Turkey sector Operational Programme Environment and Climate Change


ANNEX III: Indicative Main List of Major Projects - Water



Download 1.49 Mb.
Page18/19
Date19.10.2016
Size1.49 Mb.
#4548
1   ...   11   12   13   14   15   16   17   18   19

ANNEX III: Indicative Main List of Major Projects - Water

Major Project No:

1

Project title:

Erzurum Drinking Water Supply Project

Brief description of its aim and intended results:

The project package for Erzurum Drinking Water Project comprises the following components to be implemented in the period 2014 to 2017.

    • Construction of a new water distribution network

    • Technical Assistance for the supervision of construction works to ensure the quality of the construction works.

Project value and funding sources:

Approximately EUR 36 million

Sources of Funding:

Implementation period:

2 years + DNP

Stage of preparation:

Master Plan, Draft IPA AF, Draft FS, Draft Tender Documents have been prepared by on-going Technical Assistance and Supervision Consultant of Erzurum Wastewater Project.


ANNEX III: Indicative Reserve List of Major Projects - Water

Major Project No:

1

Project title:

Yüksekova Integrated Water Project

Brief description of its aim and intended results:

Project Components will cover the following elements:

  • Construction of Stage 1 of sewerage network Waste Water Treatment Plant (WWTP) 1stPhase

  • Replacement of storage reservoirs and installation of disinfection

  • Construction of Stage 1 of water supply network to all developed areas

  • Rehabilitation of wells

  • Provision of Combination Trucks (Suction/Jetting) CCTV and leak detection equipment

  • Provision of Integrated GIS/MIS systems & Hydraulic Sewer and water supply model (hardware/software/training)

  • Implementation of capacity building and supervision of construction works

Project value and funding sources:

EUR 50 million

Sources of Funding:

  • EU IPA Grant Funds

  • National Sources

Implementation period:

2 years + DNP

Stage of preparation:

Draft Master Plan has been prepared in the scope of TA to prepare integrated water projects.



Major Project No:

2

Project title:

Şırnak Integrated Water Project

Brief description of its aim and intended results:

Project Components will cover the following elements:

  • Construction of new network and transmission lines between reservoirs

  • Rehabilitation of existing reservoirs and pumping stations, construction of new reservoirs

  • Construction of 1st phase WWTP

  • Construction of sewerage

  • Provision of meters, combination trucks, CCTV equipment, GIS/MIS systems and hydraulic sewer model

  • Implementation of capacity building and supervision of construction works

Project value and funding sources:

EUR 39 million

Sources of Funding:

  • EU IPA Grant Funds

  • National Sources

Implementation period:

2 years + DNP

Stage of preparation:

Draft Master Plan has been prepared in the scope of TA to prepare integrated water projects.




Major Project No:

3

Project title:

Rize Integrated Water Project

Brief description of its aim and intended results:

Project Components will cover the following elements:

  • Construction of new network and transmission lines between reservoirs

  • Construction of new water storage facilities

  • Rehabilitation of existing reservoirs and pumping stations, construction of new reservoirs

  • Construction of Sea Outfall Facility and collectors

  • Construction of sewerage network and main collector lines

  • Construction of stormwater network

  • Provision of meters, combination trucks, CCTV equipment, GIS/MIS systems and hydraulic sewer model

  • Implementation of capacity building and supervision of construction works

Project value and funding sources:

EUR 89 million

Sources of Funding:

  • EU IPA Grant Funds

  • National Sources

Implementation period:

2 years + DNP

Stage of preparation:

Draft Master Plan has been prepared in the scope of TA to prepare integrated water projects.




Major Project No:

4

Project title:

Giresun Integrated Water Project

Brief description of its aim and intended results:

Project Components will cover the following elements:

  • Construction and rehabilitation of network and transmission lines between reservoirs

  • Construction of water transmission lines

  • Construction of sewerage network and main collector lines

  • Rehabilitation of Sea Outfall Facility

  • Construction of stormwater network

  • Rehabilitation of pumping stations

  • Provision of meters, combination trucks, CCTV equipment, GIS/MIS systems and hydraulic sewer model

  • Implementation of capacity building and supervision of construction works

Project value and funding sources:

EUR 79 million

Sources of Funding:

  • EU IPA Grant Funds

  • National Sources

Implementation period:

2 years + DNP

Stage of preparation:

Draft Master Plan has been prepared in the scope of TA to prepare integrated water projects.



