In this part of the report, prevention and improvement plans are given against possible impacts of activities to be carried out in construction and operation stages. In the prevention and improvement plan, possible impacts are itemized for construction and operation stages. For each specified impact, measures to be taken, responsible organization, stakeholders and relevant legislation. Information giving Prevention and Improvement Plans are given in Table 3 .4, Table 3 .5 and Table 3 .6 for the construction stage and in Table 3 .7, Table 3 .8 for the operation stage. Relevant tables define the measures to be taken against possible risk factors, responsible organization relating the measures, stakeholders that may be affected and the legislation about the subject matter. How these measures should be implemented according to legislation is given in Section 3.3.1.
Table 3.4 Prevention and Improvement Plan in the Construction Stage
Subject
|
Measures to be Taken
|
Responsible Organization
|
Stakeholders
|
Relevant Legislation
|
Excavation waste
|
Excavation waste from the excavation work will be used as filling material. Environmental measures will be taken for temporary storage areas via site planning. Balecloth covering and bordering with plastic lines will be done on and around the excavation waste.
|
Contractor
|
Neighborhood Population, NGO's
|
Regulation for Control of Excavation Soil, Construction and Demolition Waste
|
Used pipe waste
|
Old pipes from replacement of the network will be disposed in solid waste landfill. (Please refer to the Asbestos Cement Pipes (ACP) Section below.)
|
Contractor
|
Neighborhood Population, NGO's
|
Reg. for Cont. of Excavation Soil, Construction and Demolition Waste (date 18.03.2004, no. RG 25406)
|
Historic, cultural and archeological assets
|
If any asset of historic, cultural or archeological value is found in excavations, Directorate of Provincial Culture and Tourism will be informed and works will stop. No work will continue until agreement and permission to do so is granted by this Directorate. Precautions will be taken for preventing the removal of artifacts by workers. Security camera and a security person will be in service in case of a finding.
|
Contractor
|
Neighborhood Population, NGO's, Directorate of Provincial Culture
|
Law of Protection of Cultural and Natural Assets no 2863
|
Dust/air pollution
|
Vehicles carrying material will be covered on the top. Working site will be wetted especially in warm, dry and windy weather.
|
Contractor
|
Neighborhood Population, NGO's
|
Reg. for Cont. of Air Pollution Caused by Industrial Plants
|
Table 3.5 Prevention and Improvement Plan in the Construction Stage (cont'd)
Subject
|
Measures to be Taken
|
Responsible Organization
|
Stakeholders
|
Relevant Legislation
|
Noise pollution
|
Noise levels of excavation and working machines operation at construction cannot exceed the level stated in the "Regulation for Assessment and Management of Environmental Noise". (Impact noise Lcmax cannot exceed 100 dBC.) Construction activities will be performed between 07.00-19.00 hours. Since the construction will be executed in three separate stages, generation of collective noise will be relatively avoided. In case when the construction activities must continue at night, local population that will be affected will be informed at least one week before the activity date.
|
Contractor
|
Neighborhood Population, NGO's
|
Regulation for Assessment and Management of Environmental Noise / Vibration Regulation
|
Exhaust fumes
|
During construction, each vehicle related with the construction will be checked and inspected with "Motor Vehicle Exhaust Emission Measurement License" to see whether the Exhaust Measurements are made in accordance with the criteria specified by the Ministry of Environment and Forestry
|
Contractor
|
Neighborhood Population, NGO's
|
Regulation for Control of Exhaust Gas Emissions of Vehicles in the Traffic
|
Excavation
|
In order not to damage other infrastructural works, relevant organizations and institutions (water, natural gas, sewerage, communication, transportation) will be informed in written before the start of excavation. Necessary institutional permits will be obtained.
|
Contractor
|
Neighborhood Population, NGO's Municipalities Police Directorate
|
Regulation for Infrastructure Coordination Centers of Municipalities
|
Public safety
|
In order that the project will not create any danger for public safety (particularly to children), entry of people to the construction site should be prevented by placing plastic bands, barriers, phosphorous and illuminated warning signs. Additionally, necessary measures will be taken with relevant institutions to ensure the safe traffic flow. Polices traffic department will be informed and their service will be in use during constructions.
|
Contractor
|
Neighborhood Population, NGO's Municipalities Police Directorate
|
Regulation for Health and Safety in Construction Works
|
Table 3.6 Prevention and Improvement Plan in the Construction Stage (cont'd)
Worker dwellings
|
Worker dwellings will be constructed in a safe distance (min. 30 m.) from the construction site. All equipments for workers’ daily rations will be provided.
|
Contractor
|
Workers, Neighborhood Population, Municipalities,NGO’s
|
Regulation for Health and Safety in Construction Works
|
Access Roads
|
Road and traffic arrangements for construction equipments and trucks will be planned and applied. These will be planned by the contractor until the end of construction.
|
Contractor
|
Neighborhood Population,NGO’s, Municipalities, Police Directorate
|
Regulation for Highway Traffic
|
Asbestos Cement Pipes (ACP)
|
Workers will use masks during the carriage, replacement, temporary and final landfilling works. The necessary isolation barriers will be provided around the body of waste. Especially all the asbestos material will be kept wet at all times.
|
Contractor
|
Workers, Neighborhood Population, Municipalities, NGO’s
|
Regulation for Health and Safety in Construction Works
|
Construction site restoration
|
At the end of construction, the site will be rehabilitated and the construction site will be reinstated.
|
Contractor
|
Neighborhood Population, NGO's Municipalities
|
Regulation for Environmental Inspection
|
Disasters and accidents
|
Immediate response plans will be established- for damage, stealing, etc. events that may happen in valve rooms and pipes and reservoirs. This management plan will be prepared by contractor before the operation begins. This plan will be reviewed and approved by municipalities disaster management expert.
|
Elbistan Municipality
|
Neighborhood Population, NGO's Municipalities
|
Disaster Regulation for Infrastructures
|
Safety of water structures
|
Necessary monitoring and inspection measures will be taken against possibility of a sabotage to public health at points of reservoirs, pumping stations and valve rooms. Security personnel will controlling critical points stated above.
|
Elbistan Municipality
|
Neighborhood Population, NGO's Municipalities
|
Disaster Regulation for Infrastructures
|
Measuring the Water Quality Periodically
|
Flow and analysis parameters of water quality will be measured periodically. Necessary intervention equipment will be provided.
|
Elbistan Municipality
|
Neighborhood Population, NGO's Municipalities
|
Reg. for Water of Human Consumption Purpose
|
Safety of Disinfectant Tanks
|
Disinfectant tanks will be appropriate for chemical storage Chlorine will be used as disinfectant. Ventilation and discharge mechanisms will be provided to prevent leakages and gas accumulations. Tanks will be assembled special rooms. Special clothes for emergency actions will be provided.
|
Elbistan Municipality
|
Workers, Neighborhood Population, NGO’s, Municipalities
|
Reg. of urban and rural water supply of Bank of Provinces Water Supply Project(22.04.1985, no 18733)
|
Consequently, measures to be taken must be strictly applied to minimize environmental impacts to be caused by the project. Risks of activities to be carried out under the project may be effectively managed by taking the Prevention and Improvement Plan as the basis in tender, implementation and operation processes.