ANNEX III: Indicative Main List of Major Projects - Water
Page 18/19 Date 19.10.2016 Size 1.49 Mb. #4548
ANNEX III: Indicative Main List of Major Projects - Water
Major Project No:
1
Project title:
Erzurum Drinking Water Supply Project
Brief description of its aim and intended results:
The project package for Erzurum Drinking Water Project comprises the following components to be implemented in the period 2014 to 2017.
Construction of a new water distribution network
Technical Assistance for the supervision of construction works to ensure the quality of the construction works.
Project value and funding sources:
Approximately EUR 36 million
Sources of Funding:
Implementation period:
2 years + DNP
Stage of preparation:
Master Plan, Draft IPA AF, Draft FS, Draft Tender Documents have been prepared by on-going Technical Assistance and Supervision Consultant of Erzurum Wastewater Project.
ANNEX III: Indicative Reserve List of Major Projects - Water
Major Project No:
1
Project title:
Yüksekova Integrated Water Project
Brief description of its aim and intended results:
Project Components will cover the following elements:
Construction of Stage 1 of sewerage network Waste Water Treatment Plant (WWTP) 1stPhase
Replacement of storage reservoirs and installation of disinfection
Construction of Stage 1 of water supply network to all developed areas
Rehabilitation of wells
Provision of Combination Trucks (Suction/Jetting) CCTV and leak detection equipment
Provision of Integrated GIS/MIS systems & Hydraulic Sewer and water supply model (hardware/software/training)
Implementation of capacity building and supervision of construction works
Project value and funding sources:
EUR 50 million
Sources of Funding:
EU IPA Grant Funds
National Sources
Implementation period:
2 years + DNP
Stage of preparation:
Draft Master Plan has been prepared in the scope of TA to prepare integrated water projects.
Major Project No:
2
Project title:
Şırnak Integrated Water Project
Brief description of its aim and intended results:
Project Components will cover the following elements:
Construction of new network and transmission lines between reservoirs
Rehabilitation of existing reservoirs and pumping stations, construction of new reservoirs
Construction of 1st phase WWTP
Construction of sewerage
Provision of meters, combination trucks, CCTV equipment , GIS/MIS systems and hydraulic sewer model
Implementation of capacity building and supervision of construction works
Project value and funding sources:
EUR 39 million
Sources of Funding:
EU IPA Grant Funds
National Sources
Implementation period:
2 years + DNP
Stage of preparation:
Draft Master Plan has been prepared in the scope of TA to prepare integrated water projects.
Major Project No:
3
Project title:
Rize Integrated Water Project
Brief description of its aim and intended results:
Project Components will cover the following elements:
Construction of new network and transmission lines between reservoirs
Construction of new water storage facilities
Rehabilitation of existing reservoirs and pumping stations, construction of new reservoirs
Construction of Sea Outfall Facility and collectors
Construction of sewerage network and main collector lines
Construction of stormwater network
Provision of meters, combination trucks, CCTV equipment, GIS/MIS systems and hydraulic sewer model
Implementation of capacity building and supervision of construction works
Project value and funding sources:
EUR 89 million
Sources of Funding:
EU IPA Grant Funds
National Sources
Implementation period:
2 years + DNP
Stage of preparation:
Draft Master Plan has been prepared in the scope of TA to prepare integrated water projects.
Major Project No:
4
Project title:
Giresun Integrated Water Project
Brief description of its aim and intended results:
Project Components will cover the following elements:
Construction and rehabilitation of network and transmission lines between reservoirs
Construction of water transmission lines
Construction of sewerage network and main collector lines
Rehabilitation of Sea Outfall Facility
Construction of stormwater network
Rehabilitation of pumping stations
Provision of meters, combination trucks, CCTV equipment, GIS/MIS systems and hydraulic sewer model
Implementation of capacity building and supervision of construction works
Project value and funding sources:
EUR 79 million
Sources of Funding:
EU IPA Grant Funds
National Sources
Implementation period:
2 years + DNP
Stage of preparation:
Draft Master Plan has been prepared in the scope of TA to prepare integrated water projects.
