Ridge Junction, Convert 15.5 miles of the Wheeler Ridge – Lamont 115 kV Line to 230 kV
|
May-20
|
Midway-Kern PP 230 kV #2 Line Project
|
Reconductor the Midway-Kern #1 230 kV Line, split it to Midway-Kern #1 and #2 230kV Lines, remove crosstie connections to split the Midway-Kern #1 Line into two circuits, reconductor the Bakersfield #1 and #2 230 kV Taps, loop Bakersfield 230 kV substation, remove Stockdale 230 kV Tap #1 and #2 from the Midway-Kern lines and relocate to Kern PP 230 kV bus
|
Jul-20
|
Moraga - Castro Valley 230 kV Line Capacity Increase Project
|
Upgrade the limiting substation equipment (jumper conductors and wave traps) at Moraga and Castro Valley substations
|
Mar-21
|
Morgan Hill Area Reinforcement Project
|
Construct new 230/115 kV Spring Substation in Morgan Hill, with connections into the Metcalf-Moss Landing No. 2 230 kV Line and the Morgan Hill-Llagas 115 kV Line.
|
May-21
|
Rio Oso 230/115 kV Transformers
|
Replace the Rio Oso 230/115 kV transformers (Nos. 1 and 2) with two 420 MVA rated transformers. Convert 115 kV bus to BAAH.
|
Jul-21
|
Rio Oso Area 230 kV Voltage Support
|
Install a new Static Var Compensator (SVC) at Rio Oso Substation and a new Shunt Capacitor at Atlantic Substation.
|
Feb-22
|
Martin 230 kV Bus Extension
|
Relocate the Jefferson-Martin 230 kV Line and one of the Martin-Embarcadero 230 kV Lines into a new 230 kV switchyard near Martin Substation.
|
Apr-22
|
Fulton 230/115 kV Transformer
|
This project proposes to install a 230/115 kV transformer at Fulton Substation rated for 420 MVA or higher.
|
May-22
|
Pittsburg 230/115 kV Transformer Capacity Increase
|
Install 3rd 230/115 kV Transformer at Pittsburg Substation with a rating of 420 MVA
|
May-22
|
Bellota – Warnerville 230 kV Line Reconductoring
|
Reconductor the Bellota – Warnerville 230 kV Line with a larger capacity conductor
|
Aug-22
|
Warnerville - Bellota 230 kV line reconductoring
|
Reconductor the Warnerville-Bellota 230 kV line
|
Aug-22
|
Gates No. 2 500/230 kV Transformer
|
Install a second 500/230/13.8 kV transformer (three single-phase units, 374 MVA each) at Gates Substation
|
Dec-22
|
Rio Oso – Atlantic 230 kV Line
|
Construct a second Rio Oso – Atlantic 230 kV Line.
|
Dec-22
|
Lockeford-Lodi Area 230 kV Development
|
Construct new 15 mile 230 kV DCTL from Eight Mile Substation to Lockeford Substation
|
Dec-22
|
Central Valley Power Connect aka Gates-Gregg 230 kV New Line
|
Build new DCTL (roughly 60 miles) of Gates-Gregg 230 kV line and upgrade substation equipment.
|
Dec-22
(on hold)
|
Midway-Andrew 230 kV
|
Upgrade existing 65 miles long Midway-Santa Maria 115KV line to 230kV
|
Jun-25
|
Midway-Kern PP 230 kV Line Nos. 1, 3 and 4 Capacity Increase Project
|
Replace limiting components at Kern PP and Midway Substations, to achieve full capacity on the Midway-Kern 230 kV Line Nos. 1, 3 and 4
|
Nov-26
|
PROJECT NAME
|
PROJECT DESCRIPTION
|
DATE IN SERVICE
|
Vaca Dixon - Lakeville 230 kV Reconductoring
|
Reconductor the Vaca – Lakeville No. 1, Tulucay – Vaca, and Tulucay – Lakeville 230 kV Lines with larger capacity conductors.
|
Cancelled
|
Tesla - Newark 230 kV Upgrade II
|
Reconductor limiting sections of Tesla - Newark 230 kV No. 2 with larger capacity conductors.
|
Cancelled
|
San Mateo Synchronous Condensor Replacement
|
Install reactive support device to replace old synchronous condensers at 115kV.
|
Cancelled
|
Moraga-Potrero 230 kV Project
|
Establish a 230 kV connection between Moraga and Potrero Substations.
|
Cancelled
|
Table 2
Planned Generation Interconnection Projects
Waiver of “Significant Transmission Project” Status Granted in 2014, 2015 and 20161
PROJECT NAME
|
PROJECT DESCRIPTION
|
DATE IN SERVICE
|
Tranquility Solar Generation Project
|
Interconnect a 200 megawatt (MW) (net output) of generation facility to a new PG&E owned 230 kV switching station that loops into PG&E’s Panoche – Helm and Panoche – Kearney 230 kV lines.
|
In Service
|
Panoche Valley Generation Interconnection Project
|
Interconnect a 240 MW (net output) of generation facility to a new PG&E owned 230kV switching station that loops into PG&E’s Moss Landing – Panoche and Coburn – Panoche 230 kV Lines. Construct a new 3 Bay, 8 breaker Switching station (BAAH)
|
Dec-17
|
Wright Solar Park
|
Interconnect a 200 MW (net output) solar-based generation facility to Los Banos – Panoche 230 kV Line No. 1 by looping in through a new PG&E-owned switching station. The new Switching Station is a 2-Bay, 5 Breaker 230 kV.
|
Feb-18
|
California Flats Solar Generation Interconnection Project
|
Interconnect 280 MW solar generation to Morro Bay - Gates 230 kV Line Number 2.
|
Jul-18
|
Oakley Generation Interconnection Project
|
To interconnect 651 MW of new generation, install a new 230 kV circuit breaker at Contra Costa Substation, install SPS at Contra Costa Substation, reconductor Contra Costa – Delta Pumps 230 kV Line, only east circuit, reconductor Las Positas – Newark 230 kV Line, only west circuit.
|
Project in suspension
|
(Dec-18)
|
Table 3
Planned Transmission Projects
Requesting Waiver of “Significant Transmission Project” Status
PROJECT NAME
|
PROJECT DESCRIPTION
|
DATE IN SERVICE
|
Bellota 230 kV Substation Shunt Reactor
|
Install 100 MVar Shunt Reactor at Bellota 230 kV Substation
|
Jan-19
|
Delevan 230 kV Substation Shunt Reactor
|
Install 200 MVar Shunt Reactor at Delevan 230 kV Substation
|
Feb-19
|
Los Esteros 230 kV Substation Shunt Reactor
|
Install 250 MVar Shunt Reactor at Los Esteros 230 kV
|
May-19
|
Ignacio 230 kV Substation Shunt Reactor
|
Install 150 MVar Shunt Reactor at Ignacio 230 kV Substation
|
Jun-20
|
Table 4
Planned Generation Interconnection Projects
Requesting Waiver of “Significant Transmission Project” Status
PROJECT NAME
|
PROJECT DESCRIPTION
|
DATE IN SERVICE
|
Q1032 / Tranquillity 8
|
The Project is a Photovoltaic generation and Battery Storage system with a total rated output of 200 MW to Pacific Gas and Electric Company’s (PG&E’s) 230kV Tranquillity BAAH Switchyard
|
Dec-17
|
Share with your friends: |