Major Project No:

5

Project title:

Iğdır Integrated Water Project

Brief description of its aim and intended results:

Project Components will cover the following elements:

  • Construction of water transmission lines

  • Construction of sewerage network and main collector lines

  • Construction of new WWTP

  • Construction of stormwater network

  • Provision of meters, combination trucks, CCTV equipment, GIS/MIS systems and hydraulic sewer model

  • Implementation of capacity building and supervision of construction works

Project value and funding sources:

EUR 46 million

Sources of Funding:

  • EU IPA Grant Funds

  • National Sources

Implementation period:

2 years + DNP

Stage of preparation:

Draft Master Plan has been prepared in the scope of TA to prepare integrated water projects.



Major Project No:

6

Project title:

Niksar Integrated Water Project

Brief description of its aim and intended results:

Project Components will cover the following elements:

Drinking Water:

  • Construction of water network

  • Construction of storage tanks

  • Construction of a pumping station

  • Rehabilitation of a pumping station

  • Construction of main transmission lines

Waste Water:

  • Construction of main collector lines

  • Construction of new WWTP

  • Construction of storm water network

  • Construction of sewerage water network

  • Construction of pumping stations

Project value and funding sources:

EUR 36 million

Sources of Funding:

  • EU IPA Grant Funds

  • National Sources

Implementation period:

2 years + DNP

Stage of preparation:

IPA Application and draft Master Plan has been prepared in the scope of TA to prepare integrated water projects.



Major Project No:

7

Project title:

Kırıkhan Integrated Water Project

Brief description of its aim and intended results:

Project Components will cover the following elements:

Drinking Water:

  • Rehabilitation of water network

  • Construction of main transmission lines

Waste Water:

  • Construction of WWTP

  • Construction of storm water network

  • Construction of sewerage network

Project value and funding sources:

EUR 42 million

Sources of Funding:

  • EU IPA Grant Funds

  • National Sources

Implementation period:

2 years + DNP

Stage of preparation:

IPA Application and draft Master Plan has been prepared in the scope of TA to prepare integrated water projects.




Major Project No:

8

Project title:

Kastamonu Integrated Water Project

Brief description of its aim and intended results:

Project Components will cover the following elements:

Drinking Water:

  • Construction of water network

  • Construction and rehabilitation of water storage tanks

  • Construction of transmission lines

  • Construction of main transmission lines

  • SCADA system

Waste Water:

  • Construction of new WWTP

  • Construction of sewerage water network

  • Construction of a pumping station

Project value and funding sources:

EUR 85 million

Sources of Funding:

  • EU IPA Grant Funds

  • National Sources

Implementation period:

2 years + DNP

Stage of preparation:

IPA Application and draft Master Plan has been prepared in the scope of TA to prepare integrated water projects.




Major Project No:

9

Project title:

Bandırma Integrated Water Project

Brief description of its aim and intended results:

Project Components will cover the following elements:

Drinking Water:

  • Rehabilitation of water network

  • Construction of water storage tanks

  • Construction of pumping station

  • Construction of main transmission lines

  • SCADA system

Waste Water:

  • Construction of main collector lines

  • Construction of new WWTP

  • Construction of storm water network

  • Construction of sewerage water network

  • Construction of pumping stations

Project value and funding sources:

EUR 91 million

Sources of Funding:

  • EU IPA Grant Funds

  • National Sources

Implementation period:

2 years + DNP

Stage of preparation:

IPA Application and draft Master Plan has been prepared in the scope of TA to prepare integrated water projects.




Major Project No:

10

Project title:

Çankırı Integrated Water Project

Brief description of its aim and intended results:

Project Components will cover the following elements:

  • Construction and rehabilitation of network and transmission lines between reservoirs

  • Construction of water transmission lines

  • Construction of sewerage network and main collector lines

  • Construction of new WWTP

  • Construction of stormwater network

  • Provision of meters, combination trucks, CCTV equipment, GIS/MIS systems and hydraulic sewer model

  • Implementation of capacity building and supervision of construction works

Project value and funding sources:

EUR 56 million

Sources of Funding:

  • EU IPA Grant Funds

  • National Sources

Implementation period:

2 years + DNP

Stage of preparation:

Draft Master Plan has been prepared in the scope of TA to prepare integrated water projects.