Major Project No:
5
Project title:
Iğdır Integrated Water Project
Brief description of its aim and intended results:
Project Components will cover the following elements:
Construction of water transmission lines
Construction of sewerage network and main collector lines
Construction of new WWTP
Construction of stormwater network
Provision of meters, combination trucks, CCTV equipment, GIS/MIS systems and hydraulic sewer model
Implementation of capacity building and supervision of construction works
Project value and funding sources:
EUR 46 million
Sources of Funding:
EU IPA Grant Funds
National Sources
Implementation period:
2 years + DNP
Stage of preparation:
Draft Master Plan has been prepared in the scope of TA to prepare integrated water projects.
Major Project No:
6
Project title:
Niksar Integrated Water Project
Brief description of its aim and intended results:
Project Components will cover the following elements:
Drinking Water:
Construction of water network
Construction of storage tanks
Construction of a pumping station
Rehabilitation of a pumping station
Construction of main transmission lines
Waste Water:
Construction of main collector lines
Construction of new WWTP
Construction of storm water network
Construction of sewerage water network
Construction of pumping stations
Project value and funding sources:
EUR 36 million
Sources of Funding:
EU IPA Grant Funds
National Sources
Implementation period:
2 years + DNP
Stage of preparation:
IPA Application and draft Master Plan has been prepared in the scope of TA to prepare integrated water projects.
Major Project No:
7
Project title:
Kırıkhan Integrated Water Project
Brief description of its aim and intended results:
Project Components will cover the following elements:
Drinking Water:
Rehabilitation of water network
Construction of main transmission lines
Waste Water:
Construction of WWTP
Construction of storm water network
Construction of sewerage network
Project value and funding sources:
EUR 42 million
Sources of Funding:
EU IPA Grant Funds
National Sources
Implementation period:
2 years + DNP
Stage of preparation:
IPA Application and draft Master Plan has been prepared in the scope of TA to prepare integrated water projects.
Major Project No:
8
Project title:
Kastamonu Integrated Water Project
Brief description of its aim and intended results:
Project Components will cover the following elements:
Drinking Water:
Construction of water network
Construction and rehabilitation of water storage tanks
Construction of transmission lines
Construction of main transmission lines
SCADA system
Waste Water:
Construction of new WWTP
Construction of sewerage water network
Construction of a pumping station
Project value and funding sources:
EUR 85 million
Sources of Funding:
EU IPA Grant Funds
National Sources
Implementation period:
2 years + DNP
Stage of preparation:
IPA Application and draft Master Plan has been prepared in the scope of TA to prepare integrated water projects.
Major Project No:
9
Project title:
Bandırma Integrated Water Project
Brief description of its aim and intended results:
Project Components will cover the following elements:
Drinking Water:
Rehabilitation of water network
Construction of water storage tanks
Construction of pumping station
Construction of main transmission lines
SCADA system
Waste Water:
Construction of main collector lines
Construction of new WWTP
Construction of storm water network
Construction of sewerage water network
Construction of pumping stations
Project value and funding sources:
EUR 91 million
Sources of Funding:
EU IPA Grant Funds
National Sources
Implementation period:
2 years + DNP
Stage of preparation:
IPA Application and draft Master Plan has been prepared in the scope of TA to prepare integrated water projects.
Major Project No:
10
Project title:
Çankırı Integrated Water Project
Brief description of its aim and intended results:
Project Components will cover the following elements:
Construction and rehabilitation of network and transmission lines between reservoirs
Construction of water transmission lines
Construction of sewerage network and main collector lines
Construction of new WWTP
Construction of stormwater network
Provision of meters, combination trucks, CCTV equipment, GIS/MIS systems and hydraulic sewer model
Implementation of capacity building and supervision of construction works
Project value and funding sources:
EUR 56 million
Sources of Funding:
EU IPA Grant Funds
National Sources
Implementation period:
2 years + DNP
Stage of preparation:
Draft Master Plan has been prepared in the scope of TA to prepare integrated water projects.
Share with your friends:
The database is protected by copyright ©ininet.org 2024
send message