Phase 1 - Preparation
|
|
Participation in one conference in Brussels (3 days)
|
No later than 3 months after signing the contract.
|
Distribute all written communication from the working group through CIRCABC
|
During phase 1.
|
Finalise
- curricula
- lesson templates (structure, degree of detail and taxonomy corresponding to the course descriptions).
|
No later than four months after the signature of the contract.
|
Upload one page written updates on CIRCABC on progress
|
Every three weeks during phase 1.
|
Store all documentation of the preparation process in CIRCABC
|
During phase 1.
|
Send material for the preparation and testing tool to contractor of Lot 8
|
Latest two months before the start of the new training cycle
|
Phase 2 - Planning
|
|
Store all documentation of the planning process on CIRCABC and send one paper copy to the Commission
|
During phase 2.
|
Send final course schedule for approval to the Commission
|
Latest two months before the start of the new training cycle
|
Send planning of the upcoming course cycle to the Commission for approval.
|
On request of the Commission.
|
Phase 3 - Personnel, Documentation, participants, venue, travel, etc.
|
Upload electronic version of the binder content in CIRCABC
|
Latest two weeks before the first course day.
|
Implementing of the course
|
On the approved course date.
|
Offer participants a printed version of the different lessons, exercises and syndicate work sessions.
|
First day of each course.
|
Provide a hand-out for the respective presentation.
|
Before a presentation starts.
|
Provide access to an electronic version of the course material to participants.
|
At the end of the course.
|
Phase 5 – Evaluation, Reports
|
|
Mid-term report
|
At the latest eight weeks after the reporting period.
|
Participate in coordination/evaluation meetings
|
Up to three times per year.
|
Peer review
|
Once per course cycle
|
Participate in National Training Coordinators meeting (1½ days)
|
One per year
|
Final Consolidated Report
|
At the latest eight weeks after the last day of the last training course per cycle.
|
Phase 1 - Preparation, personnel and design
|
Kick-off planning meeting in Brussels providing an outline of planning to the Commission
(1 day)
|
No later than 2 months after signing the contract.
|
Participation in one conference in Brussels (3 days)
|
No later than 3 months after signing the contract.
|
Distribute all written communication from the working group through CIRCABC
|
During phase 1.
|
Store all documentation of the planning process in CIRCABC
|
During phase 1.
|
Delivery of preliminary version of the tool to the Commission for approval
|
Latest 4 months after signature of the contract
|
Delivery of tool with newly developed structure and content to the Commission for approval
|
Latest 12 months after signature of the contract
|
Phase 2 - Testing
|
|
Internal test phase 1 completed
|
Latest 4 months after signature of the contract
|
Internal test phase 2 completed
|
Latest 10 months after signature of the contract
|
External testing phase 2 completed
|
Latest 11 months after signature of the contract
|
Phase 3 - Operation
|
|
Tool fully operational 1st level
Tool fully operational 2nd level
|
Before start of the 14th course cycle (planned May/June 2016)
1 January 2017
|
Phase 4 – Maintenance
|
|
Update of the content
|
At least twice a year or at any major change
|
Report updates to the Commission
|
Once a year before start of the upcoming course cycle, starting after the first test.
|
Phase 5 - Handover
|
|
Handover
|
End of contract
|
Phase 6 – Final Meeting & final consolidated report
|
Participation in final lessons learnt meeting in Brussels and presentation of the delivery of the project
|
End of contract
|
Final consolidated report
|
At the latest eight weeks after the last day of the last training course.